Field Test Report Sample for 132 kV Power Transformer Testing...
Description
132/33 kV Transformer Bay at Lamki S/S
FIELD TEST REPORT OF POWER TRANSFORMER Test Date:
1. Equipment Detail Equipment Circuit Position Manufacturer Serial No Vector Group Type of Cooling Rated Power
: 132/33 kV Power Transformer : 132/33 kV Transformer Bay : : : : :
1.1 General check SN 1 2 3 4 5 6
7
Test Items Inspection Secondary Wiring Tightness Equipment and Structure Earthing
Results
Remarks
Ratio Selection Spare Core
As per NEA requirement All spare core are short circuited
Polarity Oil leakage Oil Level
Between Min and Max position
1.2 Insulation Resistance Test Connection
IR Value (5000V) M - 1 Min
IR Value (5000V) M - 3 Min
Remarks
Reading - 1
Reading -2
Average
HV-E HV-LV LV-E
1.3 BDV Test Sample Top Bottom
1.4 Turn Ratio Tester Tap no. Primary Voltage Actual Ratio Observed Ratio Percentage Error 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Remarks
Field Test Report of 132 kV Power Transformer
Page 1 of 3
132/33 kV Transformer Bay at Lamki S/S
1.5 Vector Group Test Test Items Measured Voltage Verifying condition Result 1V-2V 1W-2W Ok 1V-2W 1W-2V Power Transformer Vector Group Testing (YNyn0) : R-r Shorted Tap position = 9 , three phase voltage applied on the primary side.
R
R
Y
B
N
r
y
b
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Y B N r y
X
b n 1.6 Short Circuit Test R-Y-B-N Supplied and r-y-b-n shorted Tap Position 1
Primary Current R= Y= B= N=
Primary Voltage R–N= Y–N= B–N=
Secondary Current r= y= b= n=
9
R= Y= B= N=
R–N= Y–N= B–N=
r= y= b= n=
17
R= Y= B= N=
R–N= Y–N= B–N=
r= y= b= n=
Remarks
Field Test Report of 132 kV Power Transformer
Page 2 of 3
132/33 kV Transformer Bay at Lamki S/S
1.7 Winding Temperature Setting S.N 1 2 3 4
Test Item Setting Fan – Group -1 Fan – Group -2 Alarm Trip
Remarks
1.8 Oil Temperature Setting S.N Test Item 1 Alarm 2 Trip