15.2.1-Interface Management Plan_ R3

September 24, 2017 | Author: Kelly Bates | Category: Road Surface, General Contractor, Interface (Computing), Building Engineering, Industries
Share Embed Donate


Short Description

Interface Plan for Construction Project...

Description

SADARA PROJECT LSPB CONTRACT TECHNICAL DATA BOOK ATTACHMENT IV TO SCHEDULE B 15.2.1 BUILD INTERFACE MANAGEMENT PLAN Document No: A554-R-730-IN-GEN-INT-001 RTIP Rev:

1

2

3

FW Prepared by:

Majid M Alghamdi

Majid M Alghamdi

Majid M Alghamdi

FW Approved by:

Mike Dowden

Mike Dowden

Mike Dowden

Owner Approved by:

Daniel Abanto

Daniel Abanto

Daniel Abanto

Revision Date:

11 July 2012

28 Aug 2012

10 Sept 2012

Issue Purpose:

ITB

IFT

IFT

3

This document contains technical information that may be subject to the export control regulations of the United States and/or other jurisdictions. It may not be exported or reexported except as authorized under applicable U.S. or other export control regulations.

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: Tender

SUMMARY OF DOCUMENT REVISIONS Rev. No.

Date Revised

Section Revised

1

3 July-12

2

28 Aug-12

Attachment 2

Interface Dependency Table Update

3

10-Sept-12

Attachment 2

Interface Dependency Table Update

Revision Description Issued for Client Review

Contains Confidential Information of Both Dow and Saudi Aramco Page 2 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: Tender

TABLE OF CONTENTS

Section

Topic

1.0

PURPOSE ................................................................................................................ 4

2.0

SCOPE ..................................................................................................................... 4

3.0

DEFINITIONS ........................................................................................................... 4

4.0

RESPONSIBILITIES ................................................................................................ 5

4.1

INTERFACE PARTIES ............................................................................................ 6

4.2

CONTRACTOR F ..................................................................................................... 6

4.3

CONTRACTOR O .................................................................................................... 7

4.4

PROGRAM INTERFACE MANAGEMENT TEAM (PIMT) ....................................... 8

5.0

INTERFACE TYPES ................................................................................................ 8

5.1

EXTERNAL INTERFACE ......................................................................................... 8

5.2

INTERNAL INTERFACE .......................................................................................... 9

6.0

INTERFACE NUMBERING ...................................................................................... 9

7.0

COMMUNICATION ................................................................................................ 10

7.1

INTERFACE QUERIES (IQS) ................................................................................ 11

7.2

IQ NUMBERING ..................................................................................................... 11

7.3

TRANSMISSION OF DOCUMENTATION ............................................................. 11

8.0

INTERFACE GUIDELINES .................................................................................... 11

8.1

PIPING ................................................................................................................... 12

8.1.1

ABOVE GROUND PIPING INTERFACES ............................................................. 12

8.1.2

UNDERGROUND PIPING INTERFACES .............................................................. 12

8.2

CIVIL INTERFACES .............................................................................................. 13

8.2.1

ROAD INTERFACE ............................................................................................... 13

8.2.2

PAVING INTERFACES .......................................................................................... 14

8.2.3

DITCH INTERFACES ............................................................................................. 14

8.2.4

TELECOMMUNICATION CONCRETE ENCASED DUCT BANKS....................... 15

8.3

TELECOMMUNICATIONS ..................................................................................... 16

8.4

ELECTRICAL ......................................................................................................... 16

ATTACHMENT 1 – IQ GUIDELINES ................................................................................... 17 ATTACHMENT 2 – INTERFACE DEPENDENCY TABLE................................................... 19

Contains Confidential Information of Both Dow and Saudi Aramco Page 3 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Contains Confidential Information of Both Dow and Saudi Aramco Page 4 of 31

Issue Purpose: Tender

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

1.0

Issue Purpose: Tender

PURPOSE This document defines how interfaces are to be managed by the Packages Contractors. It defines the role and responsibilities of each interface Party. It does not define the engineering requirements of each interface. This document is intended to: • • • • •

2.0

Ensure all interfaces are identified Define clear responsibilities for each Party Ensure there are no interface gaps or overlaps Define the physical method of making the interface (flange, junction box, etc) Ensure schedule compatibility, relating to interfaces

SCOPE This document defines the requirements for the management of interfaces during construction phase The physical interface definition includes the following connections: • • • •

3.0

Piping (above and underground) Civil (roads, paving, ditches, ducts) IT/Telecoms Electric power cable and Control Cable

DEFINITIONS

Title

Definition

BL

Battery limit

Contractor “Package A, B, C, Or D Contractor”

The SDL Building Project is divided into four Packages, A, B,C and D. Each Package will be constructed by a Package contractor

Package contractor

The Contractor responsible for Construction of a Package.

Finalization Contractor “Contractor F”

Contractor F effectively will accept the works of Contractor O and will complete the Interface Point works. Contractor F will maintain responsibility for the Interface Point until construction turnover.

Originator Contractor “ Contractor O”

Contractor O is the Contractor who initiates the works at an IP. Contractor O will provide Contractor F the required support to allow Contractor F to complete the works at subject interface point.

Contains Confidential Information of Both Dow and Saudi Aramco Page 5 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: Tender

3rd Party contractor

Contractors nominated for works outside of the building battery limit or not included in Contractor A,B,C& D scope of work

ICF

Interconnecting Facilities Contractor

ITC

Information Technology Contractor

EW

Early Work Contractor

IDT

Interface Dependency Table

External Interface

External Interface is an interface between any Package Contractor and a third party contractor e.g. between Package C Contractor and ICF Contractor

Internal Interface

An Internal Interface is an interface between any two Package Contractors

IP

Interface Point

IQ

Interface Query

ISBL

Inside Battery Limit. A category of work scope for facilities inside a process Unit BL

OSBL

Outside Battery Limits. Outside the Process Unit BL but within the Site boundary

PMT

Project Management Team

SPOC

Single Point of Contact

4.0

RESPONSIBILITIES This section outlines the respective responsibilities of the Project Management Team and the Packages Contractors. Package Contractors are wholly responsible for the completion of all Interface Points within the parameters of the contract price. Package Contractor shall be responsible to communicate with any other Package Contractor as required to complete all works relating to the Interface Points. Package Contractor shall also be responsible for all documentation and communication with the PMT. The following is the general frame of responsibilities I.

PMT will: Oversee the interface process and nominate contractor (F) Finalization Contractor or (O) Originator Contractor in each IP.

II.

It is the responsibility of a Package Contractors to coordinate with the other Package Contractors to establish schedule of activities at each Interface Point (IP). Agreeing to the sequence of activities, and finalizing the proper sign off and required testing for each (IP) based

Contains Confidential Information of Both Dow and Saudi Aramco Page 6 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: Tender

on the role they will be assigned to as an Originator contractor Or Finalization contractor.

4.1

III.

Contractor O will be the first contractor to install their works in a condition that Contractor F will be able to complete the IP per the Contract Documents.

IV.

Contractor F prior to starting any works at an IP shall confirm Contractor O installation is acceptable to complete the IP per the terms of the contract documents. This is to include layout and elevations and general soundness of the installation.

V.

Contractor O shall facilitate Contractor F as required to complete the IP, providing required access or traffic control, etc. etc.

VI.

Upon completion of any irregularities and acceptance of Contractor O IP works, Contractor F shall complete the IP per the requirements of the contract documents.

VII.

Contractor F shall be responsible for future protection of the IP and all snag list works associated with the said IP.

VIII.

It is the responsibility of the parties involved to ensure that the appropriate Non-Disclosure Agreements are in place where the exchange of information and / or drawings & documents as specified in this document.

Interface Parties There are four parties involved in the management of interface points: • • • •

Finalization Contractor “ Contractor F” Originator Contractor “ Contractor O” 3rd party Contractor Project Management Team

For each IP, Contractor F and Contractor O will be identified by the PMT.

4.2

Contractor F Contractor F shall: 1. Be the contractor that finalizes the works at an IP 2. Participate in the creation and maintenance of the IDT Interface Dependency Table 3. Participate in all requested IP coordination meetings 4. Mutually agree with Contractor O that the IP and associated data is correct, consistent and complete. 5. Provide all necessary input and support to the PMT

Contains Confidential Information of Both Dow and Saudi Aramco Page 7 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: Tender

6. Populate interfaces completion dates in the Interface Dependency Schedule (See Attachment 2) and update regularly to manage and monitor the timing of completion of interface points and gates. Copy to be provided to PMT. 7. Reach agreement on interfaces with other Contractors in a timely manner to support the overall Project schedule. 8. Identify and agree with Contractor O the inspections, tests and construction and pre-commissioning records that are required to be performed and/or maintained by itself and Contractor O. This applies to situations where both Contractors have an overlap of activities at the interface such as the joint hydrotest of both sides of an interface point at the same time. Otherwise the Contractors shall each be responsible for their 'side' of the interface. 9. Identify and agree with Contractor O any inspections, tests, drying and any other requirements to be witnessed by itself and Contractor O. 10. Prior to starting any interface works, confirm the acceptability of the in-place works instated by Contractor O. This confirmation shall include the overall acceptability of the in place IP works, including: layout, alignment elevation and the integrity of the elements being attached to or abutted. If any unacceptable conditions are identified then an equitable resolution shall be sought with Contractor O and the PMT. If Contractor F connects to an IP without identifying any deficiencies then Contractors O IP works will be considered as accepted without exception. This will not include any “latent or impossible to identify” problems. The PMT will act as arbitrator as required. 11. Upon acceptance of Contractor O works at IP Contractor F shall complete the IP works and provide protection until final turnover of the works. 12. Complete all Snag list works associated with the IP 13. Be fully responsible for the procurement and construction of the part of system within its own area. 14. Identify IPs that are no longer relevant, and communicate such to Contractor O and the PMT in a timely manner. .

4.3

Contractor O Contractor O shall: 1. Be the contractor that starts the works at an IP 2. Participate in the creation and maintenance of the IDT Interface Dependency Table 3. Participate in all requested IP coordination meetings 4. Mutually agree with Contractor F that the IP and associated data is correct, consistent and complete. 5. Provide all necessary input and support to the PMT 6. Populate interfaces completion dates in Interface Dependency Schedule (See Attachment 2) and update regularly to manage and monitor the timing of completion of interface points and gates. Copy to be provided to PMT. 7. Reach agreement on interfaces with other Contractors in a timely manner to support the overall Project schedule. 8. Identify and agree with Contractor F the inspections, tests and construction and pre-commissioning records that are required to be performed and/or maintained by itself and Contractor F. This applies to situations where both Contractors have an overlap of activities at the interface such as the joint

Contains Confidential Information of Both Dow and Saudi Aramco Page 8 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: Tender

hydrotest of both sides of an interface point at the same time. Otherwise the Contractors shall each be responsible for their 'side' of the interface. 9. Identify and agree with Contractor F any inspections, tests, drying and any other requirements to be witnessed by itself and Contractor O. 10. Complete the first stage of the works relating to subject IP per the documented agreements made with Contractor F. 11. Facilitate all requested inspections of the IP with Contractor F and or the PMT to confirm installation is installed per the contract requirements, position and elevation. Any and all unacceptable conditions shall be rectified promptly to prevent any schedule disruption of Contractor F and the overall program schedule. 12. Provide all required interface assistance including access, traffic control and any other reasonable or required assistance to allow Contractor F complete the IP. 13. Identify IPs that are no longer relevant, and communicate such to Contractor F in a timely manner. Also communicate to PMT. 14. Be fully responsible for the procurement and construction of the part of a System within its own area.

4.4

Project Management Team (PMT) will: 1. Develop, communicate and maintain the Interface Management Plan and associated guidelines for: • Identifying and defining interface points • Assigning responsibilities of parties at each IP • Data required to define each interface point construction phase 2. Provide Final resolution of any queries at interface points

5.0

5.1

INTERFACE TYPES External Interface

External Interface specifically refers to 3rd parties outside of the contractors nominated for the building envelope.

Contains Confidential Information of Both Dow and Saudi Aramco Page 9 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: Tender

Envelope Unit

Unit 1 Package A

Unit 3 Package B

Unit 2 Package C

External Interface Point

5.2

Internal Interface Internal Interface is an interface between Package Contractors nominated for the Building scope.

Unit Envelope

Unit 1 Package A

Unit 3 Package B

Unit 2 Package C

Internal Interface Point

6.0

INTERFACE NUMBERING The IP number will be assigned as follow IP-d-w/u-nnnn Where:

Contains Confidential Information of Both Dow and Saudi Aramco Page 10 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

d w/u

nnnn

Issue Purpose: Tender

Discipline code, see below Package Contractors Code The first number shown (w) is Contractor O and the second number (u) is Contractor F. Serial number (a unique number will be assigned for each discipline)

Discipline codes: CAE

Cable Tray - Electrical

CAT

Cable Tray – IT

CBE

Cable Trench – Electrical

CBT

Cable Trench/Duct Bank - IT

CC

Civil Open Ditch

CF

Civil Fence Crossing

CR

Civil Road

CRT

Road Crossing - IT

E

Electrical Cable

F

Firewater

P

Piping

S

Structural

T

Telecommunications Cable

TS

Miscellaneous IT (Supplementary Interface Table)

U

Underground Piping (gravity flow only)

The following is the specific Package Contractors Codes, which will be used to provide clarity. A

Package A Contractor

B

Package B Contractor

C

Package C Contractor

D

Package D Contractor

For example: “IP-P-A/B-000004” would be a piping IP between the Package A Contractor and Package B Contractor.

Contains Confidential Information of Both Dow and Saudi Aramco Page 11 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

7.0

Issue Purpose: Tender

COMMUNICATION Packages Contractors shall communicate directly with each other to agree definition and completion of interfaces. PMT will maintain, the master SPOCs List which will include the names and contact details of the interface coordinators (Single Points of Contact) for all parties. Communication may take place in a combination of the following formats: • Interface Queries (IQs) • Transmission of documentation • Meetings (with decisions subsequently recorded by IQs using MOM as a proof of agreements) • Emails Each Package Contractor shall appoint a SPOC to efficiently manage such communications. Each Package Contractor shall maintain a log of all IQs sent/received. IQs raised by any Contractor shall be addressed to the other Party’s Contractor SPOC’ and shall also be copied to the ‘PMT SPOC – additional people may be copied but all IQs must be sent only ‘To’ the Package Contractor SPOC’

7.1

Interface Queries (IQs) Interface Queries (IQs) may be raised by any Party to make a query, provide or request information or to confirm an agreement, using the form in Attachment P, Contractors shall communicate directly with all other Contractors having an interest in the interface. All formal agreements and requests shall be recorded in an IQ.

7.2

IQ Numbering IQs shall be numbered in the form: IQ-x-y-nnnn Where: x y nnnn

Querying Party code Responding Party code Serial number (assigned by the querying Party)

The Party codes are included within the ‘SPOCs List’ which is maintained by PMT and regularly issued to all parties. The ‘SPOCs List’ also identifies which units are associated with each Party. For example, the second IQ from Package B Contractor to Package C contractor would be numbered IQ-B-C-002.

Contains Confidential Information of Both Dow and Saudi Aramco Page 12 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

7.3

Issue Purpose: Tender

Transmission of Documentation A record shall be kept of all documentation (documents and drawings) transmitted between Contractors and IQs shall be used for the transmittal.

8.0

INTERFACE GUIDELINES The following defines the split of responsibilities between Contractors during construction at IPs and provides guidance on how to implement interfaces for different situations that may arise. The engineering requirements are defined in the relevant Program documents and drawings. The list of IPs are listed in Attachment 2 The following is general guidance • For external interfaces between a Package and a 3rd Party contractor, then the Package Contractor will be Contractor F. • For internal interfaces between Packages, then Contractor F will be assigned by the Project Management Team.

8.1

Piping

8.1.1

Above Ground Piping Interfaces

8.1.1.1

General 1. The default position shall be that Contractor F shall provide the required isolation, based on the service, at the IP for commissioning and operating purposes. This isolation could be blind flanges, figure 8 blinds, valves or other means. Contractor F shall provide any final spacers, gaskets and bolts required for the final closure of the IP.

CONTRACTOR O

CONTRACTOR F

2. Contractor F and Contractor O shall each provide their own test gaskets, blind flanges and bolts to allow testing of the piping within their respective scope. 3. After completion of flushing, testing, etc by each Contractor of his own section of piping, Contractor F, after agreement with the other Contractor, remove the blind, install the spacer, and bolt up the flanges to complete the joint. 4. Each Contractor shall be responsible for the design and installation of insulation up to the Interface Point with Contractor F responsible for final closure of the joint.

Contains Confidential Information of Both Dow and Saudi Aramco Page 13 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

8.1.2

Underground Piping Interfaces

8.1.2.1

Firewater

Issue Purpose: Tender

1. Contractor O shall provide fire mains and appurtenances along the main roads for the overall firemain outside Buildings area and provide spurs off the ring main at the indicated on the drawings 2. The IP, which consists of a valve supplied by Contractor O will be installed in a valve box constructed by Contractor O. Contractor F will be responsible for grouting and sealing the valve box where his pipe protrudes. 3. Contractor O shall install and test the fire main up to the IP. 4. Contractor F shall install and test his fire main up to the isolation valve. 5. Contractor F shall provide the gaskets, bolts etc to make the final closure. 8.1.2.2

Other services TEMPORARY END PIECES FOR TESTING

CONTRACTOR O

ANCHOR

CONTRACTOR F ANCHOR

FINAL SPOOL, JOINTS & TESTING BY CONTRACTOR F

1.

Each contractor shall construct, test, flush, clean, and back fill their piping up to their respective battery limits. Contractor F will then complete the system with a short section of pipe. These final joints will be considered “Golden Joints” followed by service test before backfilling.

8.2

Civil Interfaces

8.2.1

Road Interfaces 1. Contractor O shall lay and compact the pavement materials to an acceptable stable slope beyond the extent of his wearing surface slope. 2. Contractor F shall ensure the soundness of this material prior to laying all subsequent layers.

Contains Confidential Information of Both Dow and Saudi Aramco Page 14 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: Tender

Centreline of Road Interface

CONTRACTOR F

CONTRACTOR F

CONTRACTOR ICF

CONTRACTOR F

Interface

Interface

CONTRACTOR ICF

CONTRACTOR ICF

PLAN

PLAN

1.0m* 1.0m*

Final Joint Surface wearing course Base course Sub –base (if required) Sub -grade *Dimensions to be confirmed by CONTRACTOR F

It is the responsibility of Contractor F to complete the interface, unless PMT instructed otherwise, recognizing that the edge of the courses, shown above, may have worn during the interim period. They will be responsible for rectification work to the edge. 8.2.2

Paving Interfaces 1. Paving interface shall typically be at the high point of paving. 2. Contractor O shall lay and compact the pavement materials to an acceptable stable slope beyond the extent of his wearing surface slope. 3. Contractor F shall ensure the soundness of this material prior to laying all subsequent layers.

CONTRACTOR O

Interface

CONTRACTOR ICF

1.0m* 1.0m*

Asphalt/concrete paving Base course

*Dimensions to be confirmed by CONTRACTOR F

Contains Confidential Information of Both Dow and Saudi Aramco Page 15 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

8.2.3

Issue Purpose: Tender

Ditch Interfaces 1. If the IP is a direct tie-in to the Contractor O ditch, Contractor O will Construct the ditch without provision for Contractor F, who will tie-in in accordance with Project Specifications. 2. If the IP is not a direct tie-in to the Contractor O ditch, Contractor O shall extend the reinforcement to permit continuity by Contractor F. 3. Contractors O & F shall provide initial construction joint with Water stops.

Section

Plan Elevation Slope

CONTRACTOR F Expansion Joint CONTRACTOR O

8.2.4

0.5m * exposed reinforcement

Telecommunication Concrete Encased Duct Banks

1. The Contractor O ensures the integrity of the conduits to be free from damage. 2. Conduit ends shall be cap and plugged at the interface point to ensure that no undesired material will enter into the conduits. 3. The Contractor O shall leave at least 300mm of the conduit, free of concrete for the Contractor F to conveniently place the couplings. 4. Contractor F shall provide and install the couplings to properly connect the conduits. 5. Contractor F shall provide and install the completion of concrete encasement for the conduit protection. 6. Contractor F shall coordinate with the Contractor O to execute mandrel throughout the length of the involved duct bank

Contains Confidential Information of Both Dow and Saudi Aramco Page 16 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

8.3

Issue Purpose: Tender

IT/ Telecom Interface All telecommunication cables inside buildings will be supplied and installed by Package Contractors as per Package Contractor scope, however ITC will terminate the cables at the wall faceplates and at the building interface terminal strip; Package Contractor will supervise terminations within the building.

8.4

Electrical Interface Electrical interfaces will be as described in Doc A554-R-730-IN-GEN-INT-002

Contains Confidential Information of Both Dow and Saudi Aramco Page 17 of 31

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

ATTACHMENT 1 – INTERFACE QUERY FORM

IQ-xxx-yyy-nnn

Contains Confidential Information of Both Dow and Saudi Aramco Page 18 of 31

Issue Purpose: Tender

SADARA Project

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRCUCTION INTERFACE MANAGEMENT PLAN

Contains Confidential Information of Both Dow and Saudi Aramco Page 19 of 31

Issue Purpose: Tender

ATTACHMENT 2– INTERFACE DEPENDENCY TABLE

No.

1  2  3  4  5  6  7  8  9  10  11  12  13  14  15  16  17  18  19  20 

Interface Point

Contractor O

Contractor F

ELECTRICAL  IP‐CBE‐B/A‐0001  IP‐CBE‐B/A‐0002  IP‐CBE‐B/A‐0003  IP‐CBE‐B/ICF‐0004  IP‐CBE‐B/ICF‐0005  IP‐CBE‐B/ICF‐0006  IP‐CBE‐B/C‐0007  IP‐CBE‐B/C‐0008  IP‐CBE‐D/C‐0009  IP‐CBE‐B/C‐0010  IP‐CBE‐D/A‐0011  IP‐CBE‐C/A‐0012  IP‐CBE‐D/C‐0013  IP‐CBE‐D/C‐0014  IP‐CBE‐D/C‐0015  IP‐CBE‐C/A‐0016  IP‐CBE‐C/A‐0017  IP‐CBE‐C/A‐0018  IP‐CBE‐C/A‐0019  IP‐CAE‐A/ICF‐0001 

B  B  B  B  B  B  B  B  D  B  D  C  D  D  D  C  C  C  C  A 

A  A  A  ICF  ICF  ICF  C  C  C  C  A  A  C  C  C  A  A  A  A  ICF 

Type

Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Trench  Electrical Cable 

IP Status

Contractor O Target Date

Contractor F Target Date

Diff. Days

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: TENDER

21  IP‐CAE‐A/ICF‐0002 



ICF 

22  IP‐CAE‐A/ICF‐0003  IT  1  IP‐CBT‐ B/A‐0001  2  IP‐CBT‐ B/A‐0002  3  IP‐CBT‐ A/ICF‐0003  4  IP‐CBT‐A /ICF‐0004  5  IP‐CBT‐ A/ICF ‐0005  6  IP‐CBT‐B/C‐0006  7  IP‐CBT‐D/C‐0007  8  IP‐CBT‐ D/C‐0008  9  IP‐CBT‐D/C‐0009  10  IP‐CBT‐ D/C‐0010  11  IP‐CBT‐ D/C‐0011  12  IP‐CBT‐B/C‐0012  13  IP‐CBT‐ B/ICF‐0013  14  IP‐CBT‐ B/A‐0014  15  IP‐CBT‐C/A‐0015  16  IP‐CBT‐D/A‐0016  17  IP‐CBT‐ D/C‐0017 



ICF 

Tray  Electrical Cable  Tray  Electrical Cable  Tray 

B  B  A  A  A  B  D  D  D  D  D  B  B  C  C  D  D 

A  A  ICF  ICF  ICF  C  C  C  C  C  C  C  ICF  ICF  A  A  C 

IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks 

  

  

Contains Confidential Information of Both Dow and Saudi Aramco Page 21 of 31

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

18  19  20  21  22  23  24  25  26  27  28  29  30  31  32  33  34  35  36  37  38  39 

IP‐CBT‐ D/C‐0018  IP‐CBT‐D/C‐0019  IP‐CBT‐ A/C‐0020  IP‐CBT‐ C/ICF‐0021  IP‐CBT‐D/A‐0022  IP‐CBT‐ B/C‐0023  IP‐CBT‐ B/D‐0024  IP‐CBT‐D/C‐0025  IP‐CBT‐B/ICF‐0026  IP‐CBT‐B/ITC‐0027  IP‐CBT‐B/ITC‐0028  IP‐CBT‐B/ITC‐0029  IP‐CBT‐B/ICF‐0030  IP‐CBT‐/‐0031  IP‐CBT‐D/A‐0032  IP‐CBT‐ C/EW‐0033  IP‐CBT‐ C/EW‐0034  IP‐CBT‐ D/EW‐0035  IP‐CBT‐ D/EW‐0036  IP‐CBT‐ D/EW‐0037  IP‐CBT‐ D/EW‐0038  IP‐CBT‐ D/EW‐0039 

Issue Purpose: TENDER

D  D  A  C  D  B  B  D  B  B  C  B  B     D  C  C  D  D  D  D  D 

C  C  C  ICF  A  D  D  C  ICF  ITC  ITC  ITC  ICF     A  EW  EW  EW  EW  EW  EW  EW 

IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks     IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks 

  

                 

Intentionally   Not Used    

                    

                    

Contains Confidential Information of Both Dow and Saudi Aramco Page 22 of 31

                    

                    

3

3

3

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

40  41  42  43  1  2  3  4  5  6  7  8  9  10  11  12  13  14  15  16  17  18 

IP‐CBT‐ D/EW‐0040  IP‐CBT‐ D/EW‐0041  IP‐CBT‐ D/EW‐0042  IP‐CBT‐ D/EW‐0043  CIVIL  IP‐CR‐A/ICF‐0001  IP‐CR‐A/ICF‐0002  IP‐CR‐A/ICF‐0003  IP‐CR‐A/ICF‐0004  IP‐CR‐A/ICF‐0005  IP‐CR‐A/ICF‐0006  IP‐CR‐A/ICF‐0007  IP‐CR‐A/ICF‐0008  IP‐CR‐A/ICF‐0009  IP‐CR‐B/ICF‐0010  IP‐CR‐A/B‐0011  IP‐CR‐A/B‐0012  IP‐CR‐A/B‐0013  IP‐CR‐A/B‐0014  IP‐CR‐A/B‐0015  IP‐CR‐A/B‐0016  IP‐CR‐A/B‐0017  IP‐CR‐A/B‐0018 

Issue Purpose: TENDER

D  D  D  D 

EW  EW  EW  EW 

IT Duct Banks  IT Duct Banks  IT Duct Banks  IT Duct Banks 

A  A  A  A  A  A  A  A  A  B  A  A  A  A  A  A  A  A 

ICF  ICF  ICF  ICF  ICF  ICF  ICF  ICF  ICF  ICF  B  B  B  B  B  B  B  B 

Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road 

           

           

Contains Confidential Information of Both Dow and Saudi Aramco Page 23 of 31

           

           

3

3

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

19  20  21  22  23  24  25  26  27  28  29  30  31  32  33  34  35  36  37  38  39  40  41 

IP‐CR‐B/ICF‐0019  IP‐CR‐B/ICF‐0020  IP‐CR‐B/ICF‐0021  IP‐CR‐C/ICF‐0022  IP‐CR‐D/C‐0023  IP‐CR‐D/C‐0024  IP‐CR‐D/C‐0025  IP‐CR‐D/C‐0026  IP‐CR‐A/C‐0027  IP‐CR‐A/C‐0028  IP‐CR‐A/C‐0029  IP‐CR‐A/C‐0030  IP‐CR‐D/C‐0031  IP‐CR‐D/PREP‐0032  IP‐CR‐D/PREP‐0033  IP‐CR‐D/PREP‐0034  IP‐CR‐D/PREP‐0035  IP‐CR‐D/C‐036  IP‐CR‐C/ICF‐0037  IP‐CR‐C/ICF‐0038  IP‐CR‐D/ICF‐0039  IP‐CR‐D/PREP‐0040  IP‐CR‐D/ICF‐0041 

Issue Purpose: TENDER

B  B  B  C  D  D  D  D  A  A  A  A  D  D  D  D  D  D  C  C  D  D  D 

ICF  ICF  ICF  ICF  C  C  C  C  C  C  C  C  C  PREP  PREP  PREP  PREP  C  ICF  ICF  ICF  PREP  ICF 

Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road  Road 

              

              

Contains Confidential Information of Both Dow and Saudi Aramco Page 24 of 31

              

              

3

3

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

42  43  44  37  38  39  40  41  42  43  44 

IP‐CR‐D/PREP‐0042  IP‐CR‐D/PREP‐0043  IP‐CR‐D/ICF‐0044  IP‐CC‐A/B‐0001  IP‐CC‐A/B‐0002  IP‐CC‐A/ICF‐0003  IP‐CC‐A/ICF‐0004  IP‐CC‐A/ICF‐0005  IP‐CC‐B/ICF‐0006  IP‐CC‐C/PREP‐0007  IP‐CC‐D/C‐0008 

45  46  47  48 

IP‐CC‐ ‐0009  IP‐CC‐D/C‐0010  IP‐CC‐C/A‐0011  IP‐CC‐A/C‐0012 

49  50  51  52  53  54 

IP‐CC‐ 0013  IP‐CC‐C/A‐0014  IP‐CC‐A/RC‐0015  IP‐CC‐D/C‐0016  IP‐CC‐D/C‐0017  IP‐CC‐C/RC‐0018 

Issue Purpose: TENDER

D  D  D  A  A  A  A  A  B  D  D 

PREP  PREP  ICF  B  B  ICF  ICF  ICF  ICF  C  C 

Road  Road  Road  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches 

        

        

Intentionally  Not  Used 

D  C  A 

C  A  C 

Storm Ditches  Storm Ditches  Storm Ditches  Intentionally  Not  Used 

C  A  D  D  C 

A  RC  C  C  RC 

Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches 

Contains Confidential Information of Both Dow and Saudi Aramco Page 25 of 31

        

        

3

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

55  56  57  58  59  60  61  62 

Issue Purpose: TENDER

IP‐CC‐D/C‐0019  IP‐CC‐D/C‐0020  IP‐CC‐B/C‐0021  IP‐CC‐B/RC‐0022  IP‐CC‐B/C‐0023  IP‐CC‐B/C‐0024  IP‐CC‐C/ICF‐0025  IP‐CC‐C/ICF‐0026  PIPING  1  IP‐P‐B/A‐0001 

D  D  B  B  B  B  C  C 

C  C  C  RC  C  C  ICF  ICF 





2  IP‐P‐B/A‐0002 





3  IP‐P‐B/A‐0003 





Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches  Storm Ditches 

  

  

  

5  IP‐P‐ ‐0005 

  

  

  

6  IP‐P‐ ‐0006 

  

  

  

7  IP‐P‐ ‐0007  8  IP‐P‐B/A‐0008  9  IP‐P‐B/A‐0009 

  

  

   Potable Water  Compressed Air 

A  A 

     

Sanitary System  Return ‐ Chilled  Water  Supply ‐ Chilled  Water 

4  IP‐P‐ ‐0004 

B  B 

     

Intentionally   Not Used  Intentionally   Not Used  Intentionally   Not Used  Intentionally   Not Used 

Contains Confidential Information of Both Dow and Saudi Aramco Page 26 of 31

     

     

3

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: TENDER

10  IP‐P‐B/A‐0010 





11  IP‐P‐B/A‐0011  12  IP‐P‐B/A‐0012 

B  B 

A  A 

13  IP‐P‐B/C‐0013 





14  15  16  17  18  19  20  21  22  23  24  25  26 

IP‐P‐B/C‐0014  IP‐P‐B/C‐0015  IP‐P‐B/C‐0016  IP‐P‐B/C‐0017  IP‐P‐B/C‐0018  IP‐P‐D/C‐0019  IP‐P‐D/C‐0020  IP‐P‐B/C‐0021  IP‐P‐B/C‐0022  IP‐P‐B/C‐0023  IP‐P‐C/A‐0024  IP‐P‐C/A‐0025  IP‐P‐C/A‐0026 

B  B  B  B  B  D  D  B  B  B  C  C  C 

C  C  C  C  C  C  C  C  C  C  A  A  A 

27  IP‐P‐D/C‐0027  28  IP‐P‐D/C‐0028 

D  D 

C  C 

Return ‐ Chilled  Water  Supply ‐ Chilled  Water  Sanitary System  Return ‐ Chilled  Water  Supply ‐ Chilled  Water  Potable Water  Potable Water  Sanitary System  Sanitary System  Sanitary System  Potable Water  Utility Water  Compressed Air  Potable Water  Potable Water  Utility Water  Sanitary System  Supply ‐ Chilled  Water  Return ‐ Chilled 

Contains Confidential Information of Both Dow and Saudi Aramco Page 27 of 31

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: TENDER

Water  29  IP‐P‐ ‐0029  30  IP‐P‐D/C‐0030 

  

31  IP‐P‐ ‐0031  32  IP‐P‐A/C‐0032 

  

   D 







33  IP‐P‐A/C‐0033 





34  IP‐P‐A/C‐0034 





   Potable Water  Return ‐ Chilled  Water  Supply ‐ Chilled  Water 

C  C  C  C  C  B 

   Sanitary System  Sanitary System  Potable Water  Sanitary System  Sanitary System  Potable Water 

35  36  37  38  39  40  41 

IP‐P‐ ‐0035  IP‐P‐D/C‐0036  IP‐P‐D/C‐0037  IP‐P‐D/C‐0038  IP‐P‐D/C‐0039  IP‐P‐D/C‐0040  IP‐P‐D/B‐0041 

42  IP‐P‐ ‐0042  43  IP‐P‐B/C‐0043  44  IP‐P‐ ‐0044  45  IP‐P‐ ‐0045 

  

   Potable Water 

  

   D  D  D  D  D  D 

Intentionally   Not Used  Intentionally   Not Used 

Intentionally   Not Used 

Intentionally  Not  Used 





Sanitary System  Intentionally  Not  Used  Intentionally  Not 

Contains Confidential Information of Both Dow and Saudi Aramco Page 28 of 31

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: TENDER

Used 

46  IP‐P‐ ‐0046  47  IP‐P‐ ‐0047  48  IP‐P‐ ‐0048  49  50  51  52  53  54  55 

IP‐P‐ ‐0049  IP‐P‐B/A‐0050  IP‐P‐B/A‐0051  IP‐P‐B/A‐0052  IP‐P‐C/A‐0053  IP‐P‐C/A‐0054  IP‐P‐C/A‐0055 

B  B  B  C  C  C 

A  A  A  A  A  A 

Sanitary System  Potable Water  Compressed Air  Potable Water  Compressed Air  Utility Water 

56  IP‐P‐C/EW‐0056 



EW 

Sanitary System 

57  IP‐P‐C/EW‐0057  58  IP‐P‐D/BRINE‐0058  59  IP‐P‐D/BRINE‐0059  60  IP‐P‐D/EW‐0060  61  IP‐P‐D/ICF‐0061  62  IP‐P‐D/ICF‐0062  63  IP‐P‐D/ICF‐0063 

C  D  D  D  D  D  D 

EW  BRINE  BRINE  EW  ICF  ICF  ICF 

Potable Water  Sanitary System  Potable Water  Potable Water  Sanitary System  Sanitary System  Potable Water 

Intentionally  Not  Used  Intentionally  Not  Used  Intentionally  Not  Used  Intentionally  Not  Used                    MUSSALA & CAFÉ  4  MUSSALA & CAFÉ  4  GATE 4  GATE 4 

3

3

GATE 5  GATE 5 

3

GATE7  GATE 7 

Contains Confidential Information of Both Dow and Saudi Aramco Page 29 of 31

3

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

Issue Purpose: TENDER

64  IP‐P‐D/ICF‐0064 



ICF 

Sanitary System 

65  IP‐P‐D/ICF‐0065  66  IP‐F‐B/A‐0001 

D  B 

ICF  A 

Potable Water  Firewater 

67  IP‐F‐ ‐0002 

  

  

  

68  IP‐F‐ ‐0003 

  

  

  

69  IP‐F‐ ‐0004 

  

  

  

70  IP‐F‐ ‐0005  71  IP‐F‐B/C‐0006  72  IP‐F‐B/C‐0007 

  

  

   Firewater  Firewater 

73  IP‐F‐ ‐0008 

  

  

  

74  IP‐F‐ ‐0009  75  IP‐F‐C/A‐0010  76  IP‐F‐B/C‐0011 

  

  

   Firewater  Firewater 

B  B 

C  C 

C  B 

A  C 

77  IP‐F‐ ‐0012 

  

  

  

78  IP‐F‐ ‐0013  79  IP‐F‐ ‐0014 

     

     

     

PEDESTRIAN  SOUTH  PEDESTRIAN  SOUTH 

Intentionally   Not Used  Intentionally   Not Used  Intentionally   Not Used  Intentionally   Not Used 

Intentionally   Not Used  Intentionally   Not Used 

Intentionally   Not Used  Intentionally   Not Used  Intentionally  

Contains Confidential Information of Both Dow and Saudi Aramco Page 30 of 31

3

SADARA PROJECT

Document No. A554-R-730-IN-GEN-INT-001 Revision: 3

SDL BUILDING CONSTRUCTION INTERFACE MANAGEMENT PLAN

80  IP‐F‐ ‐0015 

Issue Purpose: TENDER

  

  

  

Intentionally  Not  Used  Intentionally  Not  Used  Intentionally  Not  Used 

81  IP‐F‐ ‐0016  82  IP‐F‐ ‐0017  83  IP‐F‐A/PREP‐0018  84  85  86  87  88  89 

IP‐F‐ ‐0019  IP‐F‐B/C‐0020  IP‐F‐B/A‐0021  IP‐F‐C/A‐0022  IP‐F‐B/C‐0023  IP‐F‐C/EW‐0024 

Not Used  Intentionally   Not Used 

  B  B  C  B  C 

  C  A  A  C  EW 

   Firewater  Firewater  Firewater  Firewater  Firewater 

Intentionally   Not Used 

  

  

Contains Confidential Information of Both Dow and Saudi Aramco Page 31 of 31

  

  

3

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF