Pearl GTL Project Shell Project No: HP-3000-QAT Project Document Number: T- 4.234.572
Purchase Order Number:
2MH127
Tag/Item Number(s):
N/A
Unit(s):
ASU
PCWBS:
Z
LINDE ENGINEERING
Contractor Project No: Project Rev.: A
Page 2 of 8
5887
QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION
E
A
15.02.09
Ready for Construction
SB
EO
AG
RFC
D
O
04.01.09
Company Comments Incorporated
SB
AB
AG
CCI
C
O
30.12.08
Issued for Company Comments
SB
AB
AG
ICC
B
18.12.08
Issued for Review
SB
EO
AG
IFR
A
25.11.08
Issued for Internal Review
SB
EO
AG
IIR
Date
Description
GAMA Rev. No.
Project Rev No.
Prepared Checked Approved By By By ORIGINATOR
Status
Document Title:
LINDEGINEERING AG
ITP FOR INSTALLATION OF GYPSUM BOARD (BUILDINGS) Document No.
Contractor
Gama Qatar Co. W. L. L.
LOC470 GAM
ITP
QAC
GTL
044
E
Org. Code
Doc. Type
Disc. Code
Geogr. Area
Seq. No
Rev. No
Project Document Number: T- 4.234.572
Vendor Code
Rev No: A
QSGTL PEARL PROJECT C2 ASU Construction Works
ITP FOR INSTALLATION OF GYPSUM BOARD (Buildings) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
Document No.: GAM-ITP-QAC-GTL- 044 Date: 15.02.2009 Rev. E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory) Item
1.0 1.1 2.0 2.1
2.2 3.0
3.1
3.2
Activity
Test Frequency
METHOD STATEMENTS/PROCEDURES Method Statements / Prior to start of Procedures activity Preparation
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
X
Subcontractor Method Statements / Procedure
Project Requirements
QA/QC
Project Specifications & Material Approval Request
H
R R
Manufacturers Technical data sheet, certificates
QC – Civil Inspector
Manufacturers Technical data sheets & certificates
H
R R
Manufacturer’s recommendation.
QC – Civil Inspector
Visual confirmation
I
S S
QC – Civil Inspector
GAM-QCR-QACGTL- 168
I
S S
QC – Civil Inspector
GAM-QCR-QACGTL-166
I
W S
C
MATERIALS CERTIFICATES Verification of Acoustical & rock wool material. Storage and handling of Acoustical & rock wool material. INSPECTIONS Environmental Conditions 1. Ambient temp.
Inspection for surface preparation ( Repairing the surface of R.C.C Wall)
T- 4.234.572
Rev. A
100%
100%
100%
100%
T.4.234582 , DEP 34.17.00.32-Gen & DEP 34.17.10.30-Gen T.4.234.582 , DEP 34.17.00.32-Gen & DEP 34.17.10.30-Gen
T.4.234.582 , DEP 34.17.00.32-Gen & DEP 34.17.10.30-Gen
T.4.234.582 & T.4.234.555
DEP 34.17.00.32Gen & DEP 34.17.10.30-Gen & Manufacturer’s data sheet DEP 34.17.00.32Gen & DEP 34.17.10.30-Gen & Manufacturer’s data sheet
Page 4
A
QSGTL PEARL PROJECT C2 ASU Construction Works
ITP FOR GYPSUM BOARD INSTALLATION (Buildings) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
Document No.: GAM-ITP-QAC-GTL- 044 Date: 15.02.2009 Rev. E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
X
100%
T.4.234.582 , DEP 34.17.00.32-Gen & DEP 34.17.10.30-Gen
T.4.234.555 Procedure for Building works
QC – Civil Inspector
GAM-QCR-QACGTL-168
I
W S
T.4.234.582 & Manufacturer’s recommendation
Manufacturer’s recommendation & RFC drawings
QC – Civil Inspector
GAM-QCR-QACGTL-168
I
S
T.4.234.582 & Manufacturer’s recommendation
Manufacturer’s recommendation & RFC drawings
QC – Civil Inspector
GAM-QCR-QACGTL-168
I
W S
T.4.234.582 & Manufacturer’s recommendation
Manufacturer’s recommendation
QC – Civil Inspector
GAM-QCR-QACGTL-168
I
S
S
Visual confirmation
Site Engineer & QC – Civil Inspector
Check Records & Punch List
I
H
W
3.3
Inspection for installation of framing system
3.4
Inspection for Installation of Conduits (If applicable)
100%
3.5
Inspection for 40mm thick rock wool insulation
100%
3.6
In process inspection of Gypsum Board Installation system
100%
3.7
Final inspection & Punch Listing
T- 4.234.572
Rev. A
100%
Mechanical Completion Documentation
Page 5
C
S
A
QSGTL PEARL PROJECT C2 ASU Construction Works
ITP FOR GYPSUM BOARD INSTALLATION (Buildings) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
Document No.: GAM-ITP-QAC-GTL- 044 Date: 15.02.2009 Rev. E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory) Item
3.8
Activity
Disposal of high risk wastes such as rock wool waste & gypsum board waste.
T- 4.234.572
Rev. A
Test Frequency
100%
Reference Document
Acceptance Criteria
T.13.377.450Construction waste Management Procedure
Check & ensure in Hazard area ,flammable area any paint material
Responsible Party
Verifying Documents
S
X
C
Visual
I
S S
Site Engineer
Page 6
A
QSGTL-PEARL GTL PROJECT C2-ASU-Construction Project Inspection Form for Surface Preparation(Buildings) GAM-QCR-QAC-GTL-166 Rev. O
Date :
GAM-ITP-QAC-GTL-
Location Bldg/Area: Drawing No: Tag No and Tag description :
Item
Details of Activity
Remarks
Sign off will Confirm Released to Next activity GAMA QATAR Name
Signature
Date
LINDE
QSGTL or its PMC
QSGTL PEARL PROJECT C2 ASU Construction Works FORM NO: GAM-QCRQAC-GTL-168 Rev. O
Gypsum Board , Suspended Ceiling Date: works & Rock Wool Installation ITP No: GAM–ITP–QAC–GTLCheck List
Report No: Item description: Item location/area: Drawing reference:
Ambient Temp. :
Tag No & Description:
Ref.
DETAIL OF ACTIVITY
1
GYPSUM BOARD WORK Dimensionally correct plumb, level and square etc ... complete. Screws, Anchors, U-Channels, Studs, Brackets fixing. Application of Joint Filler or joint tape etc ... complete.
1.1 1.2 1.3 2 2.1 2.2 2.3
Hangers, channels, studs, furring correctly spaced, braced. Plumbed and level Material application and jointing correctly installed at ceilings, openings and fittings Trims are installed level and clean.
4 5
Work area is clean and free from debris
3.1 3.2 3.3
REMARKS
SUSPENDED CEILING
ROCK WOOL INSULATION ( Roof & Wall) Positioning, grouting and curing in accord with codes of practice and vendor instructions Finish with plumb, level, clean and free from spalls Gaps and coursing, expansion joints, stained joints are in accord with the relevant drawing and specifications All works are Completed with final touch-ups
3
COMPLIANCE YES NO N/A
SIGN OFF AS ACCEPTED GAMA QATAR Name
Signature
Date
LINDE
QSGTL or its PMC
0
C