1.0 Introduction
Short Description
plan quality project for construction...
Description
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Target Resources Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 1
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
1.0 INTRODUCTION 1.1 PURPOSE The purpose of the Project Quality Plan is to provide the key to the successful outcome of a project and such is the strategic planning document for the project. It is the document in which the Project Manager identifies the key challenges and critical execution issues for the particular project and documents the strategies for ensuring that these issues get the attention they warrant at crucial times and are managed and closed out effectively. This chapter sets out the general structure and approach for the preparation of a Quality Plan, as the project develops from stage to stage, it does this by:
Establishing a firm foundation at the outset Providing ongoing support to good practice throughout the implementation
The PQP:
Is structured the same for all projects Provides project specific information within the common structure Forms a road map through the project Prompts consideration of the key issues Is a live document Is progressively completed Forms an audit trail Records changes
1.2 OBJECTIVE OF THE PQP The objective of the PQP is to ensure that all phase of the project are executed with the optimum quality of satisfying the client’s requirement. ACDA site team and consultant project team will be implemented, maintained and improved through all phase of the project. Implementation of PQP must be fully supported by all personnel engaged on the project.
PQP/00
Page 2
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
1.3 SCOPE All projects required a PQP. The chapter describes the actions that the Project Manager must take to initiate and maintain the PQP. The Project Manager has sole responsibility for the initiation and maintain of the PQP for the project. The chapter establishes a clear link between the ISO 9001:2008 requirement and also with the Client’s requirements. PQP to be review every 6 (six) month.
PQP/00
Page 3
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Target Resources Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Target Resources Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 4
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
2.0
SYSTEM IMPLEMENTATION POLICIES
2.1
Project Quality Statement
2.2
2.3
PQP/00
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
i)
ACSB is fully committed to the quality objective of the works for Perumahan Rakyat Ladang Tanah Merah Project.
ii)
The scope of this PQP comprise of collection procedures and instruction in order to achieve the specified quality as per contract specification and standards.
iii)
All members of ACSB are committed to work as a team to achieve the objective of our client.
Quality Policy i)
To implement the ACSB Quality system employing systematic, planned and cost effective procedures that determine, assess and achieve quality and value.
ii)
To require the use of appropriate Quality System by our own suppliers and subcontractors.
iii)
To require all staff to perform their duties in compliance with the ACSB Quality System.
Quality Objectives i)
Deliver project within contract time.
ii)
Compliance to Client’s requirement.
iii)
Minimize defect up to 70%.
Page 5
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 6
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
3.0 PROJECT BRIEF 3.1
GENERAL PROJECT BRIEF
PROJECT:
Merekabentuk, Membina dan Menyiapkan 100 Unit Rumah Teres Satu Tingkat dan Kerja – kerja Berkaitan Bagi Program Perumahan Rakyat (PPR) di Ladang Tanah Merah Port Dickson, Negeri Sembilan Untuk Kementerian Kesejahteraan Bandar, Perumahan dan Kerajaan Tempatan
Contract No.
:
KPKT/CPPP/JPN/7/3/2015
Letter of Award
:
Ref No.: (2)dlm.KPKT/CPPP/UB/864/2/7-7K
Date of Award
:
11th February 2015
Contract Period
:
24 Months from the date of site possession
Site Possession
:
16 April 2015
Completion Date
:
15h April 2017
Defect Liability Period
:
24 Months
Liquidated & Ascertained Damages (LAD)
:
RM 3,166.00 per calendar day
Contract Sum
:
RM 16,842,490.00
Retention Sum
:
10% of Certified Value Up to a maximum of 5% of the Contract Sum
Client
:
Tel Fax Person In-Charge
: : : :
KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN Bahagian Pembangunan Dan Pelaksanaan Projek Cawangan Pelaksanna Dan Penyelenggaran Projek Aras 5-8, No.51, Persiaran Perdana, Presint 4, 62100 Putrajaya, Malaysia. 03 - 8891 5000 03 – 8891 3094 1. Ir. Hj. Mohd Halimi Bin Ismail (KPPK/W3) 2. En. Chandiramohan a/l Ranjithan(PP1/W3)
PQP/00
Page 7
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
Main Contractor
:
Tel Fax Person In-Charge
: : :
Architect
:
Tel Fax Person In-Charge
: : :
Civil & Structure Engineer
:
Tel Fax
: : :
Person In-Charge
Mechanical & Electrical Engineer
:
Tel Fax
: : :
Person In-Charge
PQP/00
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
ACDA CAPITAL SDN BHD No.244-24, Jalan Haruan 5/6, Pusat Komersial Oakland 11, 70200 Seremban, Negeri Sembilan Darul Khusus 06 – 632 3322 06 – 631 3322 1. Ir. Haji Nazar bin Ujang 2. En. Kamarul Hisyam Mohd Hashim WAN ARJUNA ARCHITECT (WAA) 23-3, Jalan Wangsa Delima 12, D`Wangsa, Wangsa Maju, 53300 Kuala Lumpur, Malaysia. 03 – 4143 6616/6617 03 – 4143 6606 1. Ar. Wan Norarjuna bin Wan Mustafa 2. En. Azam Abd. Halim RMS & ASSOCIATES CONSULT (RMS) 88A, Jalan Badminton 13/29, Seksyen 13, 40100 Shah Alam, Selangor Darul Ehsan 03 – 5511 7494/7495 03 – 5511 7476 1. Ir. Hj Zolihan bin Ngadeni 2. Pn. Marlina Azwani Mohd Alias MECHYLITE CONSULT SDN BHD(MCSB) 11A, Jalan Badminton 13/29, Seksyen 13, 40100 Shah Alam, Selangor Darul Ehsan 03 – 5523 8381 03 – 5523 8382 1. Ir. Azhar bin Abu Hadzim 2. Shameeza Izma Sabariman
Page 8
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
Quantity Surveyor
:
Tel Fax
: : :
Person In-Charge Landscape Architect
:
Tel Fax Person In-Charge
: : :
Planner
:
Tel Fax Person In-Charge
: : :
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
ADAM QS CONSULTANCY SDN BHD (AQSC) 136B,Jalan Burhanuddin Helmi, Taman Tun Dr. Ismail 60000 Kuala Lumpur 03 – 7727 5503 03 – 5511 3757 1. Sr. Adam bin Salih 2. En. Mazlan Bin Omar ZAIMMAR ASSOCIATES(ZA) B-3-3, Jalan Dataran Sentral 2, Dataran Sentral, 70200 Seremban Negeri Sembilan 03 – 6277 5712 03 – 6277 0712 LAr. Marlina Binti Aminudin FOURMATE DESIGN SDN BHD(FDSB) No. 27-1, Jalan MH-1, Taman Muzaffar Heights, Hang Tuah Jaya, 75450 Ayer Keroh Melaka 03 – 6156 5413/5428 03 – 6156 5436 Ms Joanna
3.2 Summary Scope of Works AC-DA CAPITAL is comprises generally the supply of all labours, materials, tools, implement, equipment and everything else necessary for the construction and completion of MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN Generally the project is divided by sections and the works are executed by nominated sub-contractors: a) General conditions and preliminaries
PQP/00
Page 9
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
Mobilization and demobilization of Main Contractor’ plants, machineries and manpower to site. Others works includes submission of deliverables to Client and compliance to rules and regulation of Client and Local Authorities.
b)
c)
Provide all the necessary documents pertaining to CCC to the Superintending Officer Representative (SOR) before the SOR can issue the Certificate of Practical Completion (CPC) to the contractor. Building works consist of: i)
Work Below Lowest Floor Finish – All structural work/non-structural work including waterproofing membrane and anti-termite soil treatment.
ii)
Frame – Reinforced concrete.
iii)
Roof – Metal decking and roof clay tile on steel roof trusses; Reinforced concrete flat roof.
iv)
Wall – Half brickwall and one brickwall complete with stiffeners, single glazing windows come with aluminums framed.
v)
Door & Windows – Timber doors and PVC doors, casement windows and louvre windows.
vi)
Wall, Floor Finishes & Ceiling Finishes – All plastering, tiling and flooring, ceiling boards etc.
vii)
Sanitary Fittings & Accessories – Supply and fix all sanitary fittings and accessories.
External Works which consist of: i) ii) iii) iv) v) vi) vii)
e)
PQP/00
Earthwork Surface Water Drainage Building Work Road and Car park Sewerage Water Reticulation Hard & Soft Landscape Works
Mechanical and Electrical Works.
Page 10
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
3.3 Project Location Plan
PQP/00
Page 11
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
3.4 Project Organization Chart
PQP/00
Page 12
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
3.5
PQP/00
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
Project Works Programme
Page 13
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 14
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
4.0 STATUTORY APPROVAL AND AUTHORITY 4.1
List below is the activities at the ACSB site that needs statutory approval. Approval shall be obtained from the relevant local or federal statutory bodies. 4.1.1 The project development has to be notified by the client (KPKT) to the authorities for acknowledgement only. 4.1.2 ACSB is responsible for compliance with all statutory requirements for the execution of the Work and shall prior to possession of site and progressively throughout the Contract Period where required, lodge with the Architect/SO the details of the approvals required and/or which have been obtained for the contractor to perform the work. There one (1) authorities requirements and approvals i.e. a) Majlis Perbandaran Port Dickson (MPPD) 4.1.3 ACSB to obtain Approval for Planning (AP) and other related construction matters from MPPD and submit/obtain approval and clearance. 4.1.4 The project needs to be registered with Jabatan Keselamatan Dan Kesihatan Pekerjaan Negeri Sembilan (JKKPNS). The JKKPS registration number shall be display prominently at the main entrance. 4.1.3
The project also has to be registered with CIDB. The original certification shall be displayed in the site office. A photocopy of the certificate shall be kept by the Contract Department.
4.1.4 Storage of new materials such as bagged cement, reinforcement bars and diesels require a permit from Kementerian Perdagangan Dalam Negeri. 4.1.5 All lifting equipment such as cranes required Perakuan Kelayakan Mesin Angkat (PMA) from the JKKP. 4.2
All the permits and registrations obtained shall be documented and maintained in the project site office. These documents shall be updated from time to time as required.
4.3
The Project Manager is responsible to ensure that all requirement permits/certificates are obtained and updated accordingly.
PQP/00
Page 15
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 16
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
5.0 PROJECT ORGANIZATION, AUTHORITY AND RESPONSIBILITIES 5.1
SITE CONSTRUCTION ORGANIZATION 5.1.1 Executive Management has delegated responsibilities to management level the project staff with complete authority to take the necessary action to ensure conformance by all staff member of the Quality System practiced. 5.1.2 Site Construction Organization team will be made up at Project Manager, Project Engineer, Site Safety Supervisor, Civil/Site/M & E Supervisors as well as other direction, supervision and co-ordination to carry out the construction programmed in accordance with contract requirement. (Refer Appendix 1: ACSB/PPR LTM/PQP/OC). 5.1.3 The Site Management will direct and co-ordinate the appointed subcontractors and the operation of machineries at site to achieve an efficient rate of progress. They will ensure the necessary degree of control is exercised to meet the various safety, security and environmental regulations requirement. They will lease with all relevant parties and developments to promote effective co-ordination of information and activities. 5.1.4 Site Construction Organization will be responsible for enforcing policies that assure ACSB meets and maintains the stated objectives of safety, security, logistic, Quality Assurance and Environmental requirements.
5.2
QUALITY ASSURANCE COMMITTEE The member of the QA Committee shall comprise of the Project Manager, Project Engineer and All Nominated Sub-Contractor. The QA Committee shall meet at least once in 6 month to discuss and highlight problems encountered in the implementation and operation at the QA System.
5.3
RESPONSIBILITIES OF KEY PERSONNEL The Responsibilities of Key Personnel are as per the following:
5.3.1 PROJECT MANAGER
PQP/00
The Project Manager shall be report to the ACSB Project Director and shall fully responsible to oversee the management.
Page 17
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
Overall planning, coordinating site activities, site management and budgeting.
Lead a team of Engineers and Site Management Team.
Liaises with the employer representatives, consultant, subcontractors, suppliers and local authorities.
5.3.2 SITE ENGINEER
The Engineer report to the Project Manager. He may be reported to Project Director if requested.
Assisting Project Manager in planning and monitoring, preparing monthly, weekly and daily work programs, checking, resolving, clarifying inconsistencies in drawing well before work is carried out.
Attending Technical, ‘contractors’ meeting and communicating correct & tip-todate construction information between all parties.
Relating all instruction from Project Manager to sub-contractors.
Preparing or compiling from technical information (shop drawing, temporary work design, bar bending schedules) to facilities works at site.
Supervising and coordinating works amongst subcontractors, checking subcontractor’s work to eliminate mistakes abortive works.
Liaising with consultant’s representative at site and assisting sub-contractors to solve problems.
Advising sub-contractors on technical matters and ensuring sub-contractors compliance to specification.
Verifying work done by sub-contractors.
5.3.3 SITE SUPERVISOR
The Site Supervisor reports to the Site Engineer or Senior Site Supervisor. They may be reporting to the Senior Site Engineer or Project Manager if assign.
Supervising and coordinating works amongst sub-contractors, checking subcontractor’s works to eliminate mistake and abortive works.
PQP/00
Page 18
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
Liaising with consultant’s representative at site, coordinating inspection amongst sub-contractors, consultant and QA/QC team.
Assisting sub-contractors to solve site problems and advising sub-contractors on technical matters.
Ensuring sub-contractor’s on technical matters, communicating correct and up-todate construction information between all parties
Keep daily progress records and attending Monthly, Weekly and Daily contractors’ Meetings.
Measuring works done by sub-contractors and witnessing performance of test.
5.3.4 QUANTITY SURVEYOR (QS)
The Quantity Surveyor reports to and assists the Project Manager, taking-off quantities.
Assisting in preparation and submission of tenders, assisting the Project Manager in preparing the Project budget and preparation material schedules.
Sourcing, calling evaluating quotations and tenders for supply of materials and services.
Preparing cost estimates, quotations and tenders for new work items, measuring work done at site and preparing interim claims and evaluating sub-contractors’ work done and prepare claim certificates.
Assisting the set-up of Management Information System and assisting the Planning Sub-Department to prepare reports for various projects.
Preparation and submission of contractual claims, variation etc.
Assisting the preparation of the project final accounts.
5.3.5 PLANNING
PQP/00
Will plan and schedule engineering, procurement and construction details through interaction with engineering, procurement and construction personnel to include creation of activities, logic, durations, coding, resource assignments and calendar assignments.
Page 19
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
Will sequence major work priorities into a logical schedule and manpower load schedule based on estimated direct hours and calculate percent complete from schedule.
Work with functional management to resolve scheduling issues of risk.
Oversee or conduct training programs for planning and scheduling, providing technical assistance to various departments.
Communicate scheduling problems in high-risk project to functional and power division management.
Review project contracts, documents and drawings to determine project scope and schedule development and to ensure Project PPR LTM complies with functional requirements.
Oversee the verification of accuracy of critical paths across projects and review and validation of overall project duration on multiple projects.
Will produce ad hoc reports upon request and monitor schedule for changes in float, correct logistic, potential problems,
Communicate any schedule problem areas to project team and provide solutions/options for resolution and monitor upstream activities that feed engineering, procurement and construction activities for any potential impacts and report these items to site management.
Will reflect schedule change orders in the project schedule and provide Schedule “what-if” scenarios when requested.
Review and validated schedule progress via physical work product inspection and maintain through knowledge of total project progress via visual inspection.
Travel to multiple project areas and/or project sites to support project needs.
5.3.6 LICENSED SURVEYOR
PQP/00
Licensed Surveyor will be assigned by the Project Manager specific Construction Team as and when necessary. When looking for a particular project, they shall be taking instruction form the respective Senior Project Manager whilst still liaising closely with the Planning Department for technical assistance.
Page 20
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
Counter-checking the accuracy of Monuments and Benchmark provided by other parties.
Checking, confirming the correctness and resolving any dimensional discrepancies in drawings.
Liaising and resolving setting out discrepancies with relevant parties.
Surveying details for planning, design and construction purposes and to check Existing Ground Levels.
Setting out of control point, benchmarks, slope stakes, references lines, boundaries, alignment, levels at site for various works.
Measuring completed works and preparing Site Measurement Records for payment purpose.
Surveying for as-built drawing preparation
5.3.7 SITE SAFETY SUPERVISOR
The Site Safety Supervisor reports to the Project Manager on all matters pertaining to workmen’s health, safety and security.
Advising the Project Manager on issues related to health, safety and security at work sites, including Statutory Requirement and Good Practices.
Ensuring the health and safety procedures are followed and all statutory requirements are fulfilled.
Implementing Health and Safety Programmed at project sites.
Enforcing the use of personal protection equipment, improves existing method of workmen.
Determining the cause of accident and recommending means of prevention,
Identifying and rectifying any unusual measure taken at work site.
Setting up and operating a security system which monitors the movement of workers, materials, goods, plants and machinery into and out of the project site.
PQP/00
Page 21
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 22
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
6.0 QUALITY MANAGEMENT SYSTEM 6.1 MAIN CONTRACT PARTIES The Quality System personnel are responsible for the successful implementation and operation of this PQP. To achieve quality, everyone is required to: i)
Follow set procedures
ii)
Inspect their own work as to its quality
iii)
Identify all occurrence of problems
iv)
To report to Project Manager any discrepancies between the documented Quality System and actual working practices.
v)
Continually search for better ways of doing things.
vi)
Have pride in the result of their work.
6.2
STRUCTURE Our project Quality Management System consists of the following documents: 6.2.1 Project Quality Plan This document defines the composition of the Quality Management System for the project to satisfy each element of ISO 9001:2008. It encompasses the Project Quality Objectives, the project organization, the activities to be performed, the progress monitoring mechanism, the interface with other parties and other project specific information. It defines operational controls needed at each stage of the product delivery cycle. 6.2.2
Quality Procedures This document establishes the producers of what is to be done to satisfy each element of the Project Quality Plan. Refer to ISO 9001:2008 Quality Procedures.
PQP/00
Page 23
AC-DA
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
The following List of Procedures with a tick (√) is applicable to this project. The project team shall refer the Procedures Manual to implement these procedures. NO. 1.0
PROCEDURE
4.0
ACSB/MS-01
QUALITY MANUAL - Quality Manual Procedure
3.0
APPLICABLE
MAGEMENT SYSTEM - Guideline For Procedure Preparation
2.0
DOC.REF
ACSB/QM-01
√
- Control of Document Procedure
ACSB/DP-01
√
- Control of Record Procedure
ACSB/DP-02
√
- Control of Non-Conforming Procedure
ACSB/DP-03
√
- Internal Audit Procedure
ACSB/DP-04
√
- Corrective Action Procedure
ACSB/DP-05
√
DOCUMENT PROCEDURE
PROJECT IMPLEMENTATION PROCEDURE - Tendering Procedure
ACSB/PIP-01
- Detailing Work Schedule Procedure
ACSB/PIP-02
- Project Insurance, Performance &
ACSB/PIP-03
advance Bond Procedure - Project Procurement Procedure
ACSB/PIP-04
√
- Claims Procedure
ACSB/PIP-05
√
- Monitoring of Project Progress Procedure
ACSB/PIP-06
√
- Maintenance of Plant, Equipment & Tools
ACSB/PIP-07
√
ACSB/PIP-08
√
Procedure - Final Claims Procedure
PQP/00
Page 24
AC-DA
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NO. 5.0
PROCEDURE
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
DOC.REF
APPLICABLE
SITE PROCEDURE - Mobilization & Demobilization
ACSB/SP-01
√
- Control of Contract Drawings Procedure
ACSB/SP-02
√
- Main Contract Administration Procedure
ACSB/SP-03
√
- Site Security Procedure
ACSB/SP-04
√
- Occupational Health & Safety Procedure
ACSB/SP-05
√
- Calibration & Maintenance of Measuring
ACSB/SP-06
√
ACSB/SP-07
√
ACSB/SP-08
√
- Employment of Sundry Workers Procedure
ACSB/SP-09
√
- Site Office Administration Procedure
ACSB/SP-10
√
- Quality Records Procedure
ACSB/SP-11
√
- Site Instructions Procedure
ACSB/SP-12
√
- Monitoring of Project Progress Procedure
ACSB/SP-13
√
- Material Handling & Control Procedure
ACSB/SP-14
√
- Identification & Traceability of Works
ACSB/SP-15
√
- Inspection & Testing of Works Procedure
ACSB/SP-16
√
- As-Built Drawing Procedure
ACSB/SP-17
√
Instruments & Test Equipments Procedure - Purchase/Hire of Plant & Equipment Procedure - Purchase of Construction Materials Procedure
Procedure
PQP/00
Page 25
AC-DA
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
6.2.3 Method Statement Manual The procedure in this manual technically outlined the method to be adopted to execute the construction processes. Each method statement describes the method of handling, construction, testing or use of equipment for the particular activity. The following Method Statements List with a tick (√) is applicable to this project. The project team shall refer to the Method Statements Manual to implement these documents. NO. 1.0
PROCEDURE
DOC.REF
APPLICABLE
STRUCTURAL WORKS - Structural Reinforced Concrete
ACSB/CNS/MS/
√
- Drainage Work
ACSB/CNS/MS/
√
- Sewerage Work
ACSB/CNS/MS/
√
- Water Reticulation Work
ACSB/CNS/MS/
√
- Retaining Wall
ACSB/CNS/MS/
√
- Road Work
ACSB/CNS/MS/
√
- Turfing Work
ACSB/CNS/MS/
√
- Landscaping Work
ACSB/CNS/MS/
√
Work & Formwork for Building RC Retaining Wall 2.0
PQP/00
CIVIL WORKS
Page 26
AC-DA
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NO. 3.0
4.0
PROCEDURE
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
DOC.REF
APPLICABLE
ARCHITECTURAL WORKS - Anti-Termite Work
ACSB/ARCH/MS/
√
- Brick Work
ACSB/ARCH/MS/
√
- Door & Window Frame
ACSB/ARCH/MS/
√
- Roof Trusses and Covering
ACSB/ARCH/MS/
√
- Plastering Work
ACSB/ARCH/MS/
√
- Ceiling Work
ACSB/ARCH/MS/
√
- Screeding Work
ACSB/ARCH/MS/
√
- Tiling Work
ACSB/ARCH/MS/
√
- Glazing Work
ACSB/ARCH/MS/
√
- Painting Work
ACSB/ARCH/MS/
√
- Door & Window Casement
ACSB/ARCH/MS/
√
- Furniture
ACSB/ARCH/MS/
√
ACSB/MECH/MS/
√
ACSB/MECH/MS/
√
ACSB/MECH/MS/
√
ACSB/MECH/MS/
√
ACSB/MECH/MS/
√
ACSB/MECH/MS/
√
MECHANICAL WORKS - Underground Pipe for Cold Water Plumbing - Underground Sanitary Pipe Installation - Sanitary Pipes Concealed in Walls Installation - Domestic Water Pump Installation - Water Storage Tank Installation - Poly Steel Pipe for Cold Water Plumbing Installation
PQP/00
Page 27
AC-DA
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NO. 4.0
PROCEDURE
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
DOC.REF
APPLICABLE
MECHANICAL WORKS (CONT’D) - Installation of gate Valve & Stop
ACSB/MECH/MS/
√
ACSB/MECH/MS/
√
ACSB/MECH/MS/
√
Valve - Air Conditioning Refrigeration Pipe Installation - Air Conditioning Pipe Insulation
NO. 5.0
PROCEDURE
DOC.REF
APPLICABLE
ELECTRICAL WORKS - Underground Pipe for
ACSB/ELEC/MS/
√
- Concealed Conduit in Floor Slab
ACSB/ELEC/MS/
√
- Concealed Conduit inside Brickwall
ACSB/ELEC/MS/
√
- Cable Installation & Termination
ACSB/ELEC/MS/
√
- Conduit (Exposed) Installation
ACSB/ELEC/MS/
√
- Conduit Junction Box Installation
ACSB/ELEC/MS/
√
- Lightning Protection System
ACSB/ELEC/MS/
√
- Earthing Installation for DB & DP
ACSB/ELEC/MS/
√
ACSB/ELEC/MS/
√
- Installation of Trunking
ACSB/ELEC/MS/
√
- Installation of Fan Hook
ACSB/ELEC/MS/
√
- Electrical, Telephone and TV Wiring
ACSB/ELEC/MS/
√
- TNB Metering Panel
ACSB/ELEC/MS/
√
Electrical/Telephone
- Electrical Distribution System Including Feeder Pillar Switch Board and Distribution Box.
PQP/00
Page 28
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
6.2.4 Inspection and Test Plan It describes all the approval, inspection and testing requirement relevant to a particular operation or element of work of the project, in the sequences that are carried out. Refer to Inspection and Test Plan Manual. (ACSB/PPR LTM/PQP/ITP)
Page 35
PQP/00
Page 29
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 30
AC-DA
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN 7.0
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
DOCUMENT AND DATA CONTROL The Project Manager and his Site Supervision are responsible for ensuring that all critical stages of the construction process are adequately supervised, and the quality of works meet the standards and requirements spelt out in the contract document and specifications. Method of construction proposed by us, especially for special construction process, shall be review/approved by the Project Manager, Consultant/Client to ensure that adequate quality control measures have been specified. Where equipment, such measuring instruments, is being used during the process such equipment shall be suitably serviced and maintained to ensure continuing process capability. The procedure ensures that incoming documents and data where appropriate are suitably reviewed before distribution, out-going documents are suitably reviewed and approved by authorized personnel before issue, that up-to-date are available to all who need them and that obsolete are removed or otherwise assured against use.
7.1
DOCUMENT AND DATA APPROVAL ISSUE The following categories of documents have an impact on the quality of the Project and are therefore controlled through a process of review, approval and documentation as described in the Quality Procedures. 7.1.1
Project Quality Plan This document is maintained and controlled by QA Manager who responsible for reviewing, updating and distributing it. This document including all amendments and revisions shall be approved by the Project Manager.
7.1.2
Project Related Document and Data The above category includes the following: i) Project Contract Documents ii) Project Drawing iii) Project Files iv) Site Records Procedures controlling the preparation, review and approval of these documents and data, where applicable, are spelt out in the Quality Procedures.
7.1.3
Other Quality Records Other quality document, such as quality training records, internal quality auditing records, management review records, quality system files etc should be properly kept, filed and maintained by the QA Manager.
PQP/00
Page 31
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN 7.2
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
DOCUMENT AND DATA CHANGES/AMENDMENTS The Quality Procedures also spell out the detailed procedures on how changes are to be made to the Quality System document and data of construction drawings.
7.3
DOCUMENTATION CONTROL A)
INCOMING/OUTGOING CORRESPONDENCE FILE CODE FILE CODE WAA
Incoming and Outgoing Correspondence from Architect Consultant
RMS
Incoming and Outgoing Correspondence from C & S Consultant
MCSB
Incoming and Outgoing Correspondence from M & E Consultant
AQSC
Incoming and Outgoing Correspondence from QS Consultant
ZA
Incoming and Outgoing Correspondence from Landscape Consultant
SC
Incoming and Outgoing Correspondence from Subcontractor
AUT KPKT
B)
TYPE OF FILE
Incoming and Outgoing Correspondence from Authorities Incoming and Outgoing Correspondence from Client
CONTRACT FILE CODE FILE CODE
PQP/00
TYPE OF FILE
LA
LA, CPC, CF (Client and Sub-Contractor)
IB
Insurance and Bonds
CD
Contract Documents
DLP
Defect Liability Period and Certificates (DLP)
Page 32
AC-DA CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
B)
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
CONTRACT FILE CODE (CONT’D) FILE CODE
C)
TYPE OF FILE
BQ
Bill of Quantities (BQ)
TA
Tenancy Agreement
SCG
Sub-Contractors Guarantees and Warrantees
MAL
Material Approval List and Certificates
EOT
Extension of Time
CIDB
CIDB (Expand as required)
PAYMENT FILE CODE FILE CODE FA
Final Account
CLAIM
Claim to Client
PAYMENT
D)
TYPE OF FILE
Payment to Sub-Contractor
VO
Variation Order Claims
PO
Purchase Order and Delivery Order (Expand as required)
TENDER FILE CODE FILE CODE QUOT TDK
PQP/00
TYPE OF FILE Suppliers Quotation Proposed Tender Documents (Expand as required)
Page 33
AC-DA CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN E)
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
TYPE OF FILE
SM
Minutes of Site Meeting
TM
Minutes of Technical Meeting
SCM
Minutes of Sub-Contractors Meeting
PROJECT FILE CODE FILE CODE
PQP/00
REVISION : 00
MINUTE OF MEETING FILE CODE FILE CODE
F)
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
TYPE OF FILE
SOI
Superintending Officer Instruction
SD
Site Directive
RFI
Request for Information
IR
Inspection Request
TR
Testing Report
PR
Project Progress Report
NCR
Non-Conformance Report
SF
Submittal Form
DIT
Drawing,/Information Transmittal Form
Page 34
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN G)
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
ADMINISTRATION FILE CODE FILE CODE LEAVE PETTY CASH
TYPE OF FILE Staff Leave Record Petty Cash
ASSET
Office Equipment Record
STAFF
Staff Report
BILL AD-MEMO
PQP/00
CONTROLLED DOCUMENT
Site Office Bill Memo to Staff/HQ
Page 35
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
SITE DOCUMENT CONTROL FLOW CHART Process Incoming Correspondence
Responsibilities Document Control/Clerk
START
RECEIVE CORRESPONDENCE
Document Control/Clerk
Document Control/Clerk
PROJECT MATTERS
DATE STAMP, REGISTER REFERENCE
-Do-
DUPLICATION OF DOCUMENT/CORRESPONDENCE
Clerk
DEFINE DISTRIBUTION ADDRES S
CIRCULATION TO RESPECTIVE SECTION MANAGER
ORIGINAL CORRESPONDENCE TO MASTER FILE
END
Project Manager
Project Manager
DEFINE ACTIONEE DISTRIBUTION
Project Manager
ACTIONEE
Department Clerk
SUBJECT FILE
Department Clerk
END
PQP/00
Page 36
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
SITE DOCUMENT CONTROL FLOW CHART Process Outgoing Correspondence
Responsibilities
START
DRAFT CORRESPONDENCE FOR APPROVED
ASSIGNED & REGISTER REFERENCE NUMBER
Document Control/Clerk
TYPING
Clerk
CHECK
Author
ACCEPTABLE
Author
INITIAL
Author
SIGNATURE
Project Manager
REGISTER
Document Control/Clerk
SUBJECT FILE
MASTER FILE
END
PQP/00
Staff
Document Control/Clerk Document Clerk
Page 37
AC-DA CAPITAL
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
INCOMING DRAWINGS WORK FLOW CHART
START
Received drawings from sender and check Drawings Transmittal against drawings
Are drawings receive complete/correct
Requested incomplete Drawings from sender/Inform incorrect drawings
Stamp “Date Received” on the Drawing Transmittal and return copy to sender. Stamp “Data Received” on every drawing received
Record drawings received on the Drawing Register. Distribute drawings to relevant personnel for action
Replace old drawings with current revision. Stamp “Superseded” on old drawings and keep them separately
Record and keep superseded drawings in the RECALL BOX
Maintain drawings as per Drawing Register
END
PQP/00
Page 38
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 39
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN 8.0
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MAINTENANCE OF INSPECTION, MEASURING AND TEST EQUIPMENT 8.1
In order to ensure that all equipment/instrument are in good condition to meet its accuracy, that equipment/instrument required calibration shall be done on regular basis or depending on their specified frequency.
8.2
The calibration exercise shall be performed by a organized independent body. The calibration reports shall be submitted to consultant for review. The attached flow chart showing how the calibration being handled.
8.3
The equipment/instrument should have valid calibration report prior to its usage.
8.4
Consultant shall verify on site that the calibrated equipment/instruments are being used.
8.5
The calibration certificate must be readily available at site and must indicate the following items: i) ii) iii) iv)
8.6
Date of the calibration done Date of the calibration required Validity period Serial no.
The list of the new equipment/instrument to be utilized on site shall be submitted to consultant from time to time together with the calibration reports.
PQP/00
Page 40
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
CONTROL OF INSPECTION, MEASURING AND TEST EQUIPMENT
ACSB Equipment/Instrument Calibrate
Consultant to witness when required
Recognized independent Body conduct
Calibration Report
ACSB submit calibration Report to consultant for review
Consultant to review and verify
If expired recalibrate
PQP/00
ACSB use the equipment/instrument on site
Equipment/Instrument Not usable
Page 41
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 42
AC-DA CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
9.0
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
INSPECTION AND TEST PLAN The Inspection and Test Plan or usually known as Inspection Request (IR) on the site will be prepared on trade of work basis. For list of ITP, please refer to the Section 16.0 in this PQP.
9.1
RECEIVING INSPECTION AND TESTING All our design calculations (from sub-contractors) shall be checked by the consultants for completeness to ensure that all requirements and standard specified have been complied with. Whenever material samples and shop drawings are received, they shall checked or tested and accepted by the S.O/C.O.W before being used on site to ensure that all requirements and standards are complied with. Items such as steel bars and structural timber product must be accompanied by the relevant Mill Certificate and SIRIM Certificate respectively.
9.2
IN PROGRESS AND FINAL INSPECTION, TESTING AND TEST RECORDS Prior to and during the construction process, the Project/Site Engineer and Site Supervisors are responsible for checking and inspecting all critical stages of the construction work to ensure all requirements are met. Shall notify the S.O/C.O.W at least 24hrs in advance prior to any inspection being carried out. Subsequently, the relevant work should also be inspected by the consultant’s representative for approval. All approvals and comments should be documented. Any comments that need to be action shall be carried out and also documented. The project engineer shall review all testing result or reports and the site supervisor shall keep the test records of every stage of the construction processes.
PQP/00
Page 43
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MATERIALS APPROVAL FLOW CHART Sub-contractor submit list of supplier/manufacturer with catalogue and samples
Client/ACSB/ Client/TRSB/ Consultant review
Factory visit when required OK OK
Supplier, Manufacturer test Report/Mill Certs during delivery
ACSB/ Consultant joint inspection for selected
Material approved for construction used
PQP/00
Reject Reject
Return
Separate or in Dumping Site
Page 44
AC-DA
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
EARTHWORK QA/QC FLOW CHART Description 1) Accept/contest
1) Survey Accept
Action person SC
No
2) All relevant parties to spot check
ACSB RMS SC
3) Boundary Identified
ACSB SC RMS
4) To check invert level (1L), Temp, Earth drain, Silt trap, Temp Culvert
ACSB RMS SC
5) Testing (Compaction Test)
5) Field density test (sand replacement method)-compaction test
SC RMS
6) As-Built surveyor
6) As built by license survey
2) Resurvey spot check
3) Site Clearing
4) Earthwork
PQP/00
SC
Page 45
AC-DA CAPITAL
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
CONCRETE WORKS QA/QC FLOW CHART Description 1) Check equipment calibrate report & all relevant report
Action RMS ACSB
Supplier (Batching Plant) yes
2) Design mix review and carry out cube test
RMS ACSB
No Design Mix Trial Mix yes yes
3) Review concrete 3) Review concrete material according to material according to specification specification
TRSB RMS ACSB
Concrete Materials
return No (Reject)
yes 4) Check concrete quality e.g slump test, structure ready for concreting – pre pour concrete checklist
RMS ACSB
5) Concrete finish & Cube test – post concrete checklist
RMS ACSB
Concrete Placing
No (Reject)
yes
Casted Concrete
Issued NCR
yes 6) End
PQP/00
Acceptance
Refer NCR flow chart
Page 46
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 47
AC-DA CAPITAL
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
10.0 PROCEDURES/METHOD OF STATEMENT REFERENCES The Method of Statement for this project is handled as follows: Preparation
- Sub-Contractors, Supplier and Site Engineer
Checking
- Project Manager
Approval
- Consultant/Client
For the latest list of Method Statement and Manuals, please refer to the Section 6.0 (6.2.3) this PQP and Work Method Statement (ACSB/PPR LTM/PQP/MS).
PQP/00
Page 48
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 49
AC-DA
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
11.0 HANDLING OF FEEDBACK, NON-CONFORMANCE, CORRECTIVE AND PREVENTIVE ACTION 11.1
OBJECTIVE To ensure that all feedback or complaints received from clients and staffs, all nonconformances detected during the various process, must be identified. Corrective and preventive proposed action shall be implemented in order to improve the quality system and to prevent recurrence of non-conformance.
11.2
SCOPE This procedure shall apply to all process in the project.
11.3
RESPONSIBILITIES All staffs are encouraged to provide feedback on the QA System. The Project Manager has overall responsibility for ensuring that all designed personnel are notified of nonconformance product situation and deal expeditiously with client’s complaint and ensure effectiveness of corrective action.
11.4
PQP/00
PROCEDURE 11.4.1
ACSB Project Management and consultants are encouraged to rise up nonconformance report (NCR) whenever notices/detected any non-conformance product or material in the project.
11.4.2
Copy of NCR will be forwarded to relevant sub-contractors and the subcontractor should propose corrective action in order to solve and prevent the same defect recurrent.
11.4.3
All Corrective Action Request (CAR) submitted by sub-contractors will be reviewed and evaluated by ACSB Project Management and relevant consultant.
11.4.4
Sub-contractor must include all corrective action requests together with Method Statement and material brochure if necessary.
11.4.5
When a corrective action request is agreed or approved. ACSB Project Management and consultant shall monitor and ensure that relevant CAR is done within the stated time stated. If CAR is not given within the time stated, Project Management shall extend the letter with a copy of NCR to the Director(s) of the relevant company.
11.4.6
ACSB Project Management and consultants shall inspect to verify that the CAR’s are completed and satisfactory signed by relevant parties hence closing the NCR.
11.4.7
All closed NCR must compile and accessible for every staff.
Page 50
AC-DA CAPITAL
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
FLOW CHART FOR THE CONTROL OF NON-COMPLIANCE REPORT Non Conformance Activity/Product Notice/Detect
ACSB Project Management Consultant
Sub-contractor
NCR Issue to Sub-contractor
Corrective Action Request (CAR) to be submitted within Agreed time frame Yes
ACSB Project Management Consultant
Review and evaluate Corrective Action Request (CAR)
No
Yes Sub-contractor Proceed with Corrective Action Yes ACSB Project Management Consultant
Returns to sub-contractor re do redial works
Inspect Corrective Action No
ACSB Project Management Consultant
Yes Project Eng. Manager and Consultant approved and closure of NCR Yes NCR is closed and filed
PQP/00
Page 51
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 52
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
12.0 MAJOR PLANT AND MACHINERY SCHEDULE The Major Plant and Machinery Schedule shall be submitted in due course.
PQP/00
Page 53
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 54
AC-DA
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
13.0 MEETING AND ATTENDANCE The meeting for this project shall be check as follows: NO
MEETING
FREQUENCY
1)
Client
Every Month
2)
Sub-con Coordination Meeting
Weekly
3)
Safety and Health Committee Meeting
Every Month
4)
Technical Meeting
Every Month
5)
Staff Meeting
Every Month
The minutes of meeting for the above shall be documented at the site office.
PQP/00
Page 55
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 56
AC-DA
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
CAPITAL
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
14.0 LIST OF QUALITY RECORDS The List of Quality Records is as follows: NO
QUALITY RECORDS
MAINTAINED AT SITE BY
RETENTION PERIOD
1)
All Correspondences
PM
7 Years
2)
Project Quality Plan
PM
7 Years
3)
Inspection and Test Data
QA/QC
7 Years
4)
Calibration Data
QA/QC
7 Years
5)
Specification
QA/QC
7 Years
6)
As Built and Structural Drawings
QA/QC
7 Years
7)
NCR Report
QA/QC
7 Years
8)
Internal Quality Audit
QA/QC
7 Years
9)
Site Meeting Minutes
PM
7 Years
10)
Request for Inspection
QA/QC
7 Years
11)
All Checklist for Inspection
QA/QC
7 Years
12)
Post Concreting
QA/QC
7 Years
13)
Other files
PM
7 Years
REMARKS
* Upon completion of the project, all Quality shall be sent for storage by the Human Resources Department to an appointed third party store.
PQP/00
Page 57
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 58
AC-DA CAPITAL
CONTROLLED DOCUMENT
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
15.0 FORMS AND CHECKLIST 15.1 FORMS (CLIENT/CONSULTANT) NO.
DESCRIPTION
DOCUMENT REFERENCE
1.
Architect’s Instruction/ Superintending Officer Instruction
KPKT/PPRLTM/PQP/F01
2.
Architect’s Instruction/ Superintending Officer Recommendation
KPKT/PPRLTM/PQP/F02
3.
Drawing/Information Transmittal Form
KPKT/PPRLTM/PQP/F03
4.
Site Directive
KPKT/PPRLTM /PQP/F04
5.
Request For Information
KPKT/PPRLTM /PQP/F05
6.
Non Conforming Report
KPKT/PPRLTM /PQP/F06
7.
Inspection Request
KPKT/PPRLTM /PQP/F07
8.
Notification of Potential Change
KPKT/PPRLTM /PQP/F08
9.
Submittal Form
KPKT/PPRLTM /PQP/F09
10.
Sample Identification Tag
KPKT/PPRLTM /PQP/F10
11.
Shop Drawing Register
KPKT/PPRLTM /PQP/F11
12.
Meeting Attendance
KPKT/PPRLTM /PQP/F12
15.2 FORMS (ACSB) NO.
DESCRIPTION
DOCUMENT REFERENCE
1.
Request For Inspection
ACSB/PPRLTM /PQP/F01
2.
Request For Information
ACSB/PPRLTM /PQP/F02
3.
Change Design Form
ACSB/PPRLTM /PQP/F03
PQP/00
Page 59
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
15.3 CHECKLIST’S LIST (ACSB) NO.
TYPE OF WORKS
APPLICABLE
1.00
Architect Checklist
1.01
- Anti-Termite Works Inspection
√
1.02
- Brickworks Inspection
√
1.03
- Aluminium and Glazing Works
√
1.04
- Ceiling Works
√
1.05
- Cement Screeding Works
√
1.06
- Door and Window Works
√
1.07
- Floor Tiling Inspection
√
1.08
- Panting Works
√
2.00
Civil And Structure Checklist
2.01
- Excavation Works
√
2.02
- Installation Of Reinforced Earth Wall
√
2.03
- Rebar Testing Before Fabrication
√
2.04
- Cast In-Situ RC (Pre-Concreting) Inspection
√
2.05
- Cast In-Situ RC (Post-Concreting) Inspection
√
2.06
- Concreting Works Inspection
√
3.00
M&E Checklist
3.01
- AC Pipework inspection
√
3.02
- Cold Water Plumbing Inspection
√
3.03
- Conduit, Trunking and Cable Tray Inspection
√
3.04
- Hot Water Plumbing Inspection
√
3.05
- Lightning and Small Power Inspection
3.06
- Sanitary Plumbing Inspection
4.00
Material Checklist
PQP/00
√ √ √
Page 60
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN NOTE : The copyright of this Project Quality Plan Belongs to Acda Capital Sdn Bhd. Photocopying, reproduction and/or unauthorized distribution of any page, or part of, or the whole of this Project Quality Plan is prohibited. Acda Capital Sdn Bhd shall not be held responsible or any consequences that may or will arise from such sets. Only official holders of ‘Controlled Copiers’ will be notified of any revisions made to the Project Quality Plan.
PQP/00
Page 61
AC-DA CAPITAL
ACDA CAPITAL SDN BHD
MEREKABENTUK, MEMBINA DAN MENYIAPKAN 100 UNIT RUMAH TERES SATU TINGKAT DAN KERJA-KERJA BERKAITAN BAGI PROGRAM PERUMAHAN RAKYAT (PPR) DI LADANG TANAH MERAH PORT DICKSON, NEGERI SEMBILAN UNTUK KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN
CONTROLLED DOCUMENT REVISION : 00
DOC. REF.: ACSB/PPR LTM/PQP EFFECTIVE DATE : 16TH APRIL 2015
16.0 LIST OF INSPECTION AND TEST PLAN ITEM ITP 1 ITP 1A
DESCRIPTION Material
ITP 2 ITP 2A ITP 2B ITP 2C ITP 2D ITP 2E ITP 2F ITP 2G ITP 2H
Architectural Works Brick Work Tiling Work Ceiling Work Door & Window Painting Plastering Sanitary Screeding
ITP 3 ITP 3A ITP 3B ITP 3C
Structural Works Concrete Cube Test Pre-concreting Inspection Post-concreting Inspection
ITP 4 ITP 4A ITP 4B ITP 4C ITP 4D
Mechanical & Electrical Works Plumbing Works Air Conditioning Works Fire Protection Works Electrical Works
ITP 5 ITP 5A ITP SB ITP 5C ITP 5D ITP 6D
Civil Works Drainage Works Earthwork Roadwork Sewer Line Works Water Reticulation Works
ITP 6 ITP 6A ITP 6B
Final Inspection & Testing Final Inspection & Testing of Building / Civil Works Inspection and Test by Authorities
Inspection & Test of Materials
Note: Please refer to ACSB/PPR LTM/PQP/ITP for further reference.
PQP/00
Page 62
View more...