PAST RECORDS ● Aggregate approval/test results. ● Bitumen approval/test results. ● Mix design approval (including trial lay). ● Binder content, aggregate gradation & Marshall test results. Satu (1) ujian setiap 200 tan asphalt.
2
BITUMEN ● Source of bitumen approved.
M
3
Bitumen diuji sepenuhnya di ‘independent lab’ berdasarkan MS 124 dan semua keputusan ujian ‘lulus’.
AGGREGATES ● Source of coarse aggregate approved.
M
Agregat kasar diuji sepenuhnya di ‘independent lab’ berdasarkan JKR/SPJ/1988 atau JKR/SPJ/2008 dan semua keputusan ujian ‘lulus’.
● Source of fine aggregate approved. M
Agregat halus diuji sepenuhnya di ‘independent lab’ berdasarkan JKR/SPJ/1988 atau JKR/SPJ/2008 dan semua keputusan ujian ‘lulus’.
M
● Each aggregate is stored in a separate stockpile.
M
● Stockpile of fine aggregate is kept under a waterproof roof structure.
4
MIX DESIGN ● Mix design prepared and approved by KPPS/JD.
M
Laporan rekabentuk campuran hendaklah disertakan dengan kelulusan bitumen dan agregat di atas.
5
LABORATORY TEST EQUIPMENT
M
● Is a laboratory available?
M
● Is the laboratory capable to carry out the following tests? Bitumen content.
M
Aggregate gradation.
M
Thickness.
M
Density.
M
● Equipped with the following laboratory test equipment; Penetration.
M
Ring & Ball Softening Point.
M
Flash Point.
YES
NO
PINDAAN 3/2013 2
No.
ACTIVITIES ● Equipped with laboratory test equipment to determine binder content of bituminous tack coat (i.e. grade of tack coat).
M
Kuari mestilah menyediakan tiga (3) beaker berisipadu 1 liter (low form) dan tiga (3) glass rod selain oven dan balance walaupun tidak membekalkan tack coat dan menjalankan kerja paving.
M
● Have laboratory test equipment been checked and certified/calibrated (annually)? Date checked …………. Certified by ……………. Is copy of certification/calibration available?
6
QC SYSTEM ● QC system is available. ● Competent quality officer is available.
PLANT OPERATIONS 7
COLD FEED BINS ● Cold feed system shall consist of not less than 5 bins with suitable capacity.
M
● Each aggregate is stored in a separate cold bin.
M
● No spill over of aggregates into adjacent bins. ● Each bin is equipped with a control gate and measuring feeder for accurate blending of aggregates on to cold feed collecting conveyor. ● Cold feed system shall incorporate a device for moisture compensation capable of producing an accurate and continuous blend of aggregates from the cold feed bins. ● Separate dry storage is provided for mineral filler.
M
● Equipped with a screen of size ≤ 50 mm to discard oversized aggregates before entering the drum mixer.
8
DRUM MIXER ● Drum mixer shall be inclined, oil-fired and sufficiently insulated. ● Samples of aggregates can be obtained before entering the drum mixer eg. from the link conveyor. ● Fresh mixed asphalt is delivered and stored in a surge silo through a proper conveyor system.
9
M M
PLANT SETTING ● Computer able to display details of mixing proportion (and flow rate) according to approved mix design, and mix temperatures. ● The accuracy of aggregates, filler and bitumen flow rates have been checked and verified. ● Print out of recent mix production (< 1 month) which shows the aggregates, filler and bitumen tonnages is available. ● The accuracy of the plant setting as displayed on the computer screen have been checked and verified.
YES
NO
PINDAAN 3/2013 3
No.
ACTIVITIES
10
YES
NO
BITUMEN STORAGE TANK ● Have means of indicating the volume of bitumen at all times. ● Have means of drawing off samples. ● Provides for continuous circulation of hot bitumen through the bitumen feeding system and back into the bitumen storage tank. ● The end of the return line discharging into the bitumen storage tank shall be kept submerged in the bitumen to prevent oxidation of the returning hot bitumen. ● A thermometer is fitted to the bitumen storage tank or bitumen feed line. ● Have thermometers been checked and certified/calibrated (annually)? Date checked …………. Certified by ……………. Is copy of certification/calibration available? ● Bitumen storage tank and bitumen feeding system are equipped with heating system and insulating jackets.
M
M
M
11
LORRY TRANPORTER SCALES
M
● Has weigh bridge been checked and certified/calibrated (annually)? Date checked …………. Certified by ……………. Is copy of certification/calibration available?
Note: M – Mandatory Remarks:……………………………………………………………………………………………… ……………………………………………………………………………………..……..…………….. ………………………………………………………………………………………………………….
Is the plant qualified to produce asphalt for use in JKR paving works? YES
NO
Nota: i) YES – semua item mandatori DIPATUHI dan minimum 50% daripada item bukan mandatori LULUS. ii) NO – mana-mana item mandatori TIDAK DIPATUHI atau minimum 50% daripada item bukan mandatori GAGAL.
Auditor:
Auditee:
……………………………………………
……………………………………………
(Name: …………………………………) (Organisation: …………………………) Head of Audit Team