05 Loadout of Offshore Platform
Short Description
Download 05 Loadout of Offshore Platform...
Description
LOADOUT AND INSTALLATION OF OFFSHORE PLATFORM
Presented by Mr. Therasap Rattanapat
Loadout Method Loadout by Crane Lifting •
Loadout by Skidding - Winching - Strand Jack - Push-Pull System
3) Loadout by Crane Lifting
Loadout Method Selection of Loadout Method 1) Platform Weight - Approx < 6,000Te Æ Loadout by dolly - Approx > 6,000Te Æ Loadout by Skidding 2) Available Equipment Capacity - Lifting by Yard Crane Æ Normally the Maximum crawler capacity is 1,000Te, can be lifted loadout of 400Te platform weight. - Lifting by Derrick Crane Barge Æ 3,000Te capacity 3) Cargo Stowage Plan 4) Installation Method - Installation by Crane Lifting or Launching or Float-over Method
Loadout Method Facilities CPP Jacket Topside
Load-out Method Skidding and Ballasting
Transportation Method
Installation Method
Barge
Launching / crane assisted upending Float-over
Barge
Side-lifting and crane assisted upending
Barge
Side-lifting and crane assisted upending
Barge
Side-lifting
Barge
Side-lifting and crane assisted upending
QP Jacket Topside
Rolling (Dolly)
FP/T Jacket Topside
Rolling (Dolly) Lifting
Bridge
Rolling (Dolly) Lifting
Wellhead Jacket Topside
Rolling (Dolly) Lifting
Loadout Equipment Dolly – Self Propelled Modular Transport (SPMT)
Loadout Equipment Push – Pull System (For Skidding Loadout)
Loadout Equipment Strand Jack (For Skidding Loadout)
Loadout Equipment Ballasting Pump (for Barge Ballasting)
Loadout Equipment Ballasting Pump (for Barge Ballasting)
Capacity 500 Cu.m/Hr
Loadout Equipment Ballasting Pump (for Barge Ballasting)
Capacity 1,000 Cu.m/Hr
Loadout Equipment Ballasting Pump (for Barge Ballasting)
Capacity 1,000 Cu.m/Hr
Example of Loadout by Dolly LOADOUT FLOW CHART BARGE PORT IN @ TNS WHARF
PRE-LOADOUT
ALONGSIDE AND MOORING
JHA MEETING / RISK ASSESSMENT
INSTALL LOADOUT BEAM
GAS FREE CHECK
MOBILIZATION OF MWS PRE-LOADOUT MEETING
SETTING SPMT
BARGE JOINT INSPECTION
SITE MOVE TO WHARF
BARGE HANDOVER
INSTALL RAMP BETWEEN BARGE AND WHARF
BARGE PRE-BALLASTING LOADOUT CERTIFICATE ISSUE BY MWS LOADOUT TO BARGE
INNITIAL SEAFASTENING
TOWING BALLAST
COMPLETE SEAFASTENING
INSPECTION BY MWS SAILAWAY CERTIFICATE ISSUE BY MWS
CASTING OFF MOORING LINE AND BARGE HANDOVER
SAILAWAY
Example of Loadout by Dolly LOADOUT JETTY
Example of Loadout by Dolly LOADOUT JETTY Jetty No.1, 2 & 3 Total Depth 8.6m
Jetty No.4 Total Depth 12.6m
Example of Loadout by Dolly BATHYMETRIC SURVEY OF RIVER BASE LEVEL
Example of Loadout by Dolly DESIGN CRITERIA FOR BARGE MOORING
Example of Loadout by Dolly TIDE DATA RELATED TO LOADOUT
Example of Loadout by Dolly WEIGHT CONTROL REPORT FOR JACKET
Example of Loadout by Dolly REACTION CALCULATION FOR JACKET LOADOUT
JK LOADOUT REACTION CALCULATION -1025Te weight -Calculation as 3 points suspension -Gross Capacity of SPMT is 34Te/Axle line -Pay load capacity is 30Te/axle line -Maximum allowable loading is 90% of gross capacity
Example of Loadout by Dolly WEIGHT CONTROL REPORT FOR TOPSIDE
Example of Loadout by Dolly REACTION CALCULATION FOR TOPSIDE LOADOUT
TOPSIDE LOADOUT REACTION CALCULATION -2098Te weight -Calculation as 3 points suspension -Gross Capacity of SPMT is 34Te/Axle line -Pay load capacity is 30Te/axle line -Maximum allowable loading is 90% of gross capacity
Example of Loadout by Dolly SPMT ARRANGEMENT FOR JACKET LOADOUT
Example of Loadout by Dolly SPMT ARRANGEMENT FOR TOPSIDE LOADOUT
Example of Loadout by Dolly BARGE MOORING FOR JACKET LOADOUT
Example of Loadout by Dolly BARGE MOORING FOR TOPSIDE LOADOUT
Example of Loadout by Dolly JACKET LOADOUT ROUTE PLAN
Example of Loadout by Dolly TOPSIDE LOADOUT ROUTE PLAN
Example of Loadout by Dolly LINK SPAN BRIDGE FOR CROSS OVER TO BARGE Clearance between Link Span bridge and jetty shall be maintained 10-200mm along the loadout operation
Example of Loadout by Dolly POST LOADOUT PREPARATION a) Ground will be graded and compacted, any soft spot shall be cover by steel bearing plate b) Any obstruction in loadout route shall be cleared c) Barricated shall be provided along the loadout route d) SPMT shall be assembled to required configuration, function test, pressure test shall be done e) SPMT insert underneath loadout beam / loadout structure. Test lift and confirmed the pressure between 3 points suspension are acceptable, then fastening the cargo to SPMT if necessary. Computer programming for full steering of overall SPMT system (360 degree full steering) f)
Confirmed all grillage support on barge, corrected installed to the designate location, completed weld and NDE cleared.
g) Confirmed barge pre-ballasting in according to calculation and correct ballasting pump setting. h) Confirmed barge mooring i)
Confirmed actual tide level
j)
Confirmed the loadout certificate was obtained from MWS in view of approved for loadout operation
Example of Loadout by Dolly LOADOUT OPERATION a) Start Movement of loadout structure by jacking up the SPMT until the structure cleared from fabrication support. b) Re-confirmed the pressure for all 3 point suspension. c) Start movement from fabrication area to loadout jetty. d) Standby at loadout jetty, waiting the actual tide level. e) Once the actual tide level is meet to the planned in ballasting calculation then start cross over from jetty to barge. f)
Continue the loadout operation, the operation is divided into several steps and between each step necessary ballast changes have to be performed in the same magnitude as transfer of cargo load to barge and tide variation.
g) Ballasting / de-ballasting will be performed according to the pre-arranged ballasting program. h) Barge level as well as trim and heel shall be monitored continuously (shall be within 1% of barge length and width as per normal standard practice) i)
Control clearance between link span and jetty along the operation (10mm minimum, 200mm maximum)
Example of Loadout by Dolly LOADOUT OPERATION (CONTINUE) j)
Once the cargo move to it final position will be lowered down to its support, approximately half load will be transferred from SPMT to its support, then confirm the shimming requirement for all support locations and provide the shim if necessary before lower down fully and 100% load transfer to support.
k) After 100% lower down the cargo to support, SPMT will be retrieved back to shore and making to the end of loadout operation.
Example of Loadout by Dolly Barge Ballasting During Loadout
Ballasting Pumps Setting
Example of Loadout by Dolly Barge Ballasting During Loadout
Example of Loadout by Dolly Barge Ballasting During Loadout
Example of Loadout by Dolly Barge Ballasting During Loadout
Example of Loadout by Dolly Barge Ballasting During Loadout
Example of Loadout by Dolly Barge Ballasting During Loadout
Example of Loadout by Dolly Barge Ballasting During Loadout
LOAD OUT OPERATION / TOOL BOX MEETING
JACKET MOVEMENT TO LOAD OUT QUAY
JACKET LOAD OUT ONTO CARGO BARGE
JACKET LOAD OUT ONTO CARGO BARGE
DECK MOVEMENT TO LOAD OUT QUAY
DECK LOAD OUT ONTO CARGO BARGE
DECK LOAD OUT ONTO CARGO BARGE
Example of Loadout by Dolly POST LOADOUT OPERATION j)
Initial seafastening shall be provided to cargo immediately before any inshore barge maneuver.
k) Loadout of ship losses item and seafastening. l)
Barge shall be ballasted to sea-towing condition.
m) Installed all seafastening tie-down braces and fully welded with NDE clear. n) Barge final inspection by MWS o) Obtained the Sail-away Certificate from MWS. p) Barge ready for Sail-away to offshore field. q) Barge handover to transportation contractor. r) Sail-away
Transportation by using Barge
I : Installation by Launching and Crane assisted upending
Installation by side-lifting Crane-assisted upending
Installation by Float-over method
Pilling
Top Side Installation
C : Commissioning Hook-up piping – Christmas tree – Riser & Sealine – Piping interface
Hook-up E&I – –
Cable tray Tubing & Instrument
Hook-up structure – Boat-landing – Riser Clamp – Conductor
Pipeline Installation
Pipe-lay Methods
Platform Decommissioning Platform Decommissioning Scope covers: Process Decommissioning Well Abandonment Hook Down Offshore Removal (and disposal) Onshore Disposal Pipeline Decommissioning Drill Cutting Disposal
Platform Decommissioning Types of Platform Decommissioning Options
Total Removal Partial Removal Reverse Installation Piece Small Toppling Artificial Reef (Rig to Reef)
Platform Decommissioning Rig to Reef
Artificial Reef providing hard surfaces for encrusting organism such as spiny oysters, barnacles, sponges and corals. A food chain in what becomes a new new marine ecosystem for numerous types of fishes, sharks, sea turtles, spiny spiny lobsters and sea urchins. The fish populations around artificial reefs are so abundant that that many people enjoy going “Rig Fishing” Fishing” or sport fishing to take advantage of the easy catches.
Decommissioning Technology Platform Decommissioning by Versatruss
Current & New Decommissioning Technology Heavy Lift Vessel (Both Topsides & Jackets)[DLB Kuroshio class of DLBs] DLBs]
Versatruss (Topsides)[Lifted: Topsides)[Lifted: 6000 US tons Topside] Smart Leg (Topsides) [Current Design limit: 20,000 tons in 2m/12sec significant swell]
Conceptual Heavy Lift Equipment which are not been built yet
Pieter Schelte (Topsides) Offshore Shuttle (Topsides) Mastermind (Topsides) MPU Heavy Lifter (Topsides) Versatruss (Jackets) Controlled Variable Buoyancy System [CVBS] (Jackets)
Removal Techniques
Abrasive Water Jet Explosives Mechanical Cutter Oxy Arc Torch Standard Diamond Wire Sub Bottom Cutter (SBC)
Diamond Wire Cutter
MECHANICAL CUTTERS
REMOVAL TECHNIQUES
-
- & # PROTECTION ABRASIVE WATER JET - Abrasive (Al, Zn, Si, Cu, Sn, Sn, Pb) Pb) - 1 Ton/hr AV. EVALUATION MATRIX EXPLOSIVES # Hazardous materials - Soil particles, structure scraps, shock waves
ENVIRONMENT
PROTECTION EXCELLENT
MECHANICAL CUTTERS
VERY GOOD
GOOD
POOR
VERY POOR
POOR
GOOD
VERY GOOD
EXCELLENT
- Structure/tool scraps OXY ARC - TORCH # Diver operated - Hot cutting (poor recycling) STANDARD DIAMOND WIRE - Soil particles SBC #Remotely operated - Environment-friendly dredging
#
HEALTH & SAFETY PROTECTION
The First Decommissioning Platform Project In Malaysia (Ketam Project)
The First Decommissioning Platform Project In Malaysia (Ketam Project) Removal of Helideck (Top Section)
Removal of Helideck (Lower Section)
The First Decommissioning Platform Project In Malaysia (Ketam Project) Cut by External Cutter
Removed Conductors
The First Decommissioning Platform Project In Malaysia (Ketam Project)
Lifting of Deck
Flooding Pipe
Flooding Pipe
The First Ever Decommissioning Platform Project In Malaysia (Ketam Project) Internal Cutting Tool
Insert of Internal Cutting Tool
The First Decommissioning Platform Project In Malaysia (Ketam Project)
Internal Lifting Tool
Lifting of Pile by Internal Lifting Tool
The First Decommissioning Platform Project In Malaysia (Ketam Project) Welding of Pad Eye
Lift off Jacket Upper Section
Place Jacket Upper Section on Barge
The First Decommissioning Platform Project In Malaysia (Ketam Project)
Lifting of Jacket Lower Section
Place Jacket Lower Section On Barge
Removed Jacket on Barge
Conclusion
Successful gas exploration and development generally progresses through five basic operational phase I. Preliminary investigation ( includes geophysical exploration) II. Exploratory drilling III. Field development IV. Production V. Decommissioning (Plugging and Reclamation)
Thank you very much
View more...
Comments