09600_2

Share Embed Donate


Short Description

09600_2...

Description

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 1 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

PROJECT QUALITY PLAN

2 1

Approved for Implementation (ref.Transmittal 45283-KS-T-00350) Re issued for approval -revised as indicated (ref.Transmittal 45283-KS-T-00201 & letter 45283/KS/L/00103 )

F.Menichini F.Menichini

A.Castagna G.Raimondi A.Castagna G.Raimondi

0 B

Approved for Implementation (ref.Transmittal 45283-KS-T-00116) Re-issued for Approval-Incorporated comments (ref. letter 45283/KS/T/00021)

F.Menichini F. Menichini

A.Castagna G.Raimondi 21.09.10 A.Castagna G. Raimondi 16.08.10

Issued for Approval

F. Menichini Prepared

A.Castagna G. Raimondi 15.07.10 Checked Approved Date

A Rev.

Description

23.11.10 19.10.10

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 2 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

CONTENTS 1.

2.

3.

4.

5.

6.

7.

SCOPE AND FIELD OF APPLICATION

4

1.1.

General

4

1.2.

Work Scope

4

REFERENCE

5

2.1.

CONTRACTOR’s Reference Documents

5

2.2.

Contractual Reference Documents

5

TERMS AND DEFINITIONS

6

3.1.

Definitions

6

3.2.

Abbreviations

6

QUALITY MANAGEMENT SYSTEM

8

4.1.

Processes in project activities

8

4.2.

Documentation requirements

8

MANAGEMENT RESPONSIBILITY

12

5.1.

Management commitment

12

5.2.

COMPANY focus

13

5.3.

Project quality policy

13

5.4.

Project Quality objectives

14

5.5.

Project organisation: functions and responsibilities

14

5.6.

Project Management review

14

RESOURCE MANAGEMENT

15

6.1.

Human resources

15

6.2.

Personnel training & Induction

15

6.3.

Training of Company Personnel

16

PROJECT EXECUTION

17

7.1.

Planning of project execution

17

7.2.

COMPANY-related processes

20

7.3

Design and development

21

7.4.

Procurement

23

7.5.

Production and service provision

26 Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

8.

Sh. 3 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

7.6.

Subcontracts qualification & control

30

7.7.

Quality Control and inspection activities during construction phase

30

7.8.

Control of monitoring and measuring equipment

32

7.9.

Constructability review

33

MEASUREMENT, ANALYSIS AND IMPROVEMENT

35

8.1.

General requirements

35

8.2.

Monitoring and measurement

35

8.3.

Control of nonconforming products

36

8.4.

Data analysis

37

8.5.

Improvement

37

ANNEXURE 1 – LIST OF CORPORATE CONTRACTOR’S PROCEDURES

39

ANNEXURE 2 – LIST OF PROJECT PROCEDURES (TO BE SUBMITTED FOR KOC REVIEW AND APPROVAL)

40

ANNEXURE 3 – QA/QC PERSONAL

49

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 4 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

1.

SCOPE AND FIELD OF APPLICATION

1.1.

General This document defines the project Quality management system applied by the CONTRACTOR for realisation of Building New Booster Station BS-171 in West Kuwait. This Project Quality Plan is base referenced on Contractor's corporate Quality Management System Manual: • to provide consistent product that meets Company requirements, • to address Company satisfaction through the effective implementation of the system with operations for continual improvement and prevention of non conformity. In particular it specifies the Quality requirements to be applied to the project activities, the organisational structure (functions and responsibilities) implemented for the project, the multidisciplinary design reviews and the Quality audits to be conducted both in the home office and at site to achieve the Quality objectives of the project. Every control will be exercised by the project management to achieve the Quality objectives and to focus attention on prevention of nonconformities.

1.2.

Work Scope The Contractor shall construct the Facilities and supply all Materials, manpower and other resources; provide quality assurance services and all other requirements to provide the Company with complete operable Facilities in accordance with the Contract. The detailed work scope will be in accordance to the contract and is appendix: “APPENDIX E Scope Of Work and Description of Services” The Works shall include all necessary operations and services to complete and commission the Facilities and any associated work in accordance with the Contract

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

2.

Sh. 5 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

REFERENCE ISO 9000 ed. 2005 ISO 9001 ed. 2008

Quality management systems - Fundamentals and vocabulary; Quality management systems - Requirements.

Applicable industry KOC Contract documents and Company Standards, Project specifications and applicable International Codes & Standards. 2.1.

CONTRACTOR’s Reference Documents POL-SPA-QUAL-001

Quality Policy

GP-SPA-QUALON-005

BU ONSHORE (QUALITY) MANAGEMENT SYSTEM MANUAL Doc. NO. KOC-Q-014 – Project QA/QC Requirements The complete list of documents is given in Annexures -1 and 2. 2.2.

Contractual Reference Documents General Conditions of Contract for Lump Sum Turnkey Projects Appendix D, Project Administration and Coordination Procedure Appendix E, Scope of Work and Description of Services Doc. NO. KOC-Q-014 – Project QA/QC Requirements

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

Sh. 6 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan

Contract No. 45283

Unit: General

3.

TERMS AND DEFINITIONS

3.1.

Definitions (the below definition are in respect the term established on General Condition of Contract clause 1) • COMPANY: as defined on GCC clause 1 )

3.2.



CONTRACTOR: as defined on GCC clause 1 )



Contract: Contract between COMPANY and CONTRACTOR with all Annexure and Attachments (GCC clause 1 )



Construction subcontractor: organisation that is engaged by the CONTRACTOR to perform the erection and construction works with relevant inspections, examinations and tests



Work: All the work and services to be performed by the CONTRACTOR as set out in the Contract. (GCC clause 1 )

Abbreviations Project positions (*Key personnel indicated on attachment 14 of Technical Proposal clause 4), due to the split between Home office and Site the sub clause are not in sequence. The abbreviations don’t represent the totality of Project’s role.

1

PM DPM TM PE 1 PCM

-

HSEM PQM PPRM CA COM

-

DC DCC DTM MM PLE PLL

-

PPL PSL

-

Project Manager (Project Manager clause 4.1*) Deputy Project Manager Technical Manager (Engineering Manager clause 4.2*) Project Engineer (clause 4.3*) Project Control Manager (taking duty also of Planning and scheduling Engineer clause 4.4*) Project HSE Manager (clause 4.6*) Project Quality Manager (clause 4.7*) Project Procurement Manager (clause 4.8*) Contract Administrator (Contracts Manager clause 4.10*) Commissioning &Training Manager (Pre-commissioning/ commissioning engineer clause 4.14*; Training Manager clause 4.5*) Document Controller Document Control Coordinator Deputy Technical Manager Material Manager (Material Control Manager clause 4.9*) Project Planning and scheduling Engineer Project Loss Prevention and Environment Leader (Lead discipline Engineer clause 4.12 *) Project Process Leader (Lead discipline Engineer clause 4.12 *) Project Specialist Leader (Lead discipline Engineer clause 4.12*)

For this project PE duties and responsibilities are in charge at TM Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 7 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

Site organisation CM DS FEM FMMS

-

QCS WES

-

Construction Manager clause 4.11* Discipline Superintendant Field Engineering Manager (Lead construction Engineer clause 4.13*) Field Material Management Superintendent (Material Control Manager clause 4.9*) Field Quality Control Supervisor Welding Supervisor

Other abbreviations EPC Engineering, Procurement, Construction IDS Inspection data Sheets ITP Inspection and Test Plans CAR Corrective action request WBS Work Breakdown structure TQ Technical Query CR Concession Request DR Deviation Request VO Variation Order Organisation Departments PROC 2 Procurement HSE Health, Safety and Environment QUAL Quality CONSTR Construction ICT Information and Communication Technology PCON Project Control CAON Contract Administration

2

For this Project PROC is used replacing APR in all applicable Operating Procedures Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 8 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

4.

QUALITY MANAGEMENT SYSTEM

4.1.

Processes in project activities The work processes defined for the project activities are as per “APPENDIX E- Scope of work and description of services” : •

Project Management Services



Design Engineering Services



Procurement Services



Subcontracting Services



Construction Services



Quality Assurance Services



Temporary Services for Company



Training of Company Personnel



Health, Safety and Environmental (HSE) Services

4.2.

Documentation requirements

4.2.1.

General requirements The documentation includes:

4.2.2.



Contractual documents;



Project planning and control documents;



Technical and construction documents;



Purchasing and subcontracting documents;



Quality records;



Correspondence with the COMPANY, Vendors, subcontractors, etc.



Internal communication;



Minutes of meetings and reports.

Quality Manual The CONTRACTOR’s ‘BU Onshore (Quality) Management System Manual’ (GPSPA-QUALON-005) constitutes the base reference for the Project Quality Plan which defines how the CONTRACTOR’s Quality management system finds application in operational projects. The Quality Plan issuing methods are described in chapter 7.1.7.

4.2.3.

Control of documents Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 9 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

Reference documents like codes. Standards, specifications. Project specification Documents, etc. which controls activities effecting quality shall be readily available to related personnel. The latest revision of the applicable Project documents shall be made available at all activity locations. a) Document management during engineering phase The methods for preparing and identifying project documents, including those produced by the vendors of material and services, are indicated in the project procedure 000-ZA-E-09003 “Project coding and numbering procedure”. Project documents (specifications and drawings) are managed according to OPR.GM.XE.5013 “Project Documents Control” utilising a software application called Engineering Integration Manager (EIM). The above software application manages both the issue and the revision of all project documents and the storage of electronic files. Any changes to documents are formalised according to 000-ZA-E-09003 “Project coding and numbering procedure”. Changes to documents shall be verified and approved by the same functions that performed the original review and approval, using the same work instructions as described in Chapter 7.3.5. b) Document management during construction phase. On site, technical documents are managed according to the instruction given in project procedure 000-ZA-E-09000 “Project coordination/administration procedure between Company and Contractor”. c) Document management during Close-out phase.

Pre-commissioning and Commissioning and

The CONTRACTOR shall keep a copy of “as-built” drawings as indicated in the project procedure 000-AZ-E-02018 “As-built drawings procedure”. d) Document Control processes Document control processes will be manage in accordance to the requirements of Appendix “D”. Explanation of the document control processes is explained on Document Control Project procedure 000-ZA-E-09806 and monitored by the Document List and Drawing Register Status Report 000-ZA-E-09804 which as an extraction of EIM EDMS system gives the status on update time of the handover of project documentation The procedure 000-ZA-E-09806 outline the measures that has be established by the Contractor to control the issuance, retrieval and revision of documents (e.g. drawings, procedures and instructions) including changes to such documents and in which way the Participating organizations, site included, shall have in their possession procedures for control and revision of such documents to preclude the possibility of using outdated or inappropriate documents in the performance of the Works.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

4.2.4.

Sh. 10 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

Project record Books Project record book will be manage in accordance to the “Appendix D, clause 10 & 11”. A complete set of Project records and books shall be prepared by the Contractor during the period between the Date for Commencement and the date of Turnover. These documents shall be prepared to represent the Facilities in the as-built condition and shall be supplied to the Company sixty (60) days prior to Construction Completion of the whole or a Portion of the Facility. The Contractor shall prepare approved Vendor prints and data for inclusion into the Project Records Books as required by Clause 10 entitled “Project Records and Manuals.” Project records are managed according to the following table:

Normative reference (UNI EN ISO 9001:2008) 6.2.2 – Competence, awareness and Training 7.1 – Planning of product realization 7.4 – Purchasing Process

Document Curriculum Vitae – Training Induction and participants’ lists Engineerining Programme – Construction programme – Procurement programme Vendor list - Vendor prints and data

Responsibility PM TM/ PPRM/ PCL

PPRM / PSL

7.2.2 – Review of requirements related to the product 7.3.2 – Design and development inputs 7.3.4 – Design and development review 7.3.5 – Design and development verification 7.3.6 – Design and development validation 7.3.7 – Control of design and development changes 7.5.2 –Validation of processes for production and service provision 7.5.3 – Identification and traceability 7.5.4 – COMPANY property

Project Execution Plan

PM

General Design Criteria

TM

7.6 – Control of monitoring and measuring devices 8.2.2 – Internal audits 8.2.4 – Monitoring and measurement of products 8.3 – Control of nonconforming products

Monitoring and measurement device records Audit report Quality control report

8.5.2 – Corrective actions

Minutes of design review meeting

PPL/PSL/PLL

Calculation printouts, check lists

PPL/PSL/PLL

Final project report

PM

Design change record

TM

Specifications for special process recording requirements

PSL

Material traceability list Spool and traceability map Anomaly records

DS WES PM

Nonconformity reports: • Materials (QCF NC register) • Audit report (RNC) • Site (NC register) Audit report, non conformity report

MM/DS PQM MM/DS/QCS

MM PQM QCS MM/PQM QCS Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 11 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

Normative reference (UNI EN ISO 9001:2008) 8.5.3 – Preventive actions

Document Lessons learnt, Audit report HAZOP study

Responsibility Corporate Depts. HSE

The PM keeps a record of the COMPANY complaints. Once the complaint has been examined and the necessary corrective action implemented, both the complaint and the corrective action records are filed together with the project documentation.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 12 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

5.

MANAGEMENT RESPONSIBILITY

5.1.

Management commitment The Management shows its commitment by developing the activities through PM and DPM. The Management responsibility are defined on Contract document: Appendix “E” clause 2 , Project management Services •

Communicating to the functions involved in the project, the importance of complying with contractual and applicable regulatory requirements;



Establishing the Project Quality policy;



Provide all necessary fully qualified and experienced personnel to interface with the COMPANY and manage the Works including, but not limited to, the following: - Pursuant to Clause 33.6 of the General Conditions of Contract provide a fully qualified and experienced project manager acceptable to the Company who shall not be changed without prior written consent of the Company. - Establish an organisation acceptable to the Company fully capable of performing the Works. Office Organisation Charts shall be provided to the Company, as specified in Clause 33.3 of the General Conditions of Contract within fourteen (14) days from Date for Commencement of the Contract. Site Organisation Chart shall be provided to the Company, as specified in Clause 33.4 of the General Conditions of Contract no later than thirty (30) days prior to assigning construction personnel to the Site (including its design support team in Kuwait) - Develop and provide to the Company an acceptable execution plan which shall clearly illustrate the Contractor’s understanding of the Works and the timely completion of the Facilities. This Plan shall include complete Coordination Procedures within the Contractor’s organization and with the Company for each phase of the Works and incorporate all requirements of Appendix D (Project Administration and Coordination Procedure). - Provide a project controls team which shall develop the necessary schedules and plans for all phases of the Works and accurately monitor progress against the schedules and plans in accordance with the requirements of Appendix D (Project Administration and Coordination Procedure). The Team shall coordinate with the Company’s project controls team to ensure compatibility of reporting with that of the Company. - Prepare Monthly Progress Reports for presentation to and discussion with the Company. The Reports shall highlight all critical issues. Monthly Progress Reports shall be issued no later than the seventh (7th) day of the following month and shall incorporate all the requirements of Appendix D, Clause 6, “Project Reports.” - Responsibility for all management of its Vendors, and Subcontractors, as necessary, to achieve expeditious completion of the Facilities in accordance with the Contract.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 13 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

- Assist the Company in the coordination with other Company’s contractors whose scope of work directly relates to the Works. - Designate an Executive Sponsor for the Project. The Executive Sponsor shall be an executive of the Contractor, from the Contractor’s home office, who will be available to the Superintendent for the resolution of problems. The Executive Sponsor shall not be the Project Manager. 5.2.

COMPANY focus The needs and expectations of the COMPANY are satisfied by means of:

5.3.



Compliance with contractual requirements defined by the COMPANY, with the regulatory, safety and environmental requirements and with those requested by other partners of the CONTRACTOR;



Communication to the functions concerned regarding the above requirements and their involvement in the same;



Focusing on the improvement of work processes.

Project quality policy The Quality policy implemented by the CONTRACTOR during project execution aims to ensure that the products and services meet the needs and expectations of the COMPANY and conform to the Quality requirements established for the project, including applicable norms, specifications, legislation, instructions and regulations, particularly those concerning occupational health, safety and environmental conservation. This Project Quality Plan is issued in compliance with the requirements of the COMPANY and the ISO 9001:2008 standard and is in conformity with the CONTRACTOR’s Quality management system. The Quality objectives defined herein can be measured and reviewed by the Management for continual improvement of the project work processes. The CONTRACTOR shall define the responsibilities and authorities of key personnel and assign qualified and competent resources to achieve Project Quality objectives. The PM of the CONTRACTOR shall take all the necessary actions to implement the Project Quality policy throughout project execution. This Project Quality Plan documents the Project Quality Management System, resources and the work processes to be adopted in the project. The responsibility of preparation of the Project Quality Plan is entrusted to PQM, to whom the Management has awarded the necessary authority, freedom and support. The PM, in cooperation with the permanent organisation, is responsible for the implementation of continual improvement of the system in order to achieve COMPANY satisfaction and the established objectives.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

5.4.

Sh. 14 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

Project Quality objectives The Project Quality objectives are: •

Comply with KOC International Codes Standards and Specification as well the Industry Good Practices;



Absence of COMPANY complaints;



Absence of serious nonconformities;



Schedule Compliance

The achievement of Quality objectives is entrusted to all the persons involved in the project. 5.5.

Project organisation: functions and responsibilities In accordance to COMPANY requirements expressed on Key personnel indicated on attachment 17 of Tender Document, clause 4, CONTRACTOR will provide all the necessary key project positions. The key project positions, while remaining under the direction of their department manager, shall operate to achieve the project objectives, according to the instructions of the PM. The PM supervises all aspects of project execution and represents the CONTRACTOR in front of the COMPANY. The departments of the permanent structure of the CONTRACTOR are responsible for ensuring the conformance of their activities/products to Quality standards. They are also responsible for the technical accuracy of documents and for all the activities within their discipline such as technical assistance to inspections and tests, construction, pre-commissioning, commissioning, etc. The home office and site organisations, along with the functions and responsibilities, are detailed in the project procedure 000-ZA-E-09602 “Project office and site organisation charts with job descriptions”, this include also Project QA/QC function and responsibilities and Charts showing the compliance for personnel mobilization. List of QA/QC personal is shown in annex 3. Construction Subcontractor detailed QA/QC organization chart will be included on document 000-ZA-E-09606 Subcontractor Project Quality Plan issued by Construction Subcontractor and subject to CONTRACTOR and COMPANY approval.

5.6.

Project Management review The Project Quality management system is reviewed regularly by the Management and recorded for future reference and actions. The review is based on feedback from the projects in terms of problems encountered, inconsistencies and their causes, conformity of purchased products, effectiveness of work methods and organisational structures, audit reports and project records.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 15 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

6.

RESOURCE MANAGEMENT

6.1.

Human resources All personnel assigned to the project shall have correct profile in terms of skills and capabilities as per clause 5.3 of KOC-Q-014. The Responsibility of assigning adequate resources to the project is with the CONTRACTOR’s department managers. The responsibly of mobilizing adequate resources required by all the subcontractors to execute the contract Scope of work is whit the contractor. Employee's performance evaluation shall be conducted regularly to identify the necessary training requirements to meet the skill levels required for their designated works. The records attesting the competence, responsibilities and authority of the resources assigned to the project are filed by the CONTRACTOR’s department managers.

6.2.

Personnel training & Induction CONTRACTOR’s Department Managers ensure that positions within the CONTRACTOR are filled by resources with the correct profile in terms of skills and capabilities. This activity is achieved by implementing dedicated personnel training and education of the individual, consistently with the professional development objectives defined. Training records shall be maintained. At the beginning of Project a specific Induction to the Quality System applied to the project with the explanation of content of the Quality Project Plan is given to all the personnel involved in the project, who shall fully comply with the requirements and procedures indicated herein. The competence, responsibilities and authority of the resources assigned to the project are guaranteed through quality audits scheduled in the “Quality Assurance activities and Audit Plan” Doc N. 000-ZA-E-09603. CONTRACTOR will include specific Project Quality requirements in Subcontractors contract, in order to made resources aware that their work activities contribute to the achievement of quality objectives.

6.2.1.

Competence, awareness and training All personnel assigned to the project will have received professional training and have experience in accordance with corporate operating procedure OPR.RD.XB.5020 – “Personnel training”. It is the responsibility of the PM to ensure that all personnel assigned to the Project are qualified by training and/or experience and are familiar with COMPANIES to perform the tasks assigned to them. The personnel awareness of the relevance and importance of their activities, it is guaranteed with the specific project quality training. In the beginning of the Project a quality training is held with all the Project team to illustrate all the aspects treated on the Project Quality Plan for the fully understanding of the information contained, particular attention is given to all the Contract requirements that may be constitute a deviation from the normal practice of works or Corporate Procedures and for these a Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 16 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

specific Project procedures are issued. For this reason a training program is developed and relative Attendee records maintained. 6.3.

Training of Company Personnel The Contractor shall in accordance with Clause 36.0 of the General Conditions of Contract and the requirements expressed on Appendix E clause 9 prepare a training programme, “000-ZA-E-79002 Training of Company personnel programme”. Contractor in conjunction with its Subcontractors and approved manufacturers and Vendors, prepare, develop and carry out a specialist training programme to impart all necessary skills and knowledge to a certain number and category of the Company’s Operation and Maintenance personnel. Any request for quotations and purchase orders shall stipulate the training requirements to be provided by the Vendor in fulfilment of the Contractor training responsibilities. The training shall be carried out in Kuwait as specified in Appendix E in accordance with the approved training programme and shall be completed prior to, and as a condition precedent to, the issue of the Construction Completion Certificate of the relevant Portion or the whole of the Facilities

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 17 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

7.

PROJECT EXECUTION

7.1.

Planning of project execution

7.1.1.

General requirements The Contractor shall arrange the Project pre Inspection meeting (PPIM), Construction Pre-Inspection Meeting (CPIM) and Vendor Pre-Inspection Meetings (VPIM) requirements in accordance with the agenda detailed in c1ause 6.0 of KOC-Q-014 Rev 1 The project planning and project control strategy are the responsibilities of the PM. The DPM verifies all the project control documents, the PM approves all the project control documents. The PCM reviews the requirements contained in the contractual and tender documents regarding project control, and participates in defining the strategies for project execution and control. In cooperation with all the project positions and in consultation with CONTRACTOR’s permanent structure of PCON, the PCM defines the “Work Breakdown Structure” (WBS) that takes into account the contractual aspects and the constraints involved in the development of the activities. The WBS is transversal to all project activities and is defined to meet the fundamental needs of all the involved functions. The PCM prepares the document that defines the WBS and submits it to the PM for check and approval before issue. During this activity, the basic considerations for the project realisation plan are finalised and the project procedure 000-ZA-E-09800 “Planning and scheduling procedure” is issued. The detailed “Project overall contract CPM Schedule (LEV 3)” 000-ZA-E-09853, based on the contractual dates, is prepared by the PCM with the assistance of all discipline leaders; then it is verified by DPM and approved by the PM and transmitted to the COMPANY. After verifying the contractual requirements and the project development plan, CONTRACTOR also prepares the following project procedures:

7.1.2.



000-ZA-E-09801 “Project physical progress measurement procedure”;



000-ZA-E-09802 “Reporting procedure”;



000-ZA-E-09803 “Progress measurement system for invoicing procedure”



000-ZA-E-09002 “Variation order procedure”;

Occupational health and safety requirements The project procedure 000-ZA-E-85822 “HSE manual for construction” is issued by HSE department

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

7.1.3.

Sh. 18 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

HSE CONTRACTOR shall issue a " Overall Project HSE Management plan" doc. No. 000ZA-E-85800, in compliance with the project requirements, regarding health, safety and environmental conservation. The plan, prepare by HSE Manager and approved by Project Manager, describes the HSE activities to be performed for the project under the HSEM responsibility; it is a “living document” and will remain in force throughout the complete project cycle. A Projects HSE Philosophy specification, doc No. 000-ZA-E-85820 shall be issued for the project, containing contractual requirements, international standards to comply with during the project design. According to contract, the following review, under HSE responsibility, is foreseen: Hazard & Operability (HAZOP) review, to be led by a third party Chairmen, with the participation by COMPANY and CONTRACTOR. Project HSE Reviews, to be led a third party Chairmen, on the design solutions versus HSE requirement compliance.

7.1.4.

Technical-organisational coordination The exchange of documentation and information between the Contractor and the COMPANY takes into account the following: •

Contractual clauses;



Type of contract and scope of work;



Project complexity.

Particular attention is paid to the contractual clauses that affect the relationship among the parties. All the key positions of the project organisation take part in this activity. Finally all contractual communication shall vetted by CA before final issuance. In the project procedure 000-ZA-E-09000 “Project coordination/administration procedure between COMPANY and CONTRACTOR” the following points are defined: •

General information (project name, job number, parties involved specifying their tasks and mutual relationship, documents to be considered, names of persons representing the parties involved, choice of language);



Method of communication used in the correspondence (letters, fax, transmittal), verbal messages and telephone calls, meetings and possible electronic connections;



Design documents (method of identification, recording, management, transmission for approval, comments or information, filing and delivery to the COMPANY);



Purchasing documents;



Quality management documents;



Commercial and Contractual documents;



Variation request;



Turnover adjustment documents Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

7.1.5.

Sh. 19 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General



Documents related to Notification and COMPANY approval



Information (unless specified in other items) related to planning, cost control, order changes, etc;



Confidentiality requirements.

Material inspection and testing plan All purchased equipment, machineries, material and components are classified according to their inspection level. This activity is carried out immediately after the Process Flow Diagram (PFD) for primary and secondary systems and the Heat & Material Balance have been issued. This classification is required to produce the Inspection Data Sheet (IDS) and to optimise the resources to be employed in control and surveillance activities during the manufacturing of the purchased product. It is defined in the project procedure 000ZA-E-09001 “Project material classification ”.

7.1.6.

Project “Information & Communication Technology” (ICT) System The ICT system is defined following contract review and during project planning. It defines the methods and responsibilities for the implementation of information activities and voice/data transmission. The ICT resources (processing and communication systems, base and application software) and ICT standards (for example, file formats) to be used in the project and in relations with the COMPANY and third party organisations such as Vendors, Construction subcontractors and Partners, shall be identified and included in the project procedure 000-ZA-E-09005 “General specification for project information and communication technology (ICT) system”.

7.1.7.

Project quality plan All planned project activities are documented in the Project Quality Plan which is defined after the review of contractual documents. The PQM, assisted by the competent positions of the project organisation, prepares and issues the Project Quality plan based on the PM instructions. PQM ensures its conformity with applicable elements of the CONTRACTOR’s Quality management system and with the contractual requirements, The Project Quality Plan is verified by the QUAL Department manager, approved by the PM and distributed to everybody in the project organisation, distribution to all the project organization and Subcontractor is performed, as all the other documentations, in accordance to the project procedure 000-ZA-E-09806 “Document Control procedure” EIM and in accordance to the distribution matrix defined in EDMS system. Once approved by Company a general review of the PQP will take place every six month, if not significant modification arouse in the meantime, PQP will always revise in case of modification that may need after Audits results which clearly define a better assessment of the Plan.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 20 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

7.2.

COMPANY-related processes

7.2.1.

Determination of project requirements The project requirements are specified by the COMPANY in the contract including the regulatory ones.

7.2.2.

Review of contractual documents In the initial phase of the project, the contractual documents are reviewed by the project positions within their specific competence. The contractual documents include: a) documents related to management, economic and financial aspects such as: contract, scope of work, prices, penalties, financing, insurance, legal aspects, obligations of the CONTRACTOR and COMPANY, commercial agreements such as joint ventures, pre-bidding agreements, letters of intent, licensing agreements, confidentiality agreements, etc.; Following the review of the management, economic and financial documents, the document “Project Management Data” is issued; the document details the contractual requirements and constraints, and indicates the problems, criticalities, choices, fundamental strategies and operating plans defined for the project. This document shall be prepared by PM. It shall be issued for internal use only and hence shall not be recorded in the project documents. b) Technical documents: drawings and specifications block diagrams, other diagrams, technical data, environmental information, programs, codes, standards, regulatory laws and regulations. Following the review of the technical documentation, the documents “General “Design Criteria” are issued; these documents compile the input basic design data to carry out project engineering activities (see par. 7.3.2).

7.2.3.

Contract amendments As the outcome of Contract Technical Review any amendments to the contract shall be treated according to the contract specifications and with the project procedure 000-ZA-E-09002 “Variation order procedure”. Following COMPANY approval, the amendment becomes an integral part of the contract and the PM informs the parties involved and gives the authorisation to proceed accordingly. In case of disputes between the CONTRACTOR and the COMPANY, the matter is treated according to provision of Contract.

7.2.4.

COMPANY communication The tools used to communicate with the COMPANY, including the documents to be submitted for approval, review and information, are listed in the project procedure 00ZA-E-09000 “Project coordination/administration procedure between COMPANY and CONTRACTOR”.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 21 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

7.3

Design and development

7.3.1

Design and development planning The design and development phases are identified on the basis of: •

Design input;



Design output;



Design review;



Design verification;



Design validation;



Control of design changes;

as detailed in the following paragraphs. 7.3.2.

Design input Following the contract review, the project procedures •

171-ZA-E-8001 “Process design basis- BS 171”



171A-ZA-E-08050 “Process design basis- ISC”



016-ZA-E-08062 “Process design basis – GC 16”



017-ZA-E-08070 “Process design basis – GC 17”



027-ZA-E-08081 “Process design basis – GC 27”



028-ZA-E-08092 “Process design basis – GC 28”

are prepared, which gathers all the general technical data needed as a basis for project engineering. 7.3.3.

Design output The work processes for engineering and development are described in the Quality management system procedures, as indicated in the relevant section of the Quality manual. In addition to defining the methods for project documents issue and project data, these procedures provide the work instructions needed for the verification and, whenever applicable, the validation of design outputs according to input data, to provide objective evidence of their conformity to the product’s requirements. The PSL’s are in charge of the design activities, under the coordination of the TM. Design outputs include: drawings, specifications, operational and maintenance manuals, Process Flow Diagrams (PFD), Piping & Instrument Diagrams (P&ID), data sheets, Bill of Quantities (BOQ), etc.

7.3.4.

Design review The purpose of design review is to identify and solve the critical aspects of the project, taking into account the project objectives and the COMPANY requirements. Each department shall conduct a design review according to the respective department Work Instructions. Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 22 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

In accordance with the design planning, at least the following interdisciplinary reviews are performed: •

Review of Piping and Instrument Diagrams according to OPR.MO.XE.5012 “Piping and Instrument Diagrams (P&ID)”



Review of plot plans and model according to OPR.GS.XE.5060 “Plot Plans and Design Model”;



Review of HSE (see para. 7.1.3).

Individual disciplines shall carry out the respective design reviews in accordance with the departmental technical instructions. 7.3.5.

Design verification The verification and approval of project documents in Home office are carried out according to the methods and responsibilities defined in GP-SPA-ENGON-007 Verification, checking, review and approval of project document. The project outputs are approved by the concerned project function only if the verification has met the necessary requirements. The project functions performing the verification activities are authorised by their respective department managers. In addition to ensuring the conformance to specific project requirements, the verifications are carried out to guarantee an adequate safety level of engineering and to evaluate the risk associated to the plants. The Interdisciplinary review will be done in accordance to the ILA.GG.EDM.0030 and the associated distribution matrix as a reference to the IDC procedure applied to BS171. The IDC distribution list will be prepared by projects and Document Controller on the basis of inputs from PSLs. The activities applicable to the project are performed according to the OPR.RS.XE.5015 “Safety and Reliability Activities for Plant Design”, and to the project procedure 000-ZA-E-85800 “Overall Project HSE management plan”.

7.3.6.

Design validation The final design validation is carried out, whenever applicable, after the successful completion of test runs of the plant or parts of it. The above validation is formalised by the PM in the “Final Project Report”. This report states the results achieved, the problems encountered and the adopted solutions, and is distributed to the department managers.

7.3.7.

Control of design changes The identification and indication of the need for a design change can be made by anyone involved in the project. The design changes can be originated by the following causes: •

Requests from the COMPANY and/or Licensor;



Variations in design solutions and/or in supplies; Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 23 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General



Work processes or operating methods different from the established program;



Changes or delays in the activities of a department that could impact the activities of other departments. Such changes shall be communicated to COMPANY for approval.

Activities regarding the change cannot start before the COMPANY’s approval. On completion of the design change, the TM updates the “Design change record”. Design changes and modification will be carried out and documented in accordance with the relevant procedure GP-SPA-ENGON-006 “ Design change management” and the following project procedure: •

000-ZA-E-09320 “Management of change procedure”

7.4.

Procurement

7.4.1.

Procurement process The procurement work process is detailed through the following phases: •

Definition of purchasing strategies and development procedures



Bidder list definition



Receipt of purchase request



Floating request for quotations and invitation to tenders



Management and closing of bidding phase



Bid evaluation and negotiation



Contract/Purchase order assignment and signature and verification of Vendor’s order acceptance



Management of contract and order changes



Expediting



Inspection and testing



Logistics and customs



Delivery at site



Reporting



Vendor assistance for site activities (Installation and commissioning)

The purchasing activities are documented in the following project procedures: •

000-ZA-E-09700

“Procurement execution Plan”



000-ZA-E-09701

“Material Acquisition and Management Plan”



000-ZA-E-09702

“Purchasing Procedure-Materials and Equipment”



000-ZA-E-09703

“Purchasing Procedure-Services (Subcontracts)”



000-ZA-E-73004

“Logistics and Shipping Procedure”



000-AZ-E-02034

“Subcontract Plan” Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 24 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General



000-ZA-E-73003

“Expediting Procedure”



000-ZA-E-73001

“QC requirement for Vendors”



000-ZA-E-73002

“Project shop inspection test procedure”



000-ZA-E-09705

“Spare Parts management Procedure”

In detail, the procurement QA/QC activities, including the identification of critical materials that will require specific Inspection and Testing Plans and pre Inspection Meeting, are documented in the following project procedure: •

000-ZA-E-09001 “Project material classification” (contains material classification and inspection level as per Appendix D attachment 15, KOC Standard KOC-Q014)



000-ZA-E-09604 “QA requirement for Vendor” (contains requirement for ITP and PIM as per Appendix D attachment 15, KOC Standard KOC-Q-014)



000-ZA-E-73001 “QC requirement for Vendors” (contains requirement for ITP and PIM as per Appendix D attachment 15, KOC Standard KOC-Q-014)



000-ZA-E-73002

“Project shop inspection test procedure”

The above procedures are produced by the Procurement Department or by the relevant project function, according to the CONTRACTOR’s Quality management system procedures and to the KOC requested project procedure as defined on Contract documents: Appendix E clause 7.8, Appendix D clause 16 and attachment 15, KOC Standard KOC-Q-014. The relevant compliance with the KOC requested procedure is shown on Annexure 2 of this document. The activities and methods used to assure that the procured equipment, material and service will be conform to the Contract requirements are detailed in the next chapters. Project vendor list The CONTRACTOR may purchase material, equipment and services only from Vendors included in the COMPANY vendor list. Other Vendors can be added to the said list subject to COMPANY approval. Vendor qualification The requirement for Vendor qualification is coordinated by the Procurement department, by means of other competent departments in the CONTRACTOR. Procurement department also ensures the recording of qualification in the corporate information system and the filing in specific archives. The target is to evaluate and qualify the capability of Vendors to satisfy the CONTRACTOR’s requirements, through the acquisition and management of information on the Vendors themselves, according to objective and documented criteria.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 25 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

The evaluations are based on information gathered from questionnaires and visits, according to the CONTRACTOR’s applicable procedures, and are updated based on feedback of the material and services delivered by Vendors and subcontractors. The equipment, materials and construction activities to be purchased are grouped into product classes and the list of Vendors qualified by the CONTRACTOR is regularly updated. 7.4.2.

Purchasing information Purchasing data The purchasing documents shall contain information on the product to be purchased, such as: •

Inspection Data Sheets (IDS) issued by the PSL, according to Project Material Classification for material supplies (see 7.1.5);



specifications, drawings, reference codes and standards indicating the applicable edition;



requirements for Quality management of Vendors.



Field quality control plan for site activities;

The IDS provide the list of tests and inspections to be performed on the products and indicate those which the CONTRACTOR and the COMPANY may attend and the level of Surveillance. They also list the Quality records and the material certifications to be issued by the Vendor. Based on the IDS, the Vendor prepares the Inspection and Test Plans (ITP) for approval by the CONTRACTORs involved. The implementation methods for the ITP are documented in the project procedure 000-ZA-E-73002 “Project Shop Inspection procedure” Materials purchasing The “QA requirements for Vendors” are specified in the project document 000-ZA-E-09604; the “QC requirements for Vendors” are specified in the project document 000-ZA-E-73001. The PSL shall include a copy of the above documents in the purchasing documentation. Construction services purchasing The “QA requirements for Construction subcontractors” are specified in the project document 000-ZA-E-09609; the “QC requirements for Construction subcontractors” are specified in the project document 000-ZA-E-09610. The CM shall include a copy of the above documents in the purchasing documentation. Purchase requisition and technical bid evaluation The material purchase requisition and the technical bid evaluation are prepared and verified by the technical department involved, and approved by the PM according to the following procedure: STD-COR-PROC-003: “Request for Quotation – Bid Management – Tabulation”. During Purchase requisition issue, the PSL indicates to the Procurement department the need to obtain conformance certificates from the Vendors, that shall be included in the “Final Test Certificate”. Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 26 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

Spare parts The preparation of bid requests for spare parts is defined in the project document 000-ZA-E-09705 “Spare Parts Management Procedure”. 7.4.3.

Verification of purchased product Materials purchasing The inspection and testing activities on supplies are defined according to Project Material Classification. See para. 7.1.5. The inspections and tests at the Vendor’s premises are conducted as indicated in the technical documents attached to the orders and in the inspection and testing plans. The above activities are documented in the following: •

Inspection report;



Non-conformity report;



Release note;



Final test certificate;



Quality statement.

The agreements for verifications, the coordination with other involved parties, including assigned third parties, and the methods for product release, shall be arranged according to the following project procedures: •

000-ZA-E-73003 “Expediting procedure”



000-ZA-E-73002 “Project Shop Inspection procedure”.

The inspections and tests are conducted in accordance with the ITP, drawings, specifications and any other contractual requirement as expressed on Appendix “D” Construction services purchasing The site quality control activities are carried out by the Construction subcontractors for the as indicated in the document 000-ZA-09610 “QC requirements for Construction subcontractors” and specific Quality Control Standards (QCSs) issued by the technical departments, under the coordination of the PQM. QCSs will be endorsed by Construction subcontractors by issuing Quality Control Plans (QCPs); QCPs with CONTRACTOR review comments will be forwarded to the COMPANY for review and for mark up of COMPANY involvement in site QC inspection activities. All Quality Managers of the Construction subcontractors shall have a reporting line to CONTRACTOR Field Quality Coordinator. 7.5.

Production and service provision

7.5.1.

Control of work process during site activities The planning, coordination and control of site activities is ensured by the following project procedures: •

000-AZ-E-02005 “Subcontract administration procedure” Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 27 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General



000-AZ-E-02332 “Site security plan”



000-ZA-E-02003 “Temporary site facilities for Company & Contractor”



000-ZA-E-09801 “Project physical progress measurement procedure”.

The site coordination procedure illustrates the methods to be followed for the coordination between the COMPANY, CONTRACTOR and Construction subcontractor’s representatives on site. The following aspects are detailed: •

Organisation;



Correspondence;



Meetings;



Work planning and coordination;



Material delivery;



Daily reports;



Quality control;



HSE compliance;



As-built drawings.

Baseline data Collection The Contractor will arrange for and undertake all baseline data activities including isometric drawings of the fabricated and installed piping ne\work. The baseline data will provide as a minimum the following information: (a) the equipment and piping materials of construction; (b) the joining I welding type, NDT and pressure testing made; (c) the actual measured wall thickness of ali pipe spools, filtings, connections and static equipment (d) static equipment and line specifications, design and operating data and reference to P&IDs (e) painting or coating type and the dry film thickness and reference specification I standard used. - The Contractor will submit for Company review and approval its "Baseline Data Preparation Procedure" , doc 000-ZA-E-02020 well in advance of the start of the work, - Completed baseline data records will be submitted to Company in stages commensurate with the progress of work. The records shall be provided in MS Office Excel sheets so that it could be integrated with the existing Risk Based Inspection (RBI) KOC records and software under the control of Inspection & Corrosion Teams. - Equipment to be included in the baseline data are those newly installed ones by the Contractor within the Scope of the project I Contract. These equipments include the stationary pressure vessels, heat exchange equipment, storage tanks (shop fabricated or site erected), scraper traps, heaters, tiare stacks, tiare tips, slug catchers, etc. All drawings for equipment and piping isometrics shall be submitted in soft copy in both AUTOCAD and PDF formats.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 28 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

Control of mechanical completion and commissioning. The operating methods for the completion of plant construction, erection and commissioning are based on the following project procedures: •

000-AZ-E-02019 “Mechanical completion & pre commissioning procedure”;



000-ZA-E-79001 “Commissioning & start up procedure”.

The above documents are issued according to the relevant procedures of the Quality management system and according to the contractual requirements. 7.5.2.

Validation of production work process The work process validation is required when work process integrity could not be verified by subsequent monitoring or measurement. The CONTRACTOR shall validate any processes for product and service provision where the resulting output cannot be verified by subsequent monitoring or measurement. These include the activities regarding welding, thermal treatments, non-destructive controls and qualification of operators. All these processes are validated by the CONTRACTOR prior to the beginning of works. The validation activities are:

7.5.3.



qualification of work processes;



qualification of equipment and personnel;



use of specified methodologies and procedures.

Product identification and traceability During all phase of project realisation, the products are identifiable and traceable through well defined numbering and identification systems. For the bulk piping material, when required by contract, its unique identification is recorded to ensure it can be traced back to the certificate of origin and/or inspection documents. This activity is addressed to tracing each single component or lot of components for their eventual repair and/or replacement, to identify the Vendor, and to acquire feedback on the damaged, nonconforming or inadequate components. Identification methods have been established, such as the colour code and/or verification of alloy elements “Positive Material Identification” of piping material, to avoid errors in linking the piping components, which could have a negative impact on the safety or reliability of the plant. These activities are defined for each project and documented in dedicated specifications. For the Project Material Identification, in the event of critical circuits, the project procedure 000-AZ-E-02014 “Positive material identification procedure” is issued. The full traceability of material and products during construction activities is ensured through compliance with OPR.GS.XE.5007 “Traceability of Project Piping Materials”. Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

7.5.4.

Sh. 29 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

COMPANY property With the purpose of identifying responsibilities related to COMPANY property and in order to protect its value, the CONTRACTOR manages the following in compliance with contract specifications: •

parts or components provided by the COMPANY that will be incorporated in the final product;



the COMPANY’s intellectual property including specifications, drawings and confidential information.

Therefore, the CONTRACTOR shall carry out the following: •

identify the COMPANY’s property;



verify if the COMPANY’s property is damaged;



keep records of the damage and notify the COMPANY;



protect the COMPANY’s property (as set out in the following procedures: 000-AZ-E-02013 “Material management, storage and handling procedure”).

7.5.5.

Product preservation The handling, storage, packaging, preservation and delivery of material to the established destination specified in the order shall conform to the SPC.IB.GEN.0001 “Packaging and delivery of material and equipment”, and to the general purchasing conditions. In compliance with KOC standard KOC-Q-014, the CONTRACTOR will ensure a proper material management in order to: •

To ensure proper transportation and handling equipment during loading, offloading and handling of equipment and materials



To consider preservation of materials during site handling, transportation and storage



To consider timely use of material with limited life



To ensure material inspection and identification on receipt



To ensure accurate identification of material on issue



To ensure non-conforming and undefined materials will be held in quarantine until they are rectified, replaced or accepted by concession

The following project procedure shall be produced 000-ZA-E-73003 “Expediting procedure”. The material and equipment on site is managed according to the project procedure 000-AZ-E-02013 “Material management, storage and handling procedure”. The project procedure will be in compliance with KOC standard KOC-Q-014 clause 7 The following checks will be made periodically (for stored materials and equipment) and when any new equipment or materials are received: •

Examination upon receipt to detect damage in transit Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

7.6.

Sh. 30 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General



Inspection for completeness and proper type as per the Contract requirements and purchase order specifications



Periodic inspection and precautions to assure adequate storage conditions and to guard against damage for handling and deterioration during storage



Functional testing, either prior to or after installation, or both, as required to determine satisfactory operation



Identification and protection from improper use or disposition



Verification of quantity

Subcontracts qualification & control Preparation of subcontracts, approvals of Subcontractor selections, and administration procedures for subcontracts shall be per the requirements of Clause 7.0 of the General Conditions of Contract and Clause 17.0 of Appendix D (Project Administration and Coordination Procedure) The Qualification process for Subcontractor is governed by Corporate procedure STD-COR-PROC-001 Vendor Management. During request for Bid phase the complete set of Company Quality requirements requested by KOC-Q-014 is given to subcontractor. Moreover to define more in detail the managing aspect to be implemented by the Subcontractor and the control operated by Contractor Two project procedure are issued, the two document set the requirements and planning for Control subcontractor Quality activities: 000-ZA-E-09609 “Quality Assurance General Specification for Subcontractor” and 000-ZA-E-09610 “Quality Control General Specification for Subcontractor”, these two documents are part of Contractor Project Quality System and are issued to Company for approval. Contractor will manage the subcontracting aspects with dedicated Project procedure 000-AZ-E-02005 Sub-Contract Administration Procedure” Subcontractor will issue all the require Management/Technical Project documentations in order to demonstrate their compliance and understanding of the relevant assigned job and the requested Contractor requirements. The Subcontractor documentations will be subject to Contractor approval and to Companies approval.

7.7.

Quality Control and inspection activities during construction phase All construction and installation activities will be made in accordance with KOC approved procedures, the Project procedure will be in compliance with KOK-Q-014 appendix G &H. In accordance to Company requirements contained on Appendix E clause 7.10, KOCQ-014 clause 6.6 Contractor will provide a resident organization for QC activities, a resident QA/QC manager (FQM) will be on charge for all the QC activities and relation with the Companies for all the aspects related to QC activities, for each discipline work a dedicate QC Supervisor/Inspector will be put in place in order to monitor and control all the inspection and test foreseen on the ITP, more specific task is clearly defined on document “Project organization, function, responsibilities and charts” 000ZA-E-09602 Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 31 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

The site quality control activities are carried out by the CONTRACTOR (direct hiring works) and by Construction subcontractors for the subcontracted works. Direct hiring The quality control activities will be carried out by CONTRACTOR as indicated in the Quality Control Plans (QCPs) issued by the technical departments, under the coordination of the PQM QCPs will be forwarded to the COMPANY for review and for mark up of COMPANY involvement in site QC inspection activities. Requirements for execution of QC activities related working processes are defined in the specification 000-ZA-E-09610 “Quality Control Requirement for Construction Subcontractor”, it is valid also for direct hiring works. The specification 000-ZA-E-09610 is in accordance to KOC standard KOC–Q-014 clause 6.6 More in detail, it outlines the requirements for: ƒ Quality control planning and implementation, (KOC –Q-014 clause 6.6.2.1) ƒ Quality verifications (initial, in-process, final, Third Party Inspection – TPI - and by CONTRACTOR and COMPANIES), (KOC –Q-014 clause 6.6.2.2) ƒ Control of construction processes (including special processes), (KOC –Q-014 clause 6.6.6 & 6.6.7) ƒ QA/QC co-ordination (including Inspection Notification), (KOC –Q-014 clause 6.6.2.4) ƒ Inspection and Test Reporting (KOC –Q-014 clause 6.6.2.3) ƒ Quality Control Specifications applicable to the Project (KOC –Q-014 clause 6.6.1.2) ƒ QCP/ITP (Inspection and test Plan) To be issued (KOC –Q-014 clause 6.6) Subcontracted work A dedicated Specifications for subcontracting requirements for QA/QC are issued for COMPANY approval: 000-ZA-E-09609 “Quality Assurance Requirement for Construction Subcontractors & 000-ZA-E-09610 “Quality Control Requirement for Construction Subcontractor”. The Contractor will deliver to the Subcontractor a complete set of Quality Control Standards (QCS) to enable the Subcontractor to prepare the QCPs applicable to the Project, (list of QCP/ITP is given on Appendix 1 of 000-ZA-E-09610 “Quality Control Requirement for Construction Subcontractor), each QCS is issued for each main discipline work. The QCS contains several ITS (Inspection and test Standard) and related Check List to be used as base for ITP, the ITS’s and check lists covers all the test and control foreseen to the works related to the discipline of the mentioned QCS. The Subcontractors will issue the QCP, (which contains the related ITP to be used for construction), with the Project code number already assigned. The specification 000-ZA-E-09609 “Quality Assurance Requirement for Construction Subcontractor” provide requirements for the organisation, the procedures and the tools to be set up by Subcontractor to fulfil the COMPANY quality requirements (KOCQ-014, clause 6.6.3) in terms of: ƒ Quality Management System implementation, ƒ Procedures to be prepared and submitted, ƒ Personnel mobilisation and qualification Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

ƒ ƒ ƒ ƒ ƒ ƒ

Sh. 32 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

Construction processes to be controlled, Quality auditing activities Quality meetings, Management of nonconformities, Reporting to CONTRACTOR Continual improvement

The specification 000-ZA-E-09609 is in accordance to KOC standard KOC–Q-014 clause 6.6 The specification 000-ZA-E-09610 “Quality Control Requirement for Construction Subcontractor” provides requirements for the execution of QC activities related working processes. More in detail, it outlines the requirements for: ƒ Quality control planning and implementation, (KOC –Q-014 clause 6.6.2.1) ƒ Quality verifications (initial, in-process, final, Third Party Inspection – TPI - and by CONTRACTOR and COMPANIES), (KOC –Q-014 clause 6.6.2.2) ƒ Control of construction processes (including special processes), (KOC –Q-014 clause 6.6.6 & 6.6.7) ƒ QA/QC co-ordination (including Inspection Notification), (KOC –Q-014 clause 6.6.2.4) ƒ Inspection and Test Reporting (KOC –Q-014 clause 6.6.2.3) ƒ Quality Control Specifications applicable to the Project (KOC –Q-014 clause 6.6.1.2) ƒ QCP/ITP (Inspection and test Plan) To be issued (KOC –Q-014 clause 6.6) CONTRACTOR will review and approve the QCP/ITP before transmission to the COMPANY for approval and insertion of Company W/H point, CONTRACTOR will forward the QCP/ITP 14 days prior the start of the relative works. Baseline data All the information regarding the welding traceability as: ƒ piping materials, ƒ joining/welding type, NDT and pressure testing made, ƒ measured wall thickness of pipe spools, fitting, connection and static equipment ƒ static equipment and line specifications, design and operating data and reference to P&IDs ƒ painting or coating type and the dry film thickness are listed in the Welding summary list. The modality to management the Welding summary list and the Welding summary list form are described into Quality Control Plan for Welding.

7.8.

Control of monitoring and measuring equipment

7.8.1.

Control of monitoring and measuring tools, instrument As per KOC-Q-014 clause 6.6.8 requirements, the project specification 000-ZA-E09610 “QC requirements for Construction subcontractors” par. 4.4, defines the prescriptions regarding: Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 33 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

ƒ ƒ

the calibration and preservation of testing, (KOC –Q-014 clause 6.6.8.2) identification and calibration of measuring and inspection equipment (KOC –Q014 clause 6.6.8.2) ƒ calibration records (KOC –Q-014 clause 6.6.8.3) and indicates the certificates to be issued. The prescriptions apply to direct hiring and to subcontracted works Records of calibration and control sheets shall be maintained by the Contractor; FQM will be responsible for the management of the updating and disposition of control sheets. 7.8.2.

Laboratory qualification All testing laboratories that will be utilized by the Contractor, sub-Contractors will be competent in accordance with the requirements of clause 8.0 of KOCQ-014 Rev 1 & BS EN ISO/IEC17025. Contractor and subcontractors will use laboratory as Intrex and Gulf Inspection.

7.9.

Constructability review Constructability program, applicable to the Project, is performed according to project document “000-ZA-E-09022 Constructability Procedure”. The CII (Construction Industry Institute) defines constructability as the optimum use of construction knowledge and experience in planning, design, procurement and field operation, to achieve overall project objective. As part of its policy of continuous improvement in job management, Saipem considers the systematic application of Project Management methodologies (Best Practices) to be an element of fundamental importance for achieving first-rate results in projects. The application of Best Practices also contributes to the spread and rise of the Project Management culture at all levels Constructability rests on three fundamental pillars: Project Planning, Site Layout and application of the so-called Major Construction Methods.

-

In reality, it is necessary to pay extra attention to certain additional points: ƒ Develop and maintain a strong will to achieve maximum project cost effectiveness ƒ Make use of specific constructability techniques (e.g. standardization, modularization etc.) to achieve the set objectives ƒ Involve the construction experts “early on” ƒ Plan construction activities with care ƒ Insist on obtaining the receptivity of design engineers to construction needs WORK PROCESS: The work process is divided into the following phases ƒ Setting up of Constructability Team ƒ Information collection ƒ Preparation and issue of Project Constructability Procedure ƒ Constructability Implementation Schedule ƒ Kick-off meeting ƒ Discipline review of constructability checklist ƒ Objectives definition and constructability plan preparation ƒ Constructability plan review meetings ƒ Final Constructability Report G

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 34 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

During construction at planned stages established inside the constructability procedure a dedicated Constructability reviews will be performed in order to assure the correct conformance to the programs and to foreseen and correct eventual future loss of time.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 35 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

8.

MEASUREMENT, ANALYSIS AND IMPROVEMENT

8.1.

General requirements The activities that contribute to the measurement, analysis and improvement process are aimed at:

8.2.



demonstrating the conformity of the product by means of design reviews and verifications, tests and inspections conducted at the Vendor’s premises and during construction, controls and final tests during plant start-up;



ensuring the conformity of the Quality management system by means of project reviews and internal audits;



continually improving the effectiveness of the Quality management system by reviewing the work processes.

Monitoring and measurement The monitoring and measurements activities enable decision-making based on objective evidence. The feedback obtained from the project and updated continuously constitutes the base of improvement for the CONTRACTOR’s services through the involvement of all parties concerned.

8.2.1.

COMPANY satisfaction The degree of COMPANY satisfaction is monitored by the BM, both during project development with the assistance of the PM, and during post-sales activities. The COMPANY’s complaints are formally communicated to the PM who verifies if the complaint is justified. If so, he then proceeds to solving the COMPANY’s complaint, both directly and by involving the managers of the departments concerned. All the COMPANY complaints are documented and managed by means of internal or external correspondence and minutes of meetings (MOM) to identify adequate corrective action. The above-stated correspondence and minutes are recorded and filed.

8.2.2.

Project audits Project audits are planned and conducted in the Contractor home office at Contractor and Subcontractor site on Vendors and on testing laboratories with the following objectives: •

verify that the activities are performed in accordance with the provisions of the project Quality system;



assess the adequacy and effectiveness of the project Quality management system in relation to established Quality objectives, particularly considering the congruence and integration among activities;



identify possible deficiencies, determine the causes of such and, where necessary, promote appropriate corrective action; Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 36 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General



verify the application and effectiveness of the adopted corrective action;



furnish to the PM and to the responsible of QUAL department the assessment of the state of the Quality Management System to the project and also of its implementation. Based on the results of the internal audits, the PM shall ensure that appropriate corrective action is adopted.

The project audits (including external audit,), the corrective action to be adopted and the documents produced are managed according to the methods indicated in OPR.QL.XA.5010 “Quality, Environmental, Health and Safety Audits” and in the project procedure 000-ZA-E-09603 “Quality assurance activities and audits plan”. 8.2.3.

Monitoring and measurement of processes Processes are measured continuously to evaluate their effectiveness and efficiency.

8.2.4.

Monitoring and measurement of products The measurement of products shall be planned to verify their compliance with the requirements established by the parties involved (CONTRACTOR, COMPANY, Vendor, etc.). The adopted measurement methods shall take into account the following: •

characteristics to be measured, documents and acceptance criteria to be adopted;



inspections and tests to confirm that all the specified verifications and validations have been completed and accepted; list of QCP/ITP to be used for construction purposes is given on Annexure 2 and on document 000-ZA-E-09610 “QC requirements for Construction subcontractors”



records of the implemented measurements.

The above measurements and monitoring must comply with the following project procedures:

8.3.



000-ZA-E-09604 “QA requirements for Vendors”;



000-ZA-E-09610 “QC requirements for Construction subcontractors”;



000-ZA-E-73001 “QC requirements for Vendors”.



000-ZA-E-73002

“Project Shop Inspection test procedure”

Control of nonconforming products Purchasing phase The nonconformities of material and equipment registered during the purchasing phase are examined and treated in accordance with WI-SPA-PROC-005 “Inspections-Testing” The proposed use or repair of a nonconforming product shall be reported for approval to the COMPANY or his representative. Construction phase (site) The nonconformities during the construction phase (on site) are examined and treated according to the following procedure: Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283



Sh. 37 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

000-AZ-E-02033

“Site nonconformity management procedure”.

The proposed use or repair of a product with a non conformity shall be notified for to the COMPANY or its representative. 8.4.

Data analysis Data gathered from all the projects are analysed to examine CONTRACTOR’s corporate system and implement activities for continual improvement, as detailed in para. 8.5. This analysis takes into consideration the following general criteria: •

COMPANY satisfaction;



satisfaction of other interested parties;



effectiveness of the processes;



achievement of the organisation’s performance Quality objectives.

Data review and the analysis are carried out by the various departments of the CONTRACTOR. Special working group can be constituted for the analysis of particularly complex situations 8.5.

Improvement

8.5.1.

Continual improvement The continual improvement process is carried out by the CONTRACTOR at the corporate level, taking into consideration the following: •

Quality policy;



Quality objectives;



Audit reports;



Data analysis;



Corrective action;



Management review.

Continual improvement also takes into account the work phases described in OPR.QL.XA.5011 “Quality Indicators Identification and Management” and in OPR.GS.XE.5019 “Management of Lessons Learned”. 8.5.2.

Corrective actions Corrective actions by CONTRACTOR at corporate level are implemented as per OPR.QL.XA.5005 “Corrective and Preventive Action on Quality, Environment and Safety Management Systems”. Under project execution, corrective actions are defined in: •

audit reports, according to OPR.QL.XA.5010 “Quality, Environment, Health and Safety Audits”; Data file:09600-2.doc

This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283 •

Sh. 38 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

non conformity reports, according to the project document 000-AZ-E-02033 “Site nonconformity management procedure” and to WI-SPA-PROC-005 Inspections Testing

Following a COMPANY complaint or occurrence of non-compliance with project requirements by project functions, corrective actions request (CAR) are issued by the PQM. 8.5.3.

Preventive action Preventive actions by CONTRACTOR at corporate level are implemented as per OPR.QL.XA.5005 “Corrective and Preventive Action on Quality, Environment and Safety Management Systems”.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 39 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

ANNEXURE 1 – LIST OF CORPORATE CONTRACTOR’S PROCEDURES

DOC. NUMBER GP-SPA-QUALON-005 OPR.QL.XA.5005 OPR.QL.XA.5010 OPR.QL.XA.5011 GP-SPA-ENGON-007 GP-SPA-ENGON-006 OPR.GS.XE.5007 OPR.GM.XE.5013 STD-COR-PROC-001 STD-COR-PROC-003 OPR.GS.XE.5019 OPR.GS.XE.5060 OPR.MO.XE.5012

TITLE BU Oshore (Quality) Management System Manual Corrective and Preventive action on Quality, Environment and safety Management systems Quality, environmental, Health and safety audits Quality indicator identification and management Verification, control, review and approval of project documents Design change management Traceability of project piping Materials Projects Documents control Vendor Management Request for quotation-Bid management-Tabulation Management of lessons learned Plot plans and design model Piping and instrument diagrams (P & ID)

SPC.IB.GEN.0001 WI-SPA-PROC-005 OPR.RS.XE.5015 ILA.GG.EDM.0030

Packaging and delivery of material and equipment Inspections -Testing Safety and reliability activities for plant design Definition of distribution matrix

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 40 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

E 6.4.12

Constructability Procedure

CM

DPM

PM

X

I (for information)

000-ZA-E-09022

R (review)

Constructability Programme

Project document Title

A (for approval)

Project Document number

Approved

Contract Description Reference

Checked

Contract Document Reference

Prepared

ANNEXURE 2 – LIST OF PROJECT PROCEDURES (TO BE SUBMITTED FOR KOC REVIEW AND APPROVAL)

1.0 KUWAITISATION PCC 10.3

Employment of kuwaiti citizens

000-ZA-E-09007

Plan for employment of Kuwaiti citizens

CM

DPM

PM

X

PCC 10.4

Details of kuwaiti personal employment

000-ZA-E-09007

Plan for employment of kuwaiti citizen

CM

DPM

PM

X

Request for further site data/engineering information

6.0 PROVISION OF DATA GCC 4.2.2

Request for additional data

000-ZA-E-09008

Appendix F, Sect.A, par.2.2.21

Site Surveys

000-ZA-E-09012

Site survey of existing plants - Report

DTM

TM

DPM

X

DTM

TM

DPM

X

11.0 PAYMENT TERMS- 37.0 INVOICINGA3.1 GCC 11.3.3

Monthly Invoice

000-AZ-E-09803

Progress measurement system for invoicing PCM procedure

DPM

PM

X

GCC 13.1.2

Variations

000-ZA-E-09002

Variation order procedure

CA

DPM

PM

X

GCC 22.5 E 10 F 11.2

HSE plan

000-ZA-E-85800

Overall Project HSE management plan

HSE

HSEM

PM

X

GCC 22.6.1

HSE INDUCTION AND JOB ORIENTATION COURSE

000-ZA-E-85802

HSE

HSEM

PM

X

GCC 22.20.3 Appendix E Exhibit A

HSE audit and inspection plan/schedule

000-ZA-E-85802

HSE

HSEM

PM

X

17.0 HSE

HSE plan for construction, precommissioning and commissioning HSE plan for construction, precommissioning and commissioning

18.0 CONSTRUCTION GENERAL PROVISION GCC 24.7

Movement of heavy loads

000-AZ-E-02301

Safety manual - lifting operations

HSEM

CM

PM

19.0 CONTRACTORS TEMPORARY OFFICES AND WORKS

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

X

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

Doc. class.: A

2

Document title: Project Quality Plan

000-ZA-E-02003

Temporary site facilities for Company & Contractor (plot Plan, layout, KOC layout)

CM

DPM

PM

X

000-AZ-E-02332

Site security plan

HR

CM

PM

X

GCC 33.4

Organization chart showing its proposed 000-ZA-E-09602 site project organization and job descriptions

Project office & site organisation charts with job descriptions

PQM

QUAL

PM

X

GCC 33.3

Project office organization chart and job descriptions

Project office & site organisation charts with job descriptions

PQM

QUAL

PM

X

GCC25.4 GCC26.1

Resources

GCC25.4 GCC26.1

Resources

23.0 CONTRACTOR’S PERSONNEL

000-ZA-E-09602

25.0 FINAL STAGES OF CONSTRUCTION, PRECOMMISSIONING, TURNOVER AND COMMISSIONING 64.0 TRAINING OF COMPANY PERSONNEL C 2.1.1a, GCC 34.7, 35.1

Pre-commissioning procedure

000-AZ-E-02019

Mechanical completion & Pre-commissioning procedure

COM

CM

PM

X

C 2.1.1a, GCC 35.1 C 2.1.1b GCC 35.2(d)

Commissioning procedure

000-ZA-E-79001

Commissioning & start up procedure

COM

CM

PM

X

GCC 36.2 E 9.5

Training of Company personnel

000-ZA-E-79002

Training of Company personnel programme

COM

CM

PM

X

42.0 DOCUMENTATION REQUIREMENTS C

4.2.5

KOC-Q-014 para 12

Mechanical completion Baseline data collection

000-AZ-E-02017

Punch list procedure

CM

PM

PM

X

000-AZ-E-02020

Baseline Data Preparation Procedure

CM

TM

PM

X

000-ZA-E-09000

Project coordination /administration procedure between company and contractor

TM

DPM

DPM

X

000-ZA-E-09850

90 day look ahead programme

PCM

DPM

PM

X

43.0 SCOPE AND PROCEDURE

D 1.1

Project co-ordination procedure

46.0 PROJECT SCHEDULE D

5.1.1

90 day look ahead programme (lev 2)

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

I (for information)

Project document Title

R (review)

Project Document number

A (for approval)

Contract Description Reference

Approved

Unit: General

Checked

Contract Document Reference

Rev.

Prepared

Contract No. 45283

Sh. 41 of 49

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

D

5.1.2

Doc. class.: A

2

Document title: Project Quality Plan

000-ZA-E-09808

Critical document programme Detailed CPM programme for engineering, procurement & subcontract (lev 3)

PCM

DPM

PM

X

PCM

DPM

PM

X

PCM

DPM

PM

X

D 5.1.3

Detailed critical path for engineering, 000-ZA-E-09851 procurement & subcontract

D 5.1.4

Detailed cpm programme for construction / installation (lev.3)

000-ZA-E-09852

D 5.1.5

Overall detailed contract CPM programme

000-ZA-E-09853

Overall contract CPM schedule (lev.3)

PCM

DPM

PM

X

D 5.1.6

Overall Bar Chart Programme (lev 1)

000-ZA-E-09854

Overall bar Chart programme (lev 1)

PCM

DPM

PM

X

D 5.1.7

Construction equipment usage bar chart 000-AZ-E-02503 programme

Construction equipment CONST usage bar chart programme R

CM

PM

X

D 5.0

Project Program

Planning and scheduling procedure

PCM

DPM

PM

X

PCM

TM

PM

PCM

DPM

PM

X

PCM

DPM

PM

X

CM

PM

PM

X

Document Control procedure

PCM

TM

PM

X

Document list and drawing register

PCM

TM

PM

X

000-ZA-E-09800

Detailed CPM programme for construction /installation (lev3)

47.0 PROJECT REPORTS D 6.6 , D 8.8.2

Document list & drawing register status 000-ZA-E-09804 report

Document list and drawing register Project physical progress measurement procedure

D 6.0

Project Reports

000-ZA-E-09801

D 6.0 D 6.2

Project Reports

000-ZA-E-09802

Reporting procedure

D 6.1.3

Construction Progress

000-AZ-E-02107

Construction progress measurement procedure

X

49.0 DOCUMENTATION, APPROVAL, REVIEW & DISTRIBUTION D8

D 8.8.2

Documentation, approval, review and distribution Detailed and comprehensive document requirements submittal schedule

000-ZA-E-09806

000-ZA-E-09804

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

I (for information)

Critical document program

Project document Title

R (review)

Project Document number

A (for approval)

Contract Description Reference

Approved

Unit: General

Checked

Contract Document Reference

Rev.

Prepared

Contract No. 45283

Sh. 42 of 49

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

Doc. class.: A

2

Document title: Project Quality Plan

D 8.8.4

As built records including project records

000-AZ-E-02018

As-built drawing procedure

D 8.1

Project Document Numbering System

000-ZA-E-09003

Project coding and numbering procedure

000-ZA-E-09010

000-ZA-E-09009

PM

PM

DTM

TM

PM

Project record books and manuals

DTM

TM

PM

X

Detail engineering procedure for preparation of project record books and manuals

DTM

TM

PM

X

000-ZA-E-08401

Operating and maintenance manual

PPL

TM

PM

X

000-ZA-E-08401

Operating and maintenance manual

PPL

TM

PM

X

PPRM

DPM

PM

CM

X

X

50.0 PROJECT RECORDS & MANUALS D 10.0

D 10.0

Project record books and Manuals

Design Engineering procedure

51.0 OPERATING &MAINTENANCE MANUALS D 11.0

D 11.0

Draft operating and maintenance manual Approved operating and maintenance manual

53.0 OPERATIONAL SPARE PARTS RECOMMENDATIONS D 14.1

Operational Spare Parts Recommendation

000-ZA-E-09705

Spare Parts Management Procedure

X

55.0 PROCUREMENT-EXPEDITING-INSPECTION-MATERIAL HANDLING

D 16.1.1

Procedure for procurement and supply of all materials and equipments for incorporation into facilities

000-ZA-E-09700

Procurement execution plan

PPRM

DPM

PM

X

D 16.2 , E 4.0

Material acquisition & management plan

000-ZA-E-09701

Material acquisition & management plan

PPRM

DPM

PM

X

D 16.3.1

Purchasing plan

000-ZA-E-09702

Purchasing procedure - materials and equipment

PPRM

DPM

PM

X

D 16.3.1

Purchasing plan

000-ZA-E-09703

Purchasing procedure – Services (Subcontracts)

PPRM

DPM

PM

X

D 16.6.1

Transportation plan

000-ZA-E-73004

Logistics and shipping procedure

MM

DPM

PM

X

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

I (for information)

Project document Title

R (review)

Project Document number

A (for approval)

Contract Description Reference

Approved

Unit: General

Checked

Contract Document Reference

Rev.

Prepared

Contract No. 45283

Sh. 43 of 49

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

D 16.7

D 16.5.1 & attachment 15 D 16 & attachment 15 E 7.8

Doc. class.: A

2

Document title: Project Quality Plan

Ware housing plan (plan to receive and store at site materials and equipment)

000-AZ-E-02013

Material management storage & handling procedure

000-ZA-E-09001

Project Material Classification

000-ZA-E-73003

Expediting Procedure

MC

DPM

PM

CM

DPM

PM

DTM

PM

PM

X

X

X

56.0 SUBCONTRACTING D 17.3.1

Sub-contract plan

000-AZ-E-02034

Subcontract plan

CM

PM

PM

X

D 17.5.2

Sub-contract administration procedure

000-AZ-E-02005

Sub-contract administration procedure

CM

PM

PM

X

000-ZA-E-09005

General specification for project information and communication technology (ICT) system

ICT

DPM

000-ZA-E-09310

Contract close-out procedure

CA

PM

57.0 AUTOMATION TECHNOLOGY

D 18.0 D 18.2.1

Automation Technology

X

PM

58.0 CONTRACT CLOSE OUT

D19.0

Review with the company the administrative procedure to be utilized for closeout and hand over

PM

X

60.0 DESIGN ENGINEERING SERVICE E 2.1.2

Site organization chart

000-ZA-E-09602

Project office & site organisation charts with job descriptions

PQM

QUAL

HSE

HSEM

PM

X

HSE

HSEM

PM

X

PM

X

61.0 CONSTRUCTION SERVICE – 17.0 HSE E 6.4.7, E 10 & GCC 22.5

HSE Plan

000-ZA-E-85802

Project HSE Plan Construction, Precommissioning and Commissioning

E 6.4.7, E 10 & GCC 22.5

HSE Plan

000-ZA-E-85822

HSE manual for construction

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

I (for information)

Project Document number

R (review)

A (for approval)

Contract Description Reference

Items of Equipment and materials To Be Inspected Items of Equipment and materials To Be Inspected

Project document Title

Approved

Unit: General

Checked

Contract Document Reference

Rev.

Prepared

Contract No. 45283

Sh. 44 of 49

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

Doc. class.: A

2

Document title: Project Quality Plan

Project Document number

E 6.4.7, E 10 & GCC 22.5

HSE Requirements

000-ZA-E-85821

HSE Requirements for SubContractors

HSE

HSEM

E.6.2.3

HSE plan

000-ZA-E-85805

HSE plan for survey works

HSE

HSEM

PM

X

000-ZA-E-09806

Document control procedure

PCM

DPM

PM

X

000-ZA-E-09806

Document control procedure

PCM

DPM

PM

X

000-ZA-E-73002

Project Shop Inspection test procedure

MM

DPM

PM

X

000-ZA-E-73001

QC requirements for vendors

MM

DPM

PM

X

000-AZ-E-02013

Material management storage & handling procedure

CM

DPM

PM

X

000-AZ-E-02535

Technical work instruction welding consumables control

CONS TR

DS

CM

X

000-AZ-E-02531

Safe storage and handling of sources of ionising radiation for site utilisation

CONS TR

DS

CM

X

000-ZA-E-09610

QC requirements for construction contractors

PQM

CM

PM

X

PM

X

62.0 QUALITY MANAGEMENT SERVICE

E 7.6.1

E 7.6.2

E 7.6.3

E 7.6.3

E 7.6.4

E 7.6.5

E 7.6.6

E 7.6.7

QUALITY RELATED PROCEDURES-( i) Issue, revision and control of documents bv the Contractor QUALITY RELATED PROCEDURES - (ii) Vetting and control of Vendor documents. QUALITY RELATED PROCEDURES - (iii) Inspection coordination with the Company and Vendors and release of goods from Vendors QUALITY RELATED PROCEDURES - (iii) Inspection coordination with the Company and Vendors and release of goods from Vendors QUALITY RELATED PROCEDURES - (iv) Goods receiving inspection at Site QUALITY RELATED PROCEDURES (V)Site storage issue and control of welding consumables. QUALITY RELATED PROCEDURES -(VI) Site storage and Handlig of sources of ionising radiation for Site utilisation QUALITY RELATED PROCEDURES - (vii) Field inspection coordination.

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

I (for information)

Contract Description Reference

R (review)

A (for approval)

Project document Title

Approved

Unit: General

Checked

Contract Document Reference

Rev.

Prepared

Contract No. 45283

Sh. 45 of 49

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

E 7.6.8

E.7.6.9

E 7.6.10

E 7.9.1

E 7.9.1

E 7.9.1

Doc. class.: A

2

Document title: Project Quality Plan

QUALITY RELATED PROCEDURES - (viii) Pre-commissioning inspection and test of relief valves . QUALITY RELATED PROCEDURES - (ix) Internal techn ical, safety and quality audits QUALITY RELATED PROCEDURES - (x) Auditing of Subcontractors and Vendors by the Contractor Overall quality programme and quality plan for site activities Overall quality programme and quality plan for site activities Overall quality programme and quality plan for site activities

000-AZ-E-02562

Precommissioning, inspection & testing of relief valves

000-ZA-E-09603

CONS TR

DS

CM

X

Quality assurance activities and audits plan

PQM

QUAL

PM

X

000-ZA-E-09603

Quality assurance activities and audits plan

PQM

QUAL

PM

X

000-ZA-E-09600

Project quality plan

PQM

QUAL

PM

X

Quality assurance activities and audits plan

PQM

QUAL

PM

X

QA requirement for construction contractors

PQM

QUAL

PM

X

X

000-ZA-E-09603

000-ZA-E-09609

E 7.9.1

Overall quality programme and quality plan for site activities

000-ZA-E-09610

Qc requirements for construction contractors

PQM

CM

PM

E 7.9

Quality plans provided by sub-contractors

000-ZA-E-02612

Quality control plan for civil general works

CONS TR

DS

CM

X

E 7.9

Quality plans provided by sub-contractors

000-ZA-E-02613

Quality control plan for buildings

CONS TR

DS

CM

X

E 7.9

Quality plans provided by sub-contractors

000-ZA-E-02614

Quality control plan for hvac

CONS TR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02616

Quality control plan for steel structures

CON STR

DS

CM

X

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

I (for information)

Project document Title

R (review)

Project Document number

A (for approval)

Contract Description Reference

Approved

Unit: General

Checked

Contract Document Reference

Rev.

Prepared

Contract No. 45283

Sh. 46 of 49

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

Doc. class.: A

2

Document title: Project Quality Plan

Contract Description Reference

Project Document number

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02621

Quality control plan for pressure vessels

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02622

Quality control plan for heat exchangers

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02623

Quality control plan for welding

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02624

Quality control plan for storage tanks

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02626

Quality control plan for firefighting equipments

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02631

Quality control plan for piping prefabrication and erection

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02633

Quality control plan for painting work

CON STR

DS

CM

X

E 7.9

Quality plans provided by sub-contractors

000-ZA-E-02634

Quality control plan for insulation work

CONS TR

DS

CM

X

E 7.9

Quality plans provided by sub-contractors

000-ZA-E-02635

Quality control plan for lining and coating works

CONS TR

DS

CM

X

E 7.9

Quality plans provided by sub-contractors

000-ZA-E-02644

Quality control plan for electrical works

CONS TR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02642

Quality control plan for material cathodic protection

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02651

Quality control plan for instrumentation/ automation

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02653

Quality control plan for telecommunication

CON STR

DS

CM

X

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

I (for information)

R (review)

A (for approval)

Project document Title

Approved

Unit: General

Checked

Contract Document Reference

Rev.

Prepared

Contract No. 45283

Sh. 47 of 49

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT

Doc. class.: A

2

Document title: Project Quality Plan

Contract Description Reference

Project Document number

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02661

Quality control plan for rotating machineries

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02671

Quality control plan for heaters and flares

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02672

Quality control plan for energy packages

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02674

Quality control plan for packages on skids

CON STR

DS

CM

X

E 7.9

Quality plans provided by subcontractors

000-ZA-E-02681

Quality control plan for pipeline

CON STR

DS

CM

X

E 7.8

Quality Assurance During Procurement

000-ZA-E-09604

QA requirements for Vendors

PQM

QUAL

PM

X

E attachment 3 6.3.9.1

Product Identification and Traceability

000-AZ-E-02014

Positive material identification (PMI)

CM

PM

PM

X

E 7.4

Non-Conformance

000-AZ-E-02033

Site nonconformity management procedure

CM

PM

PM

X

HSEM

PM

X

HSE

HSE M

65.0 ENVIRONMENTAL IMPACT ASSESSMENT E 11.3

Environmental Impact Assessment

000-ZA-E-85803

Environmental Management Plan

HSE

Hazard and operability (HAZOP) studies

000-ZA-E-85830

HAZOP procedure

HSEM

67.0 HAZOP E 13

X

Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.

I (for information)

R (review)

A (for approval)

Project document Title

Approved

Unit: General

Checked

Contract Document Reference

Rev.

Prepared

Contract No. 45283

Sh. 48 of 49

JOB

UNIT

032092

000

SPC. 000-ZA-E-09600 NEW BOOSTER STATION BS-171 AT WEST KUWAIT Contract No. 45283

Sh. 49 of 49 Rev.

Doc. class.: A

2

Document title: Project Quality Plan Unit: General

ANNEXURE 3 – QA/QC PERSONAL

Note: Inspector can cover position on one or more site. Data file:09600-2.doc This document is the property of Saipem Spa who will safeguard its rights according to the civil and penal provisions of the law.