INSPECTION AND TESTING PLAN - VERSION 2
SENARAI KANDUNGAN BIL. 1.0 2.0 3.0 3.1 3.2 3.3 3.4 3.4.1 3.4.2 3.4.3 3.4.4 3.4.5 3.4.6 3.4.7 3.4.8 3.4.9 3.4.10 3.4.11 3.5 3.5.1 3.5.2 3.5.2.1 3.5.2.2 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.9.1 4.9.2 4.9.3 4.9.4 4.9.5 5.0 5.1 5.2 5.3 5.4
BIDANG KERJA / TRADE PRAKATA PENGHARGAAN KERJA GEOTEKNIK Site Investigation / Soil Investigation (New Trade) Earthworks (Revised Version 1) Ground Improvement (New Trade) Slope Stabilization Rock Bolt And Rock Dowel (New Trade) Reinforced Soil Slope (New Trade) Reinforced Soil Wall (Revised Version 1) Reinforced Soil Structure (New Trade) Tie Back Wall (New Trade) Ground Anchor (New Trade) Soil Nailing (New Trade) Geocell (New Trade) Guniting (New Trade) Horizontal Drain (New Trade) Hydroseeding (New Trade) Kerja Asas / Foundation Shallow Foundation (Revised Volume 2) Deep Foundation / Piling Works Pre-Cast Driven / Jacked – In Pile (New Trade) Cast-insitu Bored Pile / Micro Pile (New Trade) KERJA JALAN Flexible Pavement (Revised Version 1) Specialty Mix 1 - Porous Asphalt (Revised Volume 2) Specialty Mix 2 - Stone Mastic Asphalt (Revised Volume 2) Specialty Mix 3 - Gap Graded Asphalt (Revised Volume 2) Specialty Mix 4 - Hot In-Place Recycling (Revised Volume 2) Specialty Mix 5 - Cold In - Place Recycling (Revised Volume 2) Specialty Mix 6 - Polymer Modified Asphaltic Concrete (Revised Volume 2) Road Shoulders (New Trade) Road Furniture Corrugated Sheet Steel Beam Highway Guardrail (Revised Version 1) Concrete Kerb (Revised Version 1) Wire Rope Safety Fence (Revised Version 1) Road Marking (Revised latest – SPJ) Traffic Signs (Revised Version 1) KERJA SIVIL Drainage Works (Revised Volume 2) Sewerage Works (Revised Volume 2) External Water Reticulation (Revised Volume 2) Internal Road And Hard-standing (Revised Volume 2)
MUKA SURAT iv vi 2-3 4-5 6-7 8 9 10 11 12 13 14 15 16 17 18 19 20-21 22-23 25-30 31-34 35-38 39-41 42-44 45-47 48-51 52-53 54-55 56-57 58 59-61 62-66 68-70 71-73 74-77 78-79 i
INSPECTION AND TESTING PLAN - VERSION 2
SENARAI KANDUNGAN BIL.
BIDANG KERJA / TRADE
MUKA SURAT
6.0 6.1 6.2 6.2.1 6.2.2 6.3
KERJA STRUKTUR Concrete Works (Revised Volume 2) Roof Structure Pre-Fabricated Cold Formed Steel Roof Truss (Revised Volume 2) Pre-Fabricated Timber Roof Truss (New Trade) Steel Structure (Revised Volume 2)
86-92 93-101 102-104
7.0 7.1 7.2 7.3 7.4 7.5 7.6 7.7 7.8 7.9 7.10 7.11 7.12
KERJA ARKITEK Flooring/Rendering Works (New Trade) Water Proofing (New Trade) Tiling Works (Floor/Wall Tiles) (Revised Version 1) Plastering Works (Revised Version 1) Door, Window And Ironmongery (Revised Version 1) Ceiling Works (Revised Version 1) Roof Covering (Revised Version 1) Painting Works (Revised Version 1) Sanitary Ware & Fittings (Revised Version 1) Interior, Signage & Graphic (Revised Version 1) Softscape Works (Revised Version 1) Hardscape Works (Revised Version 1)
106-107 108-109 110-111 112 113 114-115 116-117 118-119 120 121 122 123
8.0 8.1 8.2
KERJA LAPANGAN TERBANG Rigid Pavement (New Trade) Flexible Pavement (New Trade)
125 126-127
9.0 9.1 9.2 9.3 9.4 9.5
KERJA MARIN Fender (New Trade) Bollard (New Trade) Cathodic Protection (New Trade) Revetment (New Trade) Steel Pontoon (New Trade)
129 130 131 132-133 134
10.0 10.1 10.2 10.3 10.4 10.5 10.6 10.7 10.8
KERJA MEKANIKAL Air-conditioning System (Revised Version 1) Fire Fighting System (Revised Version 1) Cold Water System (Revised Volume 2) Sanitary Plumbing System (Revised Volume 2) Lift System (Revised Volume 2) Building Automation System (New Trade) Kitchen Equipment & Ancillary System (New Trade) LPG System (New Trade)
136-138 139-142 143-144 145 146-148 149-151 152-153 154-155
81-85
ii
INSPECTION AND TESTING PLAN - VERSION 2
SENARAI KANDUNGAN BIL.
BIDANG KERJA / TRADE
11.0 11.1 11.1.1 11.1.2
KERJA ELEKTRIK Low Voltage Electrical Boards (Revised Version 1) Wiring System & Underground Cable (Revised Version 1)
11.1.3 11.1.4 11.1.5 11.2 1.2.1 11.3 11.3.1 11.3.2 11.3.3
Lightning Protection System (Revised Version 1) Standby Generator Set (Revised Version 1) Road Lighting System (Revised Volume 2) Extra Low Voltage PA System (Revised Version 1) ICT & Telephone External Installation For ICT & Telephone (Revised Version 1) Internal Installation For ICT : Active Equipment (Revised Version 1) Internal Installation For Passive Equipment And ICT Room (Revised Volume 2) Internal Installation For Telephone (Revised Volume 2) Medical Equipment General Radiography - Outsource (Revised Version 1) Examination Light - Outsource (Revised Version 1) Surgical Light - Outsource (Revised Version 1) Surgical Table - Outsource (Revised Version 1) High Tension System 11kV DRY TYPE TRANSFORMER (Revised Volume 2) Ht Switchgear (Revised Volume 2) Traffic Signal Light (New Trade)
11.3.4 11.4 11.4.1 11.4.2 11.4.3 11.4.4 11.5 11.5.1 11.5.2 11.6
MUKA SURAT
157-158 159-162 163-164 165-166 167-170 171-172 173-174 175-176 177 178 179 180 181 182 183-186 187-188 189-192
iii
PRAKATA Jabatan Kerja Raya (JKR) sebagai jabatan teknikal terunggul komited dalam memastikan kehendak pelanggan dapat direalisasikan melalui penghasilan produk yang berkualiti. Pelan Pemeriksaan dan Pengujian (Inspection and Testing Plan, ITP ) terhadap bahan dan kaedah pemasangan/pembinaan merupakan salah satu proses yang penting dalam mencapai maksud tersebut. Dokumen ITP ini merupakan dokumen rujukan dan dokumen sokongan bagi membantu staf JKR di dalam melaksanakan projek dan ia tidak terikat dengan peraturan kontrak. ITP bagi pelaksanaan projek yang dinyatakan di dalam SPB JKR di mana kontraktor perlu mengemukakan Senarai ITP di dalam C-Plan. Walau bagaimanapun, pembangunan ITP ini adalah untuk membantu staf JKR dan sebagai panduan bagi menyemak ITP yang diserahkan oleh pihak kontraktor. ITP merupakan satu alat (tool ) program Quality Assurance di mana diskripsi secara terperinci mengenai Quality Control dan aktiviti-aktiviti yang perlu dilakukan di tapak bina berpandukan standard yang ditetapkan. Aktiviti pemeriksaan dan ujian dalam ITP merangkumi semua aktiviti sebelum, semasa dan selepas (i.e : manufacturing, fabrication, construction and installation) proses penzahiran sesuatu produk. Ini bertujuan memastikan kualiti sesuatu produk itu memenuhi kriteria dan standard yang dimaksudkan. Penghasilan ITP Edisi 2012 : Versi 1 & ITP Edisi 2013 : Volume 2 telah membantu JKR untuk memenuhi keperluan dan kehendak Seksyen 7.1 Manual Pengurusan Sistem Bersepadu (MPSB) : Perancangan Bagi Penzahiran Produk iaitu “Keperluan verifikasi, validasi, pemantauan, pemeriksaan serta pengujian ke atas proses/aktiviti tertentu dalam penzahiran produk serta ciri-ciri produk yang diterima”. Kesinambungan daripada kejayaan pembangunan ITP Edisi 2012 : Versi 1 dan ITP Edisi 2013 : Volume 2 telah mendorong JKR untuk mengambil inisiatif dalam penambahbaikan ITP dengan membentuk pasukan penggubal berdasarkan Subject Matter Expert (SME) untuk membangunkan ITP Edisi 2015 : Versi 2. Selaku Urus Setia, Bahagian Pengurusan Kualiti, Cawangan Dasar Dan Pengurusan Korporat telah mengatur beberapa siri mesyuarat dan bengkel dalam memastikan kejayaan pembangunan ITP Edisi 2015 : Versi 2 ini. Dokumen ITP Edisi 2015 : Versi 2 ini mengandungi gabungan ITP Edisi 2012 : Versi 1 dan ITP Edisi 2013 : Volume 2 yang telah dibuat penambahbaikan serta pembangunan trade-trade baru yang keseluruhannya merangkumi sembilan (9) bidang kerja utama iaitu Geoteknik, Kerja Jalan, Kerja Sivil, Kerja Struktur, Kerja Arkitek, Kerja Lapangan Terbang,
iv
Kerja Marin, Kerja Mekanikal, dan Kerja Elektrik. Jumlah keseluruhan trade yang telah dibangunkan adalah sebanyak lapan puluh dua (82) trade berbanding dua puluh lapan (28) trade untuk ITP Edisi 2013 : Volume 2 dan tiga puluh tiga (33) trade untuk ITP Edisi 2012 : Versi 1 sebelum ini . Selain itu, setiap trade Dokumen ITP yang dibangunkan mengandungi Description Of Works, Point Of Inspection/Test, Standard/Requirement, Tools/Equipment serta Stage/Frequency dan penambahbaikan di dalam ITP Versi 2 Tahun 2015 dengan penyeragaman kepada jadual trade di ruangan Evidence, Responsibility dan Remarks bagi ITP Edisi : Versi 1 dan trade terkini. Dengan terhasilnya Dokumen ITP Edisi 2015 : Versi 2, adalah diharapkan ianya dapat membantu staf JKR untuk melaksanakan projek dan seterusnya menyumbang ke arah mencapai objektif JKR iaitu “Menyerahkan projek yang menepati kualiti, masa dan kos yang telah ditetapkan”.
Disediakan oleh: Urus Setia Sistem Pengurusan Bersepadu (SPB) Bahagian Pengurusan Kualiti, Cawangan Dasar Dan Pengurusan Korporat JKR Malaysia
v
PENGHARGAAN Setinggi-tinggi penghargaan dan terima kasih kepada semua yang terlibat seperti berikut: Penasihat :
Ir. Hj. Mohd Jamal Bin Sulaiman (Pengarah Cawangan Dasar Dan Pengurusan Korporat)
Pengerusi :
Ir. Hajah Ruhani Binti Haji Ali (Ketua Bahagian Pengurusan Kualiti, CDPK)
Fasilitator :
Ir. Abdul Hadi Bin Abdul Aziz Ir. Hj. Mohamad Sharip Bin Wahijan
Penggubal :
1)
CKG
Bidang Kerja Geoteknik En. Mohd Khair Bin Nordin Pn. Eng Boon Cheng Pn. Hani Nadzrah Binti Razali
CKC
Ir. Zainal Arsad Bin Md Amin Pn. Siti Zarina Binti Ngajam Pn. Sakinah Binti Dahrawi Edrus
CJ
2)
Bidang Kerja Jalan Ir. Wan Abdul Rahman Bin Wan Hassan Ir. Abdul Rahman Bin Baharuddin Ir. Abdul Mutalif Bin Abdul Hameed Ir. Hj. Othman Bin Ibrahim Ir. Asraruddin Bin Jaafar Ir. Lai Khin Onn En. Shahrul Nizam Bin Siajam En. Mohd Azral Bin Mat Jusoh
CKAS
3)
Bidang Kerja Sivil Ir. Wan Sohaimi Bin W an Mohamed Pn. Norhayati Binti Khairudin Ir. Ismail Bin Abd Rahman Pn. Aiedah @ Noraidah Binti Nadzri En. Amir Asrol Bin Ahmad Bangi En. James Anak Musa Pn. Nurzalisa Binti Abd Rahim Pn. Haslina Binti Salim
vi
CKAS
En. Shaiful Munir Bin Leman En. Mohd Fariz Adlan Bin Jasri En. Mohd Firdaus Bin Barjumin 4)
Bidang Kerja Struktur Ir. Norazman Bin Ismail Hj. Ahmad Rosli Bin Abd Rahman Ir. Mohd Azhari Bin Mohd Salleh Ir. Noraidah Binti Yahya Ir. Mohd Zamri Bin Abdullah Ir. Hilmi Bin Md. Tahir Pn. Melati Binti Mudzaffar Ali En. Mohd Fairuz Bin Muhamad Ir. Zamilah Binti Said Pn. Siti Radiah Binti Yunus En. Saiful Azzuan Bin Aznam Pn. Lee Choon Siang Pn. Durrah Munierahhannies Binti Azizan En. Megat Kamarulzaman Bin Megat Yusoff
CA
5)
Kerja Arkitek En. Saiful Fazli Bin Ramli En. Muhammad Zaki Bin Abd Manaf Pn. Nur Liyana Binti Amer Hamzah En. Somphob Charenchit En. Jabez Ho Chen Kwang
CPUM
6)
Kerja Lapangan Terbang En. Muhammad Khazani Bin Abd Rahman En. Mohd Noh Bin Karim En. Samri Haji Embong En. Mahalil Bin Mohtar
7)
Kerja Marin En. Azarul Azlan Bin Mohd Radhi En. Anuar Bin Pawan Cik.Syuhaida Binti Suaib En. Adam Bin Ali
vii
CKM
8)
Kerja Mekanikal Ir. Zulkifli Abdul Rashad Ir.Mohamad Azly Abdul Aziz Ir. Wan Shah Waliallah B.Wan Senik En. Muhammad Nazri B.Omar En. Izzat Zumairi Che Harun Ir.Hisham B. Mokhtar Pn. Warnida Bt. Abu Bakar En. Ahmad Fadzli Bin Mohamed Yusoff
CKE
9)
Kerja Elektrik Ir. Hj. Mohd Jahini Bin Mohd Dom Pn. Noor Hafiza Binti Noor Kassim Pn. Nur Hafizah Binti Bahari En. Ahmad Noor Ikmal Bin Mohamad En. Johari Bin Husin
10)
Urus Setia SPB Ir. Hajah Ruhani Binti Haji Ali En. Ramlan Bin Hamzah En. Mohd Nor Sahrul Bin Md Ali Pn. Nurul Syifaa' Binti Ahmad En. Ismail Najmuddin Bin Abdul Hadi En. Puspanathan A/L Periasamy En. Mohamad Azhari Zarzali Shah
viii
1
INSPECTION AND TESTING PLAN - VERSION 2
SITE INVESTIGATION WORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
TRADE : SITE INVESTIGATION ITEM
1
2
DESCRIPT ION OF WORKS
Deep Boring
JKR/ Mackintosh Probe
POINT OF INSPECT ION / TEST
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
Method Of Drilling
JKR/SPJ/2013-S17 Clause 17.2
Visual inspection
Every test location
Contractor/ Photos & SI Report Supervising Engineer
Sampling
JKR/SPJ/2013-S17 Clause 17.3
Visual inspection
Every test location
Contractor/ Photos & SI Report Supervising Engineer
Termination Depth
SI Scope Of Work
Tools to measure depth
Every test location
Contractor/ Borelog Supervising Engineer
Ground Water Level
JKR/SPJ/2013-S17 Clause 17.4.7
Tools to measure depth
Beginning & End Of Shift
Contractor/ Borelog Supervising Engineer
Number of probe/ Locations
Coordinates & Reduce Level
Every test location
Contractor/ As built plan Supervising Engineer
Setting up
Refer to drawings (design requirement) & scope of SI Federal Aviation Administration (FAA) AC 150/5320-6E CI 202 JKR/SPJ/2013-S17 Clause 17.4.5
Termination Depth
JKR/SPJ/2013-S17 Clause 17.4.5
JKR/SPJ/2013-S17 Clause 17.4.1
Testing procedures
4
Trial Pit
Number of trial pit/locations
Quantity of samples condition/quality of sample
Every test location
EVIDENCE
Refer to drawings (design requirement) & scope of SI Federal Aviation Administration (FAA) AC 150/5320-6E CI 202
Standard Penetration Test
Coordinates & Reduce Level
RESPONSIBILITY
Number of borehole/ Locations
3
Nota : ITP ini
STANDARD / R EQUIREM ENT
Contractor/ As built plan Supervising Engineer
Visual inspection
Every test location
Contractor/ Photos & SI Report Supervising Engineer
Digital Counter
Every test location
Contractor/ Probe log Supervising Engineer
Digital Counter & Measurement Tools
Every 1.5m depth
Contractor/ Borelog Supervising Engineer
Refer to construction drawings (design requirement) Federal Aviation Administration (FAA) AC 150/5320-6E CI 202
Coordinates & Reduce Level
Every test location
Contractor/ As built plan Supervising Engineer
JKR/SPJ/20 13-S17 Clause 17.3.8
W eighin g Sca le
Eve ry la yer of soil
Co ntractor / Trial Pit Log Supervising Engineer
REMARKS
Federal Aviation Administration (FAA) AC 150/5320-6E CI 202 for Airport Construction
Federal Aviation Administration (FAA) AC 150/5320-6E CI 202 for Airport Construction
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 2
INSPECTION AND TESTING PLAN - VERSION 2
SITE INVESTIGATIONS WORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
TRADE : SITE INVESTIGATIONS (LAPANGAN TERBANG) ITEM 1
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
STANDARD / REQIUREMENT
TOOL/ EQIUPMENT
STAGE/ FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
SOIL BORING a. Runway & Taxiway
i) Spacing Random along pavement at min 60 m intervals
Federal Aviation Administration (FAA) AC 150/5320 -6E CI 202
Visual, testing and measurement
Once per project/source
Project Manager/ Contractor
Inspection Form/SI Report
b. Other Areas Of Pavement
i) Spacing 1 boring per 930 sq m of area
Federal Aviation Administration (FAA) AC 150/5320 -6E CI 202
Visual, testing and measurement
Once per project/source
Project Manager/ Contractor
Inspection Form/SI Report
c. Borrow Areas
i) Spacing Sufficient tests to clearly define the borrow material
Federal Aviation Administration (FAA) AC 150/5320 -6E CI 202
Visual, testing and measurement
Once per project/source
Project Manager/ Contractor
Inspection Form/SI Report
ii) Depth To depth of borrow excavation 2
SOIL STRENGTH TESTS a. CBR test
Sufficient Test to clearly to defined soil strength
Federal Aviation Administration (FAA) AC 150/5320 -6E CI 205
Visual, testing and measurement
As per requirement
Project Manager/ Contractor
Inspection Form
b. Plate Bearing test
Sufficient Test to clearly to defined soil strength
Federal Aviation Administration (FAA) AC 150/5320 -6E CI 205
Visual, testing and measurement
As per requirement
Project Manager/ Contractor
Inspection Form
ICAO A. Manual Part 2
Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.
3
INSPECTION AND TESTING PLAN - VERSION 2
EARTHWORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
TRADE : EARTHWORKS ITEM
1
2
DESCRIPTION OF WORKS
Site clearing
Excavation
POINT OF INSPECTION / TEST
STAGE / FREQUENCY
Refer to construction drawings or at least 0.5m below ground level
Tools to measure depth
Survey plan
Removal of topsoil
Refer to construction drawings or at least 0.1m below ground level
Tools to measure depth
Survey plan
D im en si on al to le ra nc e ( de pt h)
W id th < 3 00 mm t ha n t he d im en si on s shown on the drawings
Tools to measure depth
When required
Unsuitable material (If any)
JKR/SPJ/2013-S2: Clause 2.2.1 (d) or JKR 20800-0183-14 Section B Cl. 5.2.3
Trial pit
When required
Material laboratory test
Grading of replacement materials
JKR/SPJ/2013-S2: Table 2.1 or JKR 20800-0183-14 Section B Cl. 5.7, Table B1 JKR/SPJ/2013-S2: Clause 2.2.1 (f) and (g) or JKR 20800-0183-14 Section B Cl. 5.2.5, Cl. 5.2.6, Cl. 5.10 JKR/SPJ/2013-S2: Clause 2.2.3.8 or JKR 20800-0183-14 Section B Cl. 5.1.2
Particle Size Distribution (Gradation analysis) Trial excavation
When required
Material laboratory test
When required
Trial excavation record
Trial blasting
When required
Trial blasting record
JKR/SPJ/2013 - Cl. 2.2.4.1 and 2.2.4.2 or Atterberg limit test JKR 20800-0183-14 Section B Cl. 5.2.4 or Federal Aviation Administration (FAA) AC Gradation analysis 150/5320-6E CI 205 Compaction test (MS 1056) Soaked CBR test
The whole site
Contractor/ Project Manager
EVIDENCE
Depth of grubbing
Suitability of materials
Survey equipment
RESPONSIBILITY
JKR/SPJ/2013-S2: Clause 2.1.2.1 Refer to construction drawings
Rock blasting
Fill materials
TOOLS / EQUIPMENT
Area to be cleared
Excavation of hard materials / rock
3
STANDARD / REQUIREMENT
Contractor/ Project Manager
3
One test/ 1500 m of the material to be used
Contractor/ Project Manager
REMARKS
Setting out plan
Survey plan
Material laboratory test Federal Aviation Administration (FAA) AC 150/5320-6E CI 205 & ICAO A. Manual Part 2 for Airport Construction
Federal Aviation Administration (FAA) AC Plate Bearing Test 150/5320-6E CI 205 & ICAO A. Manual Part 2
Nota : ITP ini
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 4
INSPECTION AND TESTING PLAN - VERSION 2
EARTHWORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
TRADE : EARTHWORKS ITEM
4
DESCRIPTION OF WORKS
Construction of embankments
POINT OF INSPECTION / TEST
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
Compaction test (MS One test/ 1500m 3 of 1056) the material to be used
T ri al compact ion t hi ckness
Max imum l oose dept h = 300mm; m ini mum area = 8m x 15m; not required if volume of 3 fill < 100m with approval from SO
Degree of compaction for placement of f ill materials
> 95% for cohesive material Compaction test (MS 1056) > 100% for cohesionless material Air voids < 5% CBR valu es as per specified in the drawing Soaked CBR test or CBR > 10%
One test/ 500m of every compacted layer
Within +10mm and -30mm of the required level.
Completion of work
Cali fornia Bearin g Ratio for subgrade
Shape, super elevation, level, and grade
Nota : ITP ini
STANDARD / REQUIREMENT
Survey equipment
2
RESPONSIBILITY
EVIDENCE
Contractor/ Project Manager
Trial compaction record
REMARKS
Compaction records
2
One test/ 4000m of compacted subgrade As built drawings
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 5
INSPECTION AND TESTING PLAN - VERSION 2
GROUND IMPROVEMENT WORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
TRADE : GROUND IMPROVEMENT I TEM
1
DE SC RI PTI ON O F WO RK S
PO IN T O F I NSPE CT IO N / T ES T
Remove and Replace of Unsuitable Identification of unsuitable material Materials Depth of removal and replacement material
2
Piled Embankment
3
Surcharging
4
5
Nota : ITP ini
Prefabricated Vertical Drain (PVD)
Basal Reinforcement with High Strength Geotextile / Geogrid
S TAND AR D / R EQ UI REM EN T
Refer to SI report
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
N/A
MS 1056 : Part 2 : 2005 or Tools to measure JKR/SPJ/2013-S2: Clause 2.2.1 (d) depth (Criteria for unsuitable materials) or JKR 20800-0183-14 Section B Cl. 5.2.3
Refer to ITP for Piling Works (Driven/ Refer to ITP for Piling Works (Driven/ Refer to ITP for Piling Jacked-in) Jacked-in) Works (Driven/ Jacked-in) Thickness of filling materials and Construction drawing & Refer to ITP for compaction works JKR/SPJ/2013 Clause 2.2.3.5 & Earthworks Clause 2.2.2.1(e) Surcharging period Refer to construction drawings Degree of consolidation & Time Approval of materials, storage and installation equipment
Refer to engineer's specification, manufacturer's instruction and approved method statement PVD installation and depth of driving Refer to construction drawin gs
Method of testing/acceptence criteria Refer to engineer's specification, manufacturer's instruction and approved method statement Approval of materials, storage and Refer to engineer's specification, installation equipment manufacturer's instruction and approved method statement Installation method and coverage Refer to construction drawings, engineer's specification, manufacturer's instruction and approved method statement Method of testing/acceptence criteria Refer to construction drawings, engineer's specification, manufacturer's instruction and approved method statement
N/A
Before and after removal work
RESPONSIBILITY
EVIDENCE
REMARKS
Contractor/ Lab test results & Supervising Engineer drawing Contractor/ SI Report & Lab test Supervising Engineer results & survey records
Refer to ITP for Piling Contractor/ As built plan Works (Driven/ Supervising Engineer Jacked-in) Refer to ITP for Contractor/ As built plan Earthworks Supervising Engineer As per engineer's instruction
Visual inspection, lab Prior to PVD test on samples installation
Contractor/ Settlement records Supervising Engineer Contractor/ Quality records, Lab Supervising Engineer test result
Visual inspection, Every installation point Contractor/ Quality records installation record Supervising Engineer verification Visual inspection, Every installation point Contractor/ Quality records installation record Supervising Engineer verification Visual inspection, lab Prior to installation Contractor/ Quality records, Lab test on samples Supervising Engineer test result Visual inspection, installation record verification
Every installation point
Contractor/ Quality records Supervising Engineer
Visual inspection, installation record verification
Refer to construction drawings & method statement
Contractor/ Borelog Supervising Engineer
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 6
INSPECTION AND TESTING PLAN - VERSION 2
GROUND IMPROVEMENT WORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
TRADE : GROUND IMPROVEMENT I TEM
6
7
DE SC RI PTI ON O F WO RK S
Stone column
Instrumentation
PO IN T O F I NSPE CT IO N / T ES T
Approval of materials, storage and installation equipment
Refer to engineer's specification, manufacturer's instruction and approved method statement Installation method and depth Refer to construction drawings, engineer's specification, manufacturer's instruction and approved method statement Method of testing/acceptence criteria Refer to construction drawings, engineer's specification, manufacturer's instruction and approved method statement Installation of instrumentation Refer to construction drawings & JKR/SPJ/2013 Clause 2.2.6.3 Location of monitoring instruments
Monitoring record
Acceptance criteria
Nota : ITP ini
S TAND AR D / R EQ UI REM EN T
At location and level as shown on drawings and protected from disturbances especially from being run down by construction machineries Refer to construction drawings & JKR/SPJ/2013 Clause 2.2.6.4
Refer to construction drawings
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
Visual inspection, any Prior to installation Contractor/ Quality records, Lab test specified by Supervising Engineer test result Engineer visual inspection, Every installation point Contractor/ Quality records installation record Supervising Engineer verification Visual inspection, load Refer to construction test drawings & method statement
Contractor/ Borelog Supervising Engineer
Visual inspection, any Prior to installation Contractor/ Quality records, Lab test specified by Supervising Engineer test result Engineer Visual inspection, Every installation point Contractor/ Quality records installation record Supervising Engineer verification
visual inspection, installation record verification
Refer to construction drawings & method statement
Settlement monitoringRefer to construction results drawings & method statement
Contractor/ Monitoring reports Supervising Engineer
Contractor/ Settlement records Supervising Engineer
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 7
INSPECTION AND TESTING PLAN - VERSION 2
SLOP STABILIZATION WORKS- ROCK BOLT AND ROCK DOWEL
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
SLOPE STABILIZATION - ROCK BOLT AND ROCK DOWEL ITEM
1
2
3
DESCRIPTIO N OF WORKS
Testing Instrument
Material
Installation
POINT OF INSPECTION / TEST
i. Testing Method ii Suitabi lity Apparatus iii Testing Procedure
i. Physical Condition ii. Structural Capacity
Termination of Drilling
STANDARD/REQUIREM ENT
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
i. JKR/SPJ/2013-S16 Cl. 16.5 ii. Construction drawing
i. JKR/SPJ/2013-S16 Cl. 16.5 ii. Construction drawing
i. JKR/SPJ/2013-S16 Cl. 16.5 ii. Construction drawing
Construction drawing
JKR/SPJ/2013-S16 Cl.16.5
Drilling record
Mat er ia l on sit e
Construction drawing
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
RESPONSIBILITY
EVIDENCE
Contractor / SO
i. Method of Statement ii. Instrument Certificate iii. Testing records & Certificate of conformance iv. RFI v. Drilling Record
Co nt ract or / SO
i. Method of Statement ii. Instrument Certificate iii. Testing records & Certificate of conformance iv. RFI v. Drilling Record
Contractor / SO
i. Method of Statement ii. Instrument Certificate iii. Testing records & Certificate of conformance iv. RFI v. Drilling Record
REMARKS
8
INSPECTION AND TESTING PLAN - VERSION 2
SLOP STABILIZATION WORKS - REINFORCED SOIL SLOPE
KERJA GEOTEKNIK
HELAIAN 1 DARI 1
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
SLOPE STABILISATION - REINFORCED SOIL SLOPE ITEM
DESCRIPTION OF WO RKS
PO INT OF INSPECTION / TEST
STANDARD/REQUIREMENT
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
RESPONSIBILITY
1
Material
i) Physic al condition ii) Strength
i. JKR/SPJ/2013- S16 Cl.16.7 ii. Construc tion Drawing
i. Vi sual ii. Measu rement iii. Testing
Initial and Construction Stage
Contractor / SO
2
H an dl in g a nd St or ag e
i) Visual ii) Measurement
i. JKR/SPJ/2013- S16 Cl.16.7 ii. Construc tion Drawing
i. Vi sual ii. Measu rement iii. Testing
Initial and Construction Stage
Contractor / SO
3
Installation
Level and Location
i. JKR/SPJ/2013-S16Cl. 16.7 ii. Construc tion Drawing
i. Vi sual ii. Measu rement iii. Testing
Initial and Construction Stage
Contractor / SO
4
Backfill and Compaction
Refer to ITP for Earthwork
Refer to ITP for Earthwork
Refer to ITP for Earthwork
Refer to ITP for Earthwork
Refer to ITP for Earthwork
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
EVIDENCE
REMARKS
i. Method statement ii. Certificate of conformance
Refer to ITP for Earthwork
9
INSPECTION AND TESTING PLAN - VERSION 2
REINFORCED SOIL WALL WORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 of 1
SLOPE STABILIZATION : REINFORCED SOIL WALL ITEM
1
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
BS 8006
Every panels/no
EVIDENCE
REMARKS
-
-
-
-
Ap pr ov al M at er ia ls : i) Facing materials
Receiving of materials /
ii) Reinforcing element and connections iii) Hot-dip galvanising
Visual inspection and manufacturer records
Specification for Reinforced Soil Structures and Slopes
iv) Joint filler and sealant V) Fill material
2
Cons truction
Found ation so il / bea ring c apacity
Spe cification for Reinforced Soil Structures an d Slopes & Construction drawings
BS 8006
Initial stage
Erection of elemental facing / verticality and horizontally
Specification for Reinforced Soil Structures and Slopes & Construction drawings
BS 8006
Every layer
Fill materials
Specification for Reinforced Soil Structures and Slopes, Construction drawings & Manufacturer recommendation
BS 8006
Every layer
Specification for Reinforced Soil Structures and Slopes, Construction drawings & Manufacturer recommendation
BS 8006
Every layer
Specification for Reinforced Soil Structures and Slopes, Construction drawings & Manufacturer recommendation
BS 8006
Every layer
Placement of reinforcing elements tensile test / pull out test Connections
Nota: ITP
ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 10
INSPECTION AND TESTING PLAN - VERSION 2
SLOPE STABILIZATION WORKS - REINFORCED SOIL STRUCTURE
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
SLOPE STABILIZATION - REINFORCED SOIL STRUCTURE ITEM
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
STANDARD/REQUIREM ENT
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
RESPONSIBILITY
1
Material
i) Physical condition ii) Structure capacity
i. JKR/SPJ/2013- S16 Cl.16.7 ii. Constru ction Drawing
i. V isual ii. Measurement iii. Testing
Initial and Construction Stage
Contractor / SO
2
H an dl in g a nd St or ag e
i) Visual ii) Measurement
i. JKR/SPJ/2013- S16 Cl.16.7 ii. Constru ction Drawing
i. V isual ii. Measurement iii. Testing
Initial and Construction Stage
Contractor / SO
3
Installation
i) Interlocking ii) Alignment
i. JKR/SPJ/2013-S16Cl. 16.7 ii. Constru ction Drawing
i. V isual ii. Measurement iii. Testing
Initial and Construction Stage
Contractor / SO
4
Backfill and Compaction
Refer to ITP for Earthwork
Refer to ITP for Earthwork
Refer to ITP for Earthwork
Refer to ITP for Earthwork
Refer to ITP for Earthwork
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
EVIDENCE
REMARKS
i. Method statement ii. Certificate of conformance
Refer to ITP for Earthwork
11
INSPECTION AND TESTING PLAN - VERSION 2
SLOPE STABILIZATION WORKS – TIE BACK WALL
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
SLOPE STABILIZATION – TIE BACK WALL ITEM
DESCRIPTION OF WO RKS
1
Material
2
P ac ka gi ng /S to ra ge
3
Installation
4
Testing
PO INT OF INSPECTION / TEST
STANDARD/REQUIREMENT
As per submission
JKR/SPJ/2013- S16 Cl.16.8
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Initial Stage
Contractor / SO
Test Report
Initial Stage
Contractor / SO
Method Statement
Initial Stage
Contractor / SO
i. Drawing ii. Method Statement
Initial Stage
Contractor / SO
REMARKS
As per submission
As per submission
JKR/SPJ/2013- S16 Cl.16.8
As per submission
As per submission
JKR/SPJ/2013- S16 Cl.16.8
As per submission
As per submission
JKR/SPJ/2013- S16 Cl.16.8
As per submission
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
Test Report
12
INSPECTION AND TESTING PLAN - VERSION 2
SLOPE STABILIZATION WORKS – GROUND ANCHOR
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
SLOPE STABILIZATION – GROUND ANCHOR I TE M
DE SCR IP TI ON O F WO RK S
1
Material i. Tendons ii. Cement Grout iii. Greases iv. Plastics v. Metal Ducting vi. Rubber Rings
2
H an dl in g A nd St or ag e
3
Installation
4
Anchor Testing
5
Monitoring
P OI NT O F I NS PE CT IO N / T ES T
S TAN DARD /RE QU IR EM ENT
JKR/SPJ/2013-S16 Material approval
Physical Condition
i. End of bore ii. Insertion of tendon iii. Grouting
Cl. 16.6.10.1– 16.6.10.7
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
i. V isual ii. Measurement i ii. Testing
Once per project
JKR Specification
i. V isual ii. Measurement
Initial and Construction Stage
JKR/SPJ/2013-S16 Cl.16.6.18
i. V isual ii. Measurement i ii. Testing
Once per project
i. V isual ii. Measurement i ii. Testing
i. Proving tests ii. On-site suitability tests iii. On-site acceptance tests
JKR/SPJ/2013-S16 Cl. 16.6.21
Monitoring Records submitted within 72 hours of completion of monitoring
JKR/SPJ/2013-S16 Cl. 16.6.22
Visual
RESPONSIBILITY
Contractor / SO
Contractor / SO
EVIDENCE
REMARKS
Results Report
i. Method Statement ii. Certificate of conformance
Contractor / SO
Records
Once per project
Contractor / SO
Test Report
During construction
Contractor / SO
Reports
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 13
INSPECTION AND TESTING PLAN - VERSION 2
SLOPE STABILIZATION WORKS – SOIL NAILING
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
SLOPE STABILIZATION – SOIL NAILING I TE M
D ES CR IPT IO N O F WO RK S
P OI NT O F I NS PEC TI ON / T EST
S TAND AR D/ RE QU IRE ME NT
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
C on tr ac to r / SO
Results Report
REMARKS
Materials 1
2
3
i. Reinforcement ii. Cement Grout iii. Centralizers iv. Corrugated HDPE Sheath
H an dl in g A nd St or ag e
Installation
Material approval
Physical Condition
i. Drilling ii. Inserting reinforcement iii. Grouting iv. Nail Head Construction
JKR/SPJ/2013-S16 Cl. 16.3.3.1 to 16. 3.3.4
i. V isual ii. Meas urement iii. Testing
O nc e p er pr oj ec t
JKR/SPJ/2013-S16 Cl. 16.3.3.5
i. Visual ii. Meas urement
Initial and Construction Stage
JKR/SPJ/2013-S16 Cl. 16.3.4
i. V isual ii. Meas urement iii. Testing
Contractor / SO
Once per project
Contractor / SO
O nc e p er pr oj ec t
C on tr ac to r / SO
i. Method St atement ii. Certificate of conformance
Records
Checking :
4
P ull -Out T es ts
i. Equipment ii. Calibration Certificate iii. Competent Installer iv. Test Results
JKR/SPJ/2013-S16 Cl. 16.3.8
i. Visual ii. Measurement iii. Testing
Test Report
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 14
INSPECTION AND TESTING PLAN - VERSION 2
REINFORCED SOIL SLOPE - GEOCELL
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
REINFORCED SOIL SLOPE - GEOCELL I TE M
DE SCR IP TI ON O F WO RK S
1
Materials
2
P ac ka gi ng /S to ra ge
3
Installation
P OI NT O F I NS PE CT IO N / T ES T
i. Physical condition ii. Technical Properties
Visual
i. Location ii. Size iii. Infill Material
S TAN DARD /RE QU IR EM ENT
i. JKR/SPJ/2013- S16 Cl. 16.2 ii. Refer Table 16.2.1 and 16.2.2
JKR/SPJ/2013- S16 Cl. 16.2.4
JKR/SPJ/2013- S16 Cl. 16.2.5
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
i. V isual ii. Measurement iii. Testing
Visual
i. V isual ii. Measurement
Initial Stage
Initial and Construction Stage
During construction
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
RESPONSIBILITY
Contractor / SO
EVIDENCE
REMARKS
i. Inspection Form ii. Consignment Certificate by Manufacturer iii. Test report iv. Method Statement
Method Statement Contractor / SO
Contractor / SO
i. Mock Up ii. As Built Drawing
15
INSPECTION AND TESTING PLAN - VERSION 2
SURFACE PROTECTION WORKS - GUNITING
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
SURFACE PROTECTION - GUNITING I TE M
D ESC RIP TI ON O F W OR KS
P OI NT O F I NS PE CT IO N / T ES T
i. Physical condition ii. Technical Properties 1
Materials
2
P ac ka gi ng /S to ra ge
3
Installation
Testing
Visual
i. Location ii. Thickness iii. Reinforcement Bar
i. Rebound Hammer ii. Coring Test
ST AN DAR D/ RE QU IR EM EN T
JKR/SPJ/2013- S16 Cl. 16.4.2
JKR/SPJ/2013- S16 Cl. 16.4.2
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
i. Vi sual ii. Measu rement iii. Testing
Visual
JKR/SPJ/2013- S16 Cl.16.4.3,16.4.6,16.4.7, 16.4.8,16.4.9
i. Vi sual ii. Measu rement
JKR/SPJ/2013- S16 Cl. 16.4.4
Rebound Hammer Coring Machine
Initial Stage
Initial and Construction Stage
RESPONSIBILITY
Contractor / SO
EVIDENCE
REMARKS
i. Inspection Form ii. Consignment Certificate by Manufacturer iii. Test report iv. Method Statement
Method Statement Contractor / SO
During construction
Contractor / SO
i. Mock Up ii. As Built Drawing
During construction
Contractor / SO
Test Report
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 16
INSPECTION AND TESTING PLAN - VERSION 2
HORIZONTAL DRAIN WORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
HORIZONTAL DRAIN I TE M
D ES CR IP TI ON O F W OR KS
P OI NT O F I NS PE CT IO N / TE ST
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
i. JKR/SPJ/2013-S16 Cl. 16.1 ii. Construction Drawing
Visual and Measurement
Initial and Construction Stage
Contractor / SO
Drilling Record
Initial and Construction Stage
Contractor / SO
Visual and Measurement
Initial and Construction Stage
Contractor / SO
S TAN DA RD /R EQ UI RE ME NT
1
Material
Physical condition
2
Drilling and Installation
Termination of drilling
i. JKR/SPJ/2013- S16 Cl.16.1 ii. Construction Drawing
3
Concrete Lined Chutes
Water Flow
i. JKR/SPJ/2013-S16 Cl. 16.1 ii. Constru ction Drawing
RESPONSIBILITY
EVIDENCE
REMARKS
Drilling record
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 17
INSPECTION AND TESTING PLAN - VERSION 2
SURFACE PROTECTION - HYDROSEEDING
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
SURFACE PROTECTION - HYDROSEEDING I TEM
1
D ESC RI PT IO N O F W OR KS
Materials
PO IN T O F IN SP EC TI ON / T EST
Visual
S TAND AR D/R EQ UI RE MEN T
JKR/SPJ/2013- S16 Cl. 16.11.2, 16.11.3
JKR/SPJ/2013- S16 Cl. 16.11.4 to 16.11.10 2
Installation
Visual
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
Visual
Visual
Initial Stage
Initial and Construction Stage
RESPONSIBILITY
EVIDENCE
Contractor / SO
Photograph
Contractor / SO
Progress Photograph
REMARKS
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 18
INSPECTION AND TESTING PLAN - VERSION 2
SHALLOW FOUNDATION WORKS
KERJA GEOTEKNIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
TRADE : SHALLOW FOUNDATION I TEM
1
2
Nota : ITP ini
DE SC RI PTI ON O F WO RK S
Excavation
Concreting works
PO IN T O F I NSPE CT IO N / T ES T
S TAN DAR D / R EQ UI REM EN T
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
Verify the founding depth
Refer to construction drawings (design requirement)
Measurement Tape
Every column position
Contractor/ Site Engineer
Verify the soil bearing capacity
Refer to construction drawings (design requirement)
JKR Probe/ Mackintosh Probe or Plate Bearing Test
Every column position (Probe)/ As per specified (PBT)
Contractor/ Site Engineer
Refer to ITP for concrete works
Refer to ITP for concrete works
Refer to ITP for concrete works
Refer to ITP for concrete works
Contractor/ Project Manager
EVIDENCE
REMARKS
N/A
Probe record/ Plate bearing test record
Refer to ITP for concrete works
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 19
INSPECTION AND TESTING PLAN - VERSION 2 SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
PILING WORKS (DRIVEN/ JACKED - IN PILE) HELAIAN 1 DARI 2
KERJA GEOTEKNIK
TRADE : PILING WORKS - PRE CAST (DRIVEN/ JACKED - IN PILE) I TEM
D ESC RI PTI ON O F W ORK S
P OI NT OF IN SP EC TI ON / TE ST
STAGE / FREQUENCY P ri or to pi le installation
RESPONSIBILITY
2
Set criteria (End bearing piles)
Set criteria calculation by contractor
Less than 10 Blows/25mm/ RequiredHiley's formulae pressure (psi) equavalent to 2.5x WL (Driven pile) or equivalent approved by S.O./ Correlation chart (Jacked-in)
Prior to pile installation
Contractor/ Project Manager
3
Piles
Physical condition of piles (Type/ dimension/ shoes/ defects)
Refer to construction drawings & JKR 20800-0183-14 Section C Cl. 2.2.13 & Cl. 2.2.14
Visual inspection
3 specimens for each batch of delivery or every 40 piles whichever is larger.
Contractor/ Project Manager
S tr uc tu ra l c ap ac it y o f p il es
R ef er to co ns tr uc ti on dr aw in gs
Concrete and Production stage in reinforcement testing factory/ Each batch of equipment delivery
Pile materials testing records & certificate of comformance
Pile bending strength Material on site/ If test equipment necessary
Pile bending test report
Handling and storage of piles
JKR 20800-0183-14 Section C Cl. 2.2.15 Visual inspection
Material on site/ If necessary
N umb er of pr el im ina ry pil e
R ef er to co ns tr uc ti on dr awi ng s
Pile deviation
< 75mm
P ri or r o in st all at io n o f preliminary pile Every pile
Verticality of pile
< 1:75
Pile extension Termination of pile
Nota : ITP ini
C on tr ac t d oc ume nt Survey equipments
Survey equipments/ plumb bob JKR 20800-0183-14 Section C Cl. 2.2.16 Visual inspection Set criteria (end bearing pile)/ Visual inspection penetration depth as specified in the drawings (friction pile)
Contractor/ Project Manager
EVIDENCE
Piling equipments (Type/ hammer weight/ pressure requirement)
Installation of piles
Refer to construction drawings & Method statement
TOOLS / EQUIPMENT V is ua l i ns pe ct io n
1
4
Approval of piling equipments
S TAN DAR D / R EQ UI RE MEN T
REMARKS
Equipment specification & calibration records Set calculation
Record and defects marking
Construction progress report Contractor/ Project As built drawing & Manager piling records As built drawing/ Survey record/ pins/ pegs/ markers As built drawing
Every extension of pile
Welding records
Every pile
Pile driving record
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 20
INSPECTION AND TESTING PLAN - VERSION 2 SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
PILING WORKS (DRIVEN/ JACKED - IN PILE) HELAIAN 2 DARI 2
KERJA GEOTEKNIK
TRADE : PILING WORKS - PRE CAST (DRIVEN/ JACKED - IN PILE) I TEM 5
D ESC RI PTI ON O F W ORK S Pile testing (Static load test)
P OI NT OF IN SP EC TI ON / TE ST Test method
Number of test
S uit ab il it y o f a pp ar at us
Testing procedures
Allowable capacity of pile (Acceptance of piles)
Nota : ITP ini
STAGE / FREQUENCY Refer to construction drawings, P ri or to Method Statement commencement of testing Refer to construction drawings Contract document & Prior to Method Statement commencement of testing J KR/ SPJ /2 010 -S 10: Sec ti on 10 .9 .4 D oc ume nt re vi ew P ri or to or commencement of JKR 20800-0183-14 Section C Cl. testing 2.9.4 JKR/SPJ/2010-S10: Section 10.9.5 Document review Every pile test or JKR 20800-0183-14 Section C Cl. 2.9.5 Residual settlement after removal of Load Settlement Every pile test test load < (D/120+4)mm or 6.5mm, Graph whichever the lowest Total settlement under design load < 12.5mm Total settlement under 2xWL < 38mm Or 10% x pile diameter; whichever is the lower value. S TAN DAR D / R EQ UI RE MEN T
TOOLS / EQUIPMENT D oc ume nt re vi ew
RESPONSIBILITY
EVIDENCE
REMARKS
Contractor/ Project Method statement Manager Load test report
Calibration certificate
Method statement
Load test report
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 21
INSPECTION AND TESTING PLAN - VERSION 2 SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
PILING WORKS (CAST IN - SITU BORED PILE/MICROPILE) HELAIAN 1 DARI 2
KERJA GEOTEKNIK
TRADE : PILING WORKS - CAST INSITU (BORED PILE/ MICROPILE) ITEM
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
1
Concrete and reinforcement
Approval of materials
Refer to ITP for concrete works
2
S up po rt f lu id ( Ben to nit e)
C on sis te nc y a nd ba tc hi ng p ro ce ss
3
Boring/ drilling operation
Dimension of drilled hole.
J KR 2 080 0- 01 83 -1 4 S ec tio n C C l. 2.5.2.4 & MS 28 Tolerance of +5% to 0%
Depth of boreholes
TOOLS / EQUIPMENT Refer to ITP for concrete works
STAGE / FREQUENCY Refer to ITP for concrete works
Visual inspection & consistency test
W hen requir ed
RESPONSIBILITY Refer to ITP for concrete works
EVIDENCE
REMARKS
Refer to ITP for concrete works
Contractor / Project Manager
Manufacturer's certificate & mix propotion Contractor/ Project Boring/ drilling record Manager
Measurement tools
Every pile
Refer to construction drawings
Measurement tools
Every pile
Contractor/ Project Manager
Depth of rock socket (if required). (Sokected Length)
Refer to construction drawings
Measurement tools
Every pile
Contractor/ Project Manager
Level of support fluid
> 1m above the external ground water level.
Measurement tools
Every pile
Contractor/ Project Manager
C on tin uit y o f c on st ruc ti on
T im e in te rv al b et we en c omp let io n of Time measurement boring and placing of concrete shall tools be < 6 hours.
Every pile
Contractor/ Project Manager
Enlarged pile bases (if any)
Concentric within 10% of shaft diameter.
Measurement tools
Every pile
Contractor/ Project Manager
P os it ion o f r ei nf or ce me nt
I f t em po ra ry c as in gs a re e mp lo ye d, Measurement tools longitundinal reinforcement shall be > 1.0m below the bottom of the casing.
Every pile
Contractor/ Project Manager
Workability
JKR/SPJ/2010-S10: Table 10.2 or Slump test equipment Refer to ITP for JKR 20800-0183-14 Section C Cl. concrete works 2.5.5.2
Volume of Concrete
Refer to construction drawings
Bleeding test on grout
Max. bleed < 5% (BS EN 4804:2005)
Sloping surface of frustum > 55
Minimum height of base = 150mm
4
Nota : ITP ini
Concreting operations
Measurement tools Bleeding test equipment
Every pile Every batch of grout
Contractor/ Project Manager
Refer to ITP for concrete works
Contractor/ Project bored pile log Manager Contractor/ Project Grouting record Manager
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 22
INSPECTION AND TESTING PLAN - VERSION 2 SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
PILING WORKS (CAST IN - SITU BORED PILE/MICROPILE) HELAIAN 2 DARI 2
KERJA GEOTEKNIK
TRADE : PILING WORKS - CAST INSITU (BORED PILE/ MICROPILE) ITEM 5
DESCRIPTION OF WORKS Pile testing (Static load test)
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
Test method
Refer to construction drawings
Number of test
Refer to construction drawings
Suitability of appar atus
Testing procedures
Allowable bearing capacity of pile
TOOLS / EQUIPMENT Document review
STAGE / FREQUENCY Prior to commencement of testing
Contract document & Prior to Method Statement commencement of testing JKR/SPJ/2010-S10: Section 10.9.4 D oc um en t r ev iew P rio r t o or commencement of JKR 20800-0183-14 Section C Cl. testing 2.9.4 JKR/SPJ/2010-S10: Section 10.9.5 Document r eview Every pile test or JKR 20800-0183-14 Section C Cl. 2.9.5 Residual settlement after removal of Load Settlement Every pile test test load < (D/120+4)mm or 6.5mm, Graph whichever the lowest Total settlement under design load < 12.5mm
RESPONSIBILITY
EVIDENCE
Contractor/ Project Manager
Method statement
Contractor/ Project Manager
Load test report
Contractor/ Project Manager
Calibration certificate
REMARKS
Contractor / Project Method statement Manager
Contractor / Project Manager
Load test report
Total settlement under 2xWL < 38mm Or 10% x pile diameter; whichever is the lower value.
Nota : ITP ini
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 23
24
INSPECTION AND TESTING PLAN - VERSION 2
FLEXIBLE PAVEMENT WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR
HELAIAN 1 DARI 6
TRADE : FLEXIBLE PAVEMENT ITEM
1.
2
DESCRIPTION OF WORKS
A ppr ov al of Su b B as e M at er ial
Sub Base Construction
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
M at er ial Su ita bi li ty : Gradation Limits
JKR/SPJ/2008-S4 - Cl 4.2.2.2 Table 4.2.2
BS1377 : Part 2 : 1990
1. Initial stage 2. One test per 750 cu metre stockpile or laid Initial Stage
Laboratory Compaction : Soaked CBR Test
JKR/SPJ/2008-S4 - Cl 4.2.2.2.i
Mechanical Properties : Plasticity Index, Pi
JKR/SPJ/2008-S4 - Cl 4.2.2.2.ii Not more 12
BS1377 : Part 4 : 1990 (4.5 kg rammer method) BS1377 : Part 2 : 1990
10% Fines Value
Not less than 30 kN
1. Initial Stage 2. One test per 750 cu metre stock pile or MS 30 : Part 9 : 1995 laid
Passing of No. 4 (4.75 mm) sieve
Not less than 45%
ASTM D2419
Thickness
JKR/SPJ/2008-S4 - Cl 4.2.2.3 & Table 4.5.1
D ip pi ng m et ho d
In Situ Compaction Test
JKR/SPJ/2008-S4 - Cl 4.2.2.3 Not less than 95% max dry density
BS1377 : Compaction One test per 500 sq Test metre of each layer laid
Surface Finishes - Shape, Super elevation, Level, Grade
JKR/SPJ/2008-S4 - Cl 4.2.2.3 within tolerance as Table 4.5.1
Relevant construction drawings
O ve r a ny 1 00 m et re length
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
RESPONSIBILITY
Project Manager / Construction Manager / QAQC
EVIDENCE
REMARKS
Form/ Certificate /Catalogue
Contractor/ Inspection Supervision Engineer Form/ Record/ Certificate
25
INSPECTION AND TESTING PLAN - VERSION 2
FLEXIBLE PAVEMENT WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR
HELAIAN 2 DARI 6
TRADE : FLEXIBLE PAVEMENT ITEM
3
4
5
DESCRIPTION OF WORKS
A pp ro va l o f R oa db as e M at er ia l
Roadbase Construction
A pp ro va l o f P ri me C oa t M at er ia l
Prime Coat Construction
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
P hys ic al & M ec ha ni ca l P ro pe rt ie s: -
J KR /S PJ /2 00 8- S4 - C l 4 .2 .3 .2
Plasticity Index
Not more than 6
Agreggate Crushing Value
Not more than 25%
BS 1377 : Part 2 : 1990 MS 30 : Part 8 : 1995
Flakiness Index
Not more than 25%
MS 30 : Part 5 : 1995
Loss of weight in magnesium sulphate soundness tests
Not more than 18%
AASHTO Test Method T 104
Soaked CBR Test
Not less than 80% when compacted to 95% max dry density
Passing of the No. 4 (4.75mm) sieve
Not less than 45%
BS 1377 : Part 4 : 1990 (4.5 kg rammer method) ASTM D 2419
Sieve Analysis
Table 4.2.3
Thickness
JKR/SPJ/2008-S4 - Cl 4.2.3.3 within Dipping tolerance as Table 4.5.1
In-Situ Compaction Test
JKR/SPJ/2008-S4 - Cl 4.2.2.3 Not less than 95% max dry density
BS1377 : Compaction One test per 500 sq Test metre of each layer laid
Surface Finishes - Shape, Super elevation, Level, Grade
JKR/SPJ/2008-S4 - Cl 4.2.3.3 within tolerance as Table 4.5.1
Relevant Construction drawings
M at er ia l S ui ta bi li ty : Cutback Emulsion
JKR/SPJ/2008-S4 - Cl 4.3.1.2 Table 4.3.1 Table 4.3.2
MS 159 MS 161
Spray Test : Tray Test Spraying Temperature
JKR/SPJ/2008-S4 - Cl 4.3.1.4c Between 0.5 to 1.0 litres per sq metre Between 25°C–45°C J KR /S PJ /2 00 8- S4 - C l 4 .3 .1 .4 d Left undisturbed for at least 24 hours
C uri ng & O pe ni ng to Tr af fi c
1. Initial stage 2. One (1) test per 750 cu.m supplied
RESPONSIBILITY
EVIDENCE
Project Manager / Construction Manager / QAQC
nspect on Form/ Certificate /Catalogue
REMARKS
BS 1377 : Part 2 : 1990 Average thickness Contractor/ Inspection over any 100 metre Supervision Engineer Form/ Record/ length not less than Certificate the required thickness
1. Initial Stage 2. Each delivery
One test per16,000 sq.m covered Daily Operation covered
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
Project Manager / Construction Manager / QAQC
Contractor/ QAQC/ Supervision Engineer
nspec on Form/ Certificate /Catalogue /Method of Inspection Form/ Record
26
INSPECTION AND TESTING PLAN - VERSION 2
FLEXIBLE PAVEMENT WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR
HELAIAN 3 DARI 6
TRADE : FLEXIBLE PAVEMENT ITEM
6
7
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
Tack Coat Material
Material Suitability Emulsion
JKR/SPJ/2008-S4 - Cl 4.3.1.2 Table 4.3.2
Tack Coat Construction
Spray Test : Tray Test Spraying Temperature
JKR/SPJ/2008-S4 - Cl 4.3.1.4c Between 0.25 to 0.55 litres per sq metre Between 25°C–45°C
Approval of Binder Course Material (Asphaltic Concrete)
Aggregates Grading
JKR/SPJ/2008-S4 - Cl 4.3.3.2 Table 4.3.3
Coarse Aggregate Properties:Los Angeles Abrasion Value Magnesium sulphate soundness test Flakiness Index Water Absorption
JKR/SPJ/2008-S4 - Cl 4.3.3.2a Not more than 25% Not more than 18%
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
MS161
InitialStage
RESPONSIBILITY
EVIDENCE
REMARKS
Inspection Contractor/ QAQC/ Supervision Engineer Form/ Record
One test per16,000 sq.m covered Daily Operation covered
BS1377 : Washing and Sieving Method
i. Initial stage or any change of aggregates source ii. One (1) test per 1,000 cu.m or at least one (1) test for each plant operation session.
Not more than 25% Not more than 2%
ASTM C 131: 1996 AASHTO Test Method T 104 MS 30 : Part 5 : 1995 MS 30
i. Initial stage ii. One (1) test per 200 tons produced or each plant operation
Fine Aggregates:Passing of the No. 4 (4.75mm) sieve
JKR/SPJ/2008-S4 - Cl 4.3.3.2 Not less than 45%
ASTM D 2419
Fine aggregate angularity Methylene Blue value
Not less than 45% Not more than 10mg/g
ASTM C 1252 Ohio Department of Transportation Standard Test Method
magnesium sulphate soundness test
N ot more than 18%
Water Absorption
Not more than 2%
A ASH TO T est Method T 104 MS 30
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
Project Manager / Construction Manager / QAQC
Inspection Form/ Certificate /Catalogue /Method of Statement
27
INSPECTION AND TESTING PLAN - VERSION 2
FLEXIBLE PAVEMENT WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR
HELAIAN 4 DARI 6
TRADE : FLEXIBLE PAVEMENT ITEM
8
DESCRIPTION OF WORKS
Approval of Mix Design
POINT OF INSPECTION / TEST
Approval of Construction Method
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
Job Mix Formula Marshall Properties : Bulk Specific Gravity, SG Stability, S Flow, F Stiffness, S/F Air Voids in Mix, VIM Voids in aggregate filled with bitumen, VFB
JKR/SPJ/2008-S4 - Cl 4.3.3.3a Table 4.3.5 Not less than 8000N 2.0 – 4.0mm Not less than 2000N/mm 3.0 – 7.0% 65 – 75%
ASTM D 2726 ASTM D 1559 ASTM D 1559
Bitumen Contents Bitumen Extraction
JKR/SPJ/2008-S4 - Cl 4.3.3.3 Table 4.3.4
ASTM D 2172
Plant Trial
JKR/SPJ/2008-S4 - Cl 4.3.3.b Minimum of 20 tonnes JKR/SPJ/2008-S4 - Cl 4.3.3.c Table 4.3.6
Compliance
9
STANDARD/REQUIREMENT
i. Initial stage ii. One (1) test per 200 tonsproducedor at least one (1) test for eachplant operation session.
RESPONSIBILITY
EVIDENCE
Project Manager / Construction Manager / QAQC
nspect on Form/ Certificate
Project Manager / Construction Manager / QAQC
nspec on Form/ Certificate /Catalogue
REMARKS
i. Initial stage ii.One (1) test per 200 tonsproducedor eachplant operation Initial Stage Initial stage
Longitudinal Joints
JKR/SPJ/2008-S4 - Cl 4.3.3.5h Overlap by at least 100mm
Observation
Every completed section or daily operation.
Traverse Joints
Overlap by at least 500mm
Compaction In Situ Density Test
JKR/SPJ/2008-S4 - Cl 4.3.3.5i 95 – 100% Marshall density
ASTM Test Method D One (1) sample per 1188 or ASTM Test 500 sq.m of mix laid, Method D 2726 but not less than two (2) samples for the work completed in each paving session
Thickness
JKR/SPJ/2008-S4 - Cl 4.3.3.5j i. Average thickness over any 100 metrelength ≥ required thickness ii. Minimum thickness at any point ≥ required thickness minus 5mm
Measurement
Surface Finishes - Shape, Super elevation, Level, Grade
JKR/SPJ/2008-S4 - Cl 4.2.3.5j
Relevant Construction drawings
Opening to traffic
JKR/SPJ/2008-S4 - Cl 4.2.3.5k
Observation
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
28
INSPECTION AND TESTING PLAN - VERSION 2
FLEXIBLE PAVEMENT WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR
HELAIAN 5 DARI 6
TRADE : FLEXIBLE PAVEMENT ITEM
10
11
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
Approval of Wearing Course Material Aggregates Grading (Asphaltic Concrete)
Approval of Mix Design
STANDARD/REQUIREMENT
JKR/SPJ/2008-S4 - Cl 4.3.3.2 Table 4.3.3
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
BS1377 : Washing and Sieving Method
i. Initial stage or any change of aggregates source ii. One (1) test per 1,000 cu.m or at least one (1) test for each plant operation session. i. Initial stage ii. One (1) test per 200 tons produced or each plant operation
Coarse Aggregate Properties Los Angeles Abrasion Value Magnesium sulphate soundness test Flakiness Index Water Absorption
JKR/SPJ/2008-S4 - Cl 4.3.3.2a Not more than 25% Not more than 18% Not more than 25% Not more than 2%
ASTM C 131: 1996 AASHTO Test Method T 104 MS 30 : Part 5 : 1995 MS 30
Fine Aggregates Passing of the No. 4 (4.75mm) sieve
JKR/SPJ/2008-S4 - Cl 4.3.3.2 Not less than 45%
ASTM D 2419
Fine aggregate angularity Methylene Blue value
Not less than 45% Not more than 10mg/g
ASTM C 1252 Ohio Department of Transportation Standard Test Method
magnesium sulphate soundness test
N ot more than 18%
Water Absorption
Not more than 2%
A ASH TO T est Method T 104 MS 30
Job Mix Formula Marshall Properties : Bulk Specific Gravity, SG Stability, S Flow, F Stiffness, S/F Air Voids in Mix, VIM Voids in aggregate filled with bitumen, VFB
JKR/SPJ/2008-S4 - Cl 4.3.3.3 Table 4.3.5 Not less than 8000N 2.0 – 4.0mm Not less than 2000N/mm 3.0 – 5.0% 70 – 80%
ASTM D 2726 ASTM D 1559 ASTM D 1559
Bitumen Contents Bitumen Extraction
JKR/SPJ/2008-S4 - Cl 4.3.3.3 Table 4.3.4
ASTM D 2172
i. Initial stage ii. One (1) test per 200 tonsproducedor at least one (1) test for eachplant operation session.
RESPONSIBILITY
EVIDENCE
Project Manager / Construction Manager / QAQC
Inspection Form/ Certificate /Catalogue /Method of Statement
Project Manager / Construction Mana er / QAQC
Inspection Form/ Certificate
REMARKS
i. Initial stage ii.One (1) test per 200 tonsproducedor eachplant operation
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
29
INSPECTION AND TESTING PLAN - VERSION 2
FLEXIBLE PAVEMENT WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR
HELAIAN 6 DARI 6
TRADE : FLEXIBLE PAVEMENT ITEM
12
13
DESCRIPTION OF WORKS
Approval of Construction Method
D et er mi na ti on o f Su rf ac e Re gu la ri ty
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
TOOLS /
STAGE/
EQUIPMENT
FREQUENCY
Longitudinal Joints
JKR/SPJ/2008-S4 - Cl 4.3.3.5h Overlap by at least 100mm
Observation
Traverse Joints
Overlap by at least 500mm
Compaction In Situ Density Test
JKR/SPJ/2008-S4 - Cl 4.3.3.5i 95 – 100% Marshall density
Thickness
JKR/SPJ/2008-S4 - Cl 4.3.3.5j i. Average thickness over any 100 metrelength ≥ required thickness ii. Minimum thickness at any point ≥ required thickness minus 5mm
Measurement
Surface Finishes - Shape, Super elevation, Level, Grade
JKR/SPJ/2008-S4 - Cl 4.3.3.5j
Relevant Construction drawings
Opening to traffic
JKR/SPJ/2008-S4 - Cl 4.3.3.5k
Observation
I nt er na ti on al R ou gh ne ss I nd ex ( IR I)
J KR /S PJ /2 00 8- S4 - C l 4. 5. 3. 2
A RR B Wa lk in g Profiler as outlined in AUSTROAD PAT 01:2001
RESPONSIBILITY
EVIDENCE
REMARKS
Every completed section or daily operation.
ASTM Test Method D One (1) sample per 1188 or ASTM Test 500 sq.m of mix laid, Method D 2726 but not less than two (2) samples for the work completed in each paving session
Project Manager / Construction Manager / QAQC
Before open to traffic
Contractor/ QAQC/ Supervision Engineer
Inspection Form/ Certificate /Catalogue /Method of Statement
Inspection Form/ Record
Less than 2m/km for each 100m
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
30
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 1 - POROUS ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 4
TRADE : SPECIALTY MIX 1 - POROUS ASPHALT I TEM
1
D ES CR IPT IO N O F WO RK S
P OI NT O F I NS PEC TI ON / T EST
Material
S TAND AR D / R EQ UIR EM EN T
STAGE / FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
JKR/SPJ/2008-S4 - Cl. 4.6.2
a. Course Aggregate Course Aggregate Properties : i. Abrasion Loss Los Angeles
ii. Water Absorption
Not more than 2% MS 30
iii. Flakiness Index
Not more than 25% MS 30
iv. Polished Stone Value
Not less than 40 MS 30
v. 5 cycles Magnesium Sulphate Soundness test, wt. loss
Not more than 18% AASHTO T 104
Fine Aggregate Properties : i. Aggregate fraction passing the No.4 Sieve
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Not more than 25% ASTMC 131
b. Fine Aggregate
Nota :
TOOLS / EQUIPMENT
Not less than 45% ASTM D 2419
ii. Aggregate Angularity
Not less than 45% ASTM C 1252
iii . Met hyle ne B lue V al ue
N ot mor e t han 10 mg/ g
iv. 5 cycles Magnesium Sulphate Soundness test, wt. loss
Not more than 20% AASHTO T 104
v. Water Absorption
Not more than 2% MS 30
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 31
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 1 - POROUS ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 4
TRADE : SPECIALTY MIX 1 - POROUS ASPHALT I TEM
1 (cont)
D ES CR IPT IO N O F WO RK S
c. Mineral Filler
P OI NT O F I NS PEC TI ON / T EST
Measurement
S TAND AR D / R EQ UIR EM EN T
i. Passing 75um sieve : Not less than 70% by weight
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
200 litres/test
Project Manager
Inspection Form
REMARKS
ii. Amount : Not less than 2% by weight of combined aggregates. If hydrated lime is used, it shall not exceed 2% by weight of combined aggregates d. Bituminous Binder (PG76)
JKR/SPJ/2008-S4, Cl. 4.6.2.4 Refer to Table 4.6.1 i. Prior to Rolling Thin Film Oven Test
i. Viscosity, max. 3 Pa.s, test temperature C. : 135 ASTM 4402 ii. Dynamic shear, G/sin d min. 1.00 kPa, 10 rad/s, test temperature C : 76 AASHTO T 315 iii. Penetration, 100 g, 5 s, 25 C, 0.1 mm. ASTM D 5 iv. Ring and Ball softening point, min. C : 60 ASTM D 36 o
v. Flash Point, min C : 230 AASHTO T 48 vi. Moisture sensitivity test, greater than (%) : 80 AASHTO T 283 ii. After Rolling Thin Film Oven Test i. Mass loss, max % : 1.00 AASHTO T 240 ii. Dynamic shear, G/sin d min. 2.20 kPa, 10 rad/s, test temperature C : 76 AASHTO T 315 e. T ack Co at Gr ade R S- 3K
Nota :
Sp ra yi ng R at e
Spray at a rate of 0.5 to 1.0 litre/m MS161
2
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 32
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 1 - POROUS ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 4
TRADE : SPECIALTY MIX 1 - POROUS ASPHALT I TEM
2
3
D ES CR IPT IO N O F WO RK S
Mix Design
P OI NT O F I NS PEC TI ON / T EST
Marshall Test :
JKR/SPJ/2008-S4 - Cl. 4.6.4
i. Air Void
Design and in-place air voids shall be between 18 - 25%. ASTM D 1559
ii. B ind er Dr ai n- Down
N ot mor e t han 0. 3% b y w eig ht of th e total mix ASTM D 2041
iii. Cantabro
Average loss in mass shall not be more than 15%
iv. Binder Content
In the range of 4.0-6.0%
v. Grading (sieve analysis)
Design aggregate gradation that comply with Table 4.6.4
Trial Lay - Quantity - Record
Nota :
S TAND AR D / R EQ UIR EM EN T
-Laying and compaction
20 tonnes Record as listed in JKR/SPJ/2008S4 - Cl 4.6.4.6 Refer Construction Works
Marshall Test :
JKR/SPJ/2008-S4 - Cl. 4.6.4.6
i. Air Void
Design and in-place air voids shall be between 18 - 25%
ii. B ind er Dr ai n- Down
N ot mor e t han 0. 3% b y w eig ht of th e total mix.
iii. Cantabro
Average loss in mass shall not be more than 15%
iv. Binder Content
In the range of 4.0-6.0%
v. Grading (sieve analysis)
Design aggregate gradation that comply with Table 4.6.4
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Initial stage
Project Manager
Inspection Form and Record
Visual, testing and measurement
Once per project
Project Manager
Inspection Form/Record
REMARKS
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 33
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 1 - POROUS ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 4 DARI 4
TRADE : SPECIALTY MIX 1 - POROUS ASPHALT I TEM
4
D ES CR IPT IO N O F WO RK S
P OI NT O F I NS PEC TI ON / T EST
Construction Works a. Tack Coat
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
Refer to Table 4.6.2 and Table 4.6.3 Visual, testing and MS 161 measurement
1 test per 200 liter
S TAND AR D / R EQ UIR EM EN T
RESPONSIBILITY
EVIDENCE
REMARKS
JKR/SPJ/2008 - S4 - Cl. 4.6.6 Tray/Sponge
Project Manager
Inspection Form/Record
Project Manager
Inspection Form/Record
1 coring per 500m or min 2
Project Manager
Inspection Form/Record
E ach 1 00 m s ect io n
P ro jec t Manag er
Ins pect ion Form/Record
Prior to opening
Project Manager
Inspection Form/Record
0.5–1.0 liter/sq.m
b. Laying
Min. thickness
JKR/SPJ/2008-S4 - Cl. 4.6.6.2 50mm
Visual, testing and measurement
c. Compaction
i. Rollers used
JKR/SPJ/2008 - S4 - Cl. 4.6.6.3
Visual, testing and measurement
2
Static steel tandem rollers only o
ii. Rolling temperature
Not less than 110 C
iii. Rolling pattern
In accordance to trial lay record
iv . Co mpa ct ion densi ty
N ot le ss than 97% of the la bor at or y mix design density
v. Thickness
Average over any 100m length not less than specified thickness and minimum thic kness at any point shall be not less than the specified thickness minus 5mm. The lane IRI measured for the whole Visual, testing and road length and each 100 m section measurement shall be less than 2.0m/km.
5
Surface regularity
International Roughness Index (IRI)
6
Opening to traffic
Time
JKR/SPJ/2008-S4 - Cl. 4.6.6.8
Visual, testing and measurement
Not less than 4 hours.
Nota :
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 34
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 2 - STONE MASTIC ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 4
TRADE : SPECIALTY MIX 2 - STONE MASTIC ASPHALT ITEM
1
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
Materials a.Coarse Aggregate
JKR/SPJ/2008-S4 - Cl 4.7.2.1 i. Loss by abrasion
Not more than 25% ASTM C 131
ii. Flakiness Index
Not more than 25% MS 30
iii. Polished Stone Value
Not less than 40 MS 30
iv. Magnesium Sulfate Soundness Test (5 cycles)
Not more than 18% AASHTO T 104
v. Water Absorption
Not more than 2% MS 30
b.Fine Aggregate
Nota :
STANDARD / REQUIREMENT
JKR/SPJ/2008-S4 - Cl 4.7.2.2 i. Magnesium Sulfate Soundness Test (5 cycles)
Not more than 20% AASHTO T 104
ii. Water Absorption
Not more than 2% MS 30
iii. Aggregate Fraction
Not less than 45% ASTM D 2419
iv. Aggregate Angularity
Not less than 45% ASTM C 1252
v) Methylene Blue Value
Not more than 10 mg/g Ohio Department of Transportation Standard Test Method
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 35
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 2 - STONE MASTIC ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 4
TRADE : SPECIALTY MIX 2 - STONE MASTIC ASPHALT ITEM
1 (cont)
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
c.Mineral Filler
STANDARD / REQUIREMENT
JKR/SPJ/2008-S4 - Cl 4.7.2.3
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/ source
Project Manager
Inspection Form/Certificate
Grade RS-1K MS161
Visual, testing and measurement
Once per project/ source
Project Manager
Certificate
Gradation of Combined
JKR/SPJ/2008-S4 - Cl 4.7.3
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Aggregate
Refer to Table 4.7.4
i. Passing 75um sieve
Not less than 70% by weight
ii. Amount
Not less than 8% by weight of combined aggregates. If cement is used, it shall not exceed 2% by weight of combined aggregates.
d.Bitumen Binder (PG76)
JKR/SPJ/2008-S4 - Cl 4.7.2.4 i. Properties
Refer to Table 4.7.1
ii. Fuel Resistance Test Immersion in Octane 97 for 24 hours
JKR/SPJ/2008-S4 - Cl 4.7.2.4 (d)
REMARKS
Loss of weight after immersion not more than 4% e.Stabilising agent
JKR/SPJ/2008-S4 - Cl 4.7.2.5 i. Dosage
0.3% by weight of total mix (± 10%)
ii. Properties
Refer to Table 4.7.2 or Table 4.7.3
f. Tack Coat
2
Nota :
Gradation
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 36
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 2 - STONE MASTIC ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 4
TRADE : SPECIALTY MIX 2 - STONE MASTIC ASPHALT ITEM
3
DESCRIPTION OF WORKS
Mix Design
POINT OF INSPECTION / TEST
i. Marshall Properties
STANDARD / REQUIREMENT
JKR/SPJ/2008-S4 - Cl 4.7.4 Refer to Table 4.7.5
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Initial stage
Project Manager
Inspection Form and Record
REMARKS
ASTM D 2726 ASTM D 1559 i. VIM : 3% - 5% ii. VMA : Min 17% iii. Stability : Min 6200 N iv. Flow : 2– 4 mm v. Draindown test : Max 0.30% ii. Trial Lay - Quantity - Record
4
C on st ru ct io n W or ks a. Surface Preparation
-Laying and compaction
20 tonnes Record as listed in JKR/SPJ/2008-S4 - Cl 4.7.4.4 Refer Construction Works
iii. Compliance
Refer to Table 4.7.6
Visual, testing and measurement
Initial stage
Project Manager
Report
Visual
JKR/SPJ/2008-S4 - Cl 4.7.6.1
Visual, testing and measurement
Prior to spraying of the tack coat
Project Manager
Inspection Form/ Record
1 spraying test per 200 liters of asphalt emulsion
Project Manager
Inspection Form/ Record
Project Manager
Inspection Form/ Record
Surface clean from loosematerials
b. Spray Tack Coat
Spray application
JKR/SPJ/2008-S4 - Cl 4.7.6.1 MS 161 0.25 – 0.55 liter/sq.m+ 10% @ 25°C Visual, testing and – 45°C during spray measurement
c. Laying and Compaction
Nota :
Visual, testing and measurement i. Temperature
120°C -150°C during laying & not less than 116°C during rolling
Every load
ii).Grading
JKR/SPJ/2008-S4 - Cl 4.7.3 Refer to Table 4.7.4
1 test per 1000 cu.m or at least 1 test for each plant operation session
iii. Binder contents
± 0.3% at OBC of JMF
1 test per 200 tons or at least 1 test/day
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 37
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 2 - STONE MASTIC ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 4 DARI 4
TRADE : SPECIALTY MIX 2 - STONE MASTIC ASPHALT ITEM
DESCRIPTION OF WORKS
4 (cont)
POINT OF INSPECTION / TEST
iv. Marshall properties
STANDARD / REQUIREMENT
JKR/SPJ/2008-S4 - Cl 4.7.4
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
Visual, testing and measurement
1 test per 200 tons or at least 1 test/day
Visual, testing and measurement
1 coring per 500m
RESPONSIBILITY
EVIDENCE
Project Manager
Inspection Form/ Record
Project Manager
Inspection Form/ Record
REMARKS
Refer to Table 4.7.5 ASTM1559 BS594 i. VIM : 3% - 5% ii. VMA : Min 17% iii. Stability : Min 6200 N iv. Flow : 2– 4 mm v. Draindown test : Max 0.30% v. Compaction
JKR/SPJ/2008-S4 - Cl 4.7.6.5 Minimum 94% Maximum Theoretical density
vi. Layer Thickness
5
6
Surface regularity
Opening to Traffic
2
per lane or min 2 cores, whichever is greater
JKR/SPJ/2008-S4 - Cl 4.7.6.6
Project Manager
Inspection Form/ Record
Average over any 100m length not Visual, testing and less than specified thickness and measurement minimum thickness at any point shall be not less than the specified thickness minus 5mm.
1 coring per 500m2 per lane or min 2 cores, whichever is greater
International Roughness Index
JKR/SPJ/2008-S4 - Cl 4.7.6.6
Visual, testing and measurement
E ac h 1 00 m s ec ti on
P ro je ct Ma na ge r
I ns pe ct io n Form/Record
(IRI)
The lane IRI measured for the whole road length and each 100 meter section shall be less than 2.0m/km
Temperature
JKR/SPJ/2008-S4 - Cl 4.7.6.7
Visual, testing and measurement
Pr ior t o openi ng
P roje ct Man ager
In spec tion F or m
Frequency of coring need to be incorporated in JKR/SPJ/2008-S4 Cl. 4.7.4
Traffic should not be placed on newly compacted surface until the material has cooled to 60°C or lower.
Nota :
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 38
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 3 - GAP GRADED ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 3
TRADE : SPECIALTY MIX 3 - GAP GRADED ASPHALT ITEM
1
DESCRIPTIO N OF WORKS
POINT OF INSPECTION / TEST
Materials a. Coarse Aggregate
STANDARD / REQ UIREMENT
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
JKR/SPJ/2008-S4 - Cl 4.8.2
i. Loss by abrasion
Not more than 25% ASTM C 131
ii. Flakiness Index
Not more than 25% MS 30
iii. Polished Stone Value
Not less than 40 MS 30
iv. Magnesium Sulfate Soundness Test (5 cycles)
Not more than 18% AASHT O T 104
v. Water Absorption
Not more than 2% MS 30
b. Fine Aggregate i. Magnesium Sulfate Soundness Test (5 cycles)
Not more than 20% AASHT O T 104
ii. Water Absorption
Not more than 2% MS 30
iii. Aggregate Fraction Passing 4.75mm sieve
Not less than 45%
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
ASTM D 2419
Nota :
iv. Aggregate Angularity
Not less than 45% ASTM C 1252
v. Methylene Blue Value
Not more than 10 mg/g Ohio Department of Transportation Standard Test Method
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 39
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 3 - GAP GRADED ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 3
TRADE : SPECIALTY MIX 3 - GAP GRADED ASPHALT ITEM
1 (cont)
DESCRIPTIO N OF WORKS
c. Mineral Filler
POINT OF INSPECTION / TEST
Hydrated lime i. Passing 75um sieve
Not less than 70% by weight
ii. Amount
Approximately 2% by weight of combined aggregates.
d. Bituminous Binder (PG76)
e. Gradation
2
JKR/SPJ/2008-S4 - Cl 4.8.2.4
i. Properties
Refer to Table 4.8.1
ii. Fuel Resistance TestImmersion in Octane 97 for 24 hours
JKR/SPJ/2008-S4 - Cl 4.8.2.4 (d) Loss of weight after immersion not more than 4%
Gradation of Combined
JKR/SPJ/2008-S4 - Cl 4.8.3
Aggregate
Refer to Table 4.8.2
Mix Design a. Job Mix Formula
STANDARD / REQ UIREMENT
JKR/SPJ/2008-S4 - Cl 4.8.4.1 i. Design Properties
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Refer toTable 4.8.3
REMARKS
Project Manager Once per project/source
Inspection Form/Certificate
Initial stage
Inspection Form and Record
Initial stage
Report
ASTM D 2726 ASTM D 1559 i. Marshall Stability : > 6200 N ii. MarshallFlow: 2 – 4 mm
iii. Stiffness : > 1550 N/mm iv. Voids in mix : 3 - 5 % v. Voids filled with bitumen : 76-82 % ii. Optimum Binder Content
iii.Trial Lay - Quantity - Record
Nota :
The aggregate gradation selected and the optimum binder content determined shall be proposed to the S.O
-Laying and compaction
20 tonnes Record as listed in JKR/SPJ/2008-S4 -Cl 4.8.4.3 Refer Construction Works
iv. Compliance
Refer to Table 4.8.4
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 40
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 3 - GAP GRADED ASPHALT
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 3
TRADE : SPECIALTY MIX 3 - GAP GRADED ASPHALT ITEM
3
DESCRIPTIO N OF WORKS
POINT OF INSPECTION / TEST
Construction Works
a. Laying and Compaction
STANDARD / REQ UIREMENT
JKR/SPJ/2008-S4 - Cl 4.8.6
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
Visual, testing and measurement
RESPONSIBILITY
EVIDENCE
REMARKS
Project Manager
i. Temperature
Not less than 150°C during laying & not less than 120°C during rolling
Every load
Inspection Form/ Record
ii. Compaction
120°C -150°C during laying & not less than 116°C during rolling
1 coring/500m or min 2 cores per paving session
iii. Density
At least 98% of Marshall density
Inspection Form/ Record
iv. Thickness
Average over any 100m length not less than specified thickness and min thickness at any point shall be not less than the specified thickness minus 5mm
Inspection Form/ Record
2
Inspection Form/ Record
4
Surface regularity
International Roughness Index (IRI)
JKR/SPJ/2008-S4 - Cl 4.8.6.7 The lane IRI measured for the whole road length and each 100 meter section shall be less than 2.0m/km
Visual, testing and measurement
Each 100 m section
Project Manager
Inspection Form/ Record
5
Opening to Traffic
Temperature
JKR/SPJ/2008-S4 - Cl 4.8.6.8
Visual, testing and measurement
Pr ior to openi ng
P roje ct Man ager
In spec tion F or m
Traffic should not be placed on newly compacted surface until the material has cooled to 60°C or lower.
Nota :
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 41
INSPECTION TESTING PLAN - VERSION 2
SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 3
TRADE : SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING IT EM
1
DE SC RI PT IO N O F W ORK S
Materials 1.1 Recycled Asphalt Mixture a.Coarse Aggregate for Fresh Bituminous Mix
P OI NT O F I NSP ECT IO N / TE ST
S TAN DAR D / RE QU IR EM ENT
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
JKR/SPJ/2008-S4 - Cl 4.9.2.1 i. Loss by abrasion
Not more than 25%
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
ASTM C 131
b.Fine Aggregate for Fresh Bituminous Mix
Nota :
i i. Ag gr eg at e C ru sh in g V al ue
N ot mo re th an 25 % BS 812
iii. Flakiness Index
Not more than 25% MS 30
iv. Polished Stone Value
Not less than 40 MS 30
v. Magnesium Sulfate Soundness Test
Not more than 18% AASHTO T 104
vi. Water Absorption
Not more than 2% MS 30
i. Magnesium Sulfate
Not more than 20%
Soundness Test
AASHTO T 104
ii. Water Absorption
Not more than 2% MS 30
iii. Aggregate Fraction
Not less than 45% ASTM D 2419
iv. Aggregate Angularity
Not less than 45% ASTM C 1252
v. Methylene Blue Value
Not more than 10 mg/g Ohio Department of Transportation Standard Test Method
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 42
INSPECTION TESTING PLAN - VERSION 2
SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 3
TRADE : SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING IT EM
1 (cont)
DE SC RI PT IO N O F W ORK S
P OI NT O F I NSP ECT IO N / TE ST
c.Aggregate Properties for Existing Physical Pavement d.Binder
1.2 Marshall Properties for fresh Bituminous Mix
1.3 Rejuvenating Agent
S TAN DAR D / RE QU IR EM ENT
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Not deviate by more than 20% from values specified in Item a and b
Visual, testing and measurement
Once per project
Project Manager
Inspection Form/Certificate
i. Fresh bituminous binder
80 -100 and 50-70 penetration grade bitumen MS 124
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/Certificate
ii. Bitumen recovered from the recycled asphalt after laying.
50 - 70 penetration grade bitumen
Visual, testing and measurement
Once per project
Project Manager
Marshall Properties
JKR/SPJ/2008-S4 - Cl 4.9.2.2
Visual, testing and measurement
Once per project
Project Manager
Inspection Form/Certificate
Grading
To comply with Table 4.9.1
Physical properties
JKR/SPJ/2008-S4 - Cl 4.9.2.3
Visual, testing and measurement
Once per project
Project Manager
Inspection Form/Certificate
REMARKS
The blended binder shall comply to Table 4.9.1
2
Mix Design
Propose mix design
Shall comply with JKR/SPJ/2008-S4 Visual, testing and Cl 4.9.3 measurement
Once per project
Project Manager
Inspection Form/Record
3
Job Mix Formula
i. Trial Lay
JKR/SPJ/2008-S4 - Cl 4.9.4
Once per project
Project Manager
Inspection Form/Record
Visual, testing and measurement
over a section of min 150m length ii. Gradation ii i. Mar shal l P roper tie s
Nota :
Shall comply withTable 4.9.1 S hall comply wi th T ab le 4. 9. 2
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 43
INSPECTION TESTING PLAN - VERSION 2
SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 3
TRADE : SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING IT EM
4
DE SC RI PT IO N O F W ORK S
P OI NT O F I NSP ECT IO N / TE ST
S TAN DAR D / RE QU IR EM ENT
Construction Works
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Visual, testing and measurement
O nce pe r p ro jec t
P rojec t Mana ger
In spec ti on F or m
Visual, testing and measurement
One core per 250 m per lane length or a min of 3 cores
Project Manager
Inspection Form/Record
i) R emi xin g wi th addi tiona l t hic kness Visual, testing and IRI less than 2.0m/km measurement
E ac h 10 0 m se ct io n
P ro je ct M an ag er
I ns pe ct io n Fo rm/ Record
ii) Remixing only IRI less than 2.5m/km
Visual, testing and measurement
E ac h 10 0 m se ct io n
P ro je ct M an ag er
I ns pe ct io n Fo rm/ Record
JKR/SPJ/2008-S4 - Cl 4.9.10
Visual, testing and measurement
Prior to opening
Project Manager
Inspection Form
a.Heating
Temperature
JKR/SPJ/2008-S4 - Cl 4.9.6.3
b.Scarifying
Depth
JKR/SPJ/2008-S4 - Cl 4.9.6.3 Within 20mm of the alignment of the grade and slope of the finished pavement
c.Laying and Compaction
Density
JKR/SPJ/2008-S4 - Cl 4.9.7 Not less than 98%
d.Joints
Heating
JKR/SPJ/2008-S4 - Cl 4.9.8 Heating shall extend at least 100 mm into the adjacent previous mat.
Finished HIPR Surface
i. Thickness
JKR/SPJ/2008-S4 - Cl 4.9.9
REMARKS
120 ≤ °C≤ 180
5
i. Average thickness over 100m length shall be not less than the specified thickness ii. Minimum thickness at any point shall be not less than the specified thickness minus 5mm. ii . Ac cept an ce Cr it er ia
6
Opening to Traffic
Time
Not less than 4 hours after commencement of rolling.
Nota :
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 44
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 3
TRADE : SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING ITEM
1
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
Cold In-Place Recycling Testing of materials to be recycled
ii. Plasticity Index iii. Aggregate Crushing Value iv. Flakiness Index v. CBR
STAGE / FREQUENCY
RESPONSIBILITY
EVIDENCE
i. Refer to Table 4.10.2 JKR/SPJ/2008-S4 ii. Plasticity index < 6 for unbound material iii. ACV < 25% MS 30 iv. Flakiness Index < 25% MS 30 v.CBR > 80% when compacted to 95% of max. dry density -soaked 4 days under surcharge 4.5 kg BS 1377
Visual, testing and measurement
Early stage/Once per project
Lab Assistant/Project Manager/SOR
REMARKS
Certified test result/report
Stabilising agent material a) Cement
Cement use
Ordinary portland cement MS 522
Visual, testing and measurement
Early stage
b) B it umen E mul sio n
P ar amet er s
JK R/ SP J/ 200 8- S4 - C l. 4. 10 .2 .3 ,c Refer to Table 4.10.1
Visual, testing and measurement
Once per project
Lab Assistant/Project Manager/SOR
i. Viscosity, Saybolt Furol at 25° C (sec) ii. Settlement, 5 days (%) iii. Storage stability test, 24hr (%) iv. Sieve test (%) v. Cement mixing test (%) vi. Distillation for oil, by volume of bitumen emulsion (%): v ii . D is ti ll at io n f or re si du e ( %) viii. Penetration for residue (%): ix. Ductility of residue, 25° C, 5cm/min (cm) x. Solubility in trichloroethylene(%) xi. Particle charge test
i. Min 20 sec, Max 100 sec MS 161 ii. Min 0 %, Max 5 % iii. Min 0 %, Max 1 % iv. Min 0 %, Max 0.1 % v. Min 0 %, Max 2 % vi. Min 0 %, Max 5 %
Visual, testing and measurement
Once per project
Lab Assistant/ Project Certified test Manager/ SOR result/report
c) Foamed Bitumen
Nota :
TOOLS / EQUIPMENT
JKR/SPJ/2008-S4 - Cl 4.10.3.2 i. Sieve Analysis
2
STANDARD / REQUIREMENT
SOR
Inspection Form Certified test result/report
v ii . M in 60 % viii . Min 60 %, Max 200 % ix. Min 40 cm x. Min 97.5 % xi. Positive
Properties
JKR/SPJ/2008 - S4 Cl. 4.10.2.3 (d) MS 124
i. Expansion Ratio ii. Half Life
Min 8 times Min 8 seconds
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 45
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 3
TRADE : SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING ITEM
3
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
Mix design a) Cement
STANDARD / REQUIREMENT
JKR/SPJ/2008-S4 - Cl. 4.10.3.3 (b) Refer to Table 4.10.3 i. Unconfined Compression Strength Test (UCS) i i. In di re ct Te ns il e T es t ( IT S) iii. Maximum cement content by weight
b) Bitumen Emulsion or Foamed Bitumen
STAGE / FREQUENCY
RESPONSIBILITY
EVIDENCE
Visual, testing and measurement
Once per project
Lab Assistant/Project Manager/SOR
Certified test result/report
Visual, testing and measurement
Once per project
Lab Assistant/Project Manager/SOR
Certified test result/report
REMARKS
i. Range (Minimum-Maximum Strength) 2 - 5 Mpa BS 1881 i i. Mi n 0 .2 Mp a iii. 5 %
JKR/SPJ/2008-S4 - Cl. 4.10.3.3 (c) Refer to Table 4.10.4/ Table 4.10.5 i. Unconfined Compressive Strength
TOOLS / EQUIPMENT
i. Min Strength 0.7 Mpa BS 1881 ii. Min Strength 0.2 MPa
ii. Indirect Tensile Test (ITS) (Unsoaked) iii. Indirect Tensile Test (ITS) on iii. Min Strength 0.15 Mpa cured briquettes, soaked for 24 hours iv. Sieve test (%) v. Maximum cement content by weight
Nota :
v. 2 %
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 46
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 3
TRADE : SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING ITEM
4
5
DESCRIPTION OF WORKS
Trial Section
POINT OF INSPECTION / TEST
Parameters
JKR/SPJ/2008-S4 - Cl 4.10.3.4
i. Gradation of the recycled material
Refer to Table 4.10.2
ii. Compaction requirements including type of roller and rolling pattern to be employed to achieve the required density; iii. Strength of the recycled layer material in terms of UCS and ITS iv. Recycling depth and compacted thickness of new recycled layer material as specified in detailed pavement design report; v. In-situ moisture content in order to determine the application rate of water to achieve the OMC; vi. Percentage by weight of the stabilising agent used vii. Speed of advance of the recycler machine
Refer to Table 4.10.8 BS 1377
Construction Works i . T ime Limit at ion bet ween mixing and final compaction ii. Compaction -Initial Compaction
Nota :
STANDARD / REQUIREMENT
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
Visual, testing and measurement
Early stage/Once per project (150m)
SOR
Trial result report/record
Visual, testing and measurement
Once per project
SOR
Inspection Fom
REMARKS
Refer to Table 4.10.8 Refer to Table 4.10.8
Refer to Table 4.10.8 BS 1377 Refer to Table 4.10.8 Refer to Table 4.10.8
JKR/SPJ/2008-S4 - Cl 4.10.5 Refer to Table 4.10.8 Re fe r t o T abl e 4. 10. 6
JKR/SPJ/2008-S4 - Cl. 4.10.5.3 (a) Refer to Table 4.10.7
-Trimming and Final Compaction
JKR/SPJ/2008-S4 - Cl. 4.10.5.3 (b)
iii. Joints iv. Quality of Materials and Workmanship
JKR/SPJ/2008-S4 - Cl. 4.10.5.4 JKR/SPJ/2008-S4 - Cl 4.10.5.6 Refer to Table 4.10.8 & Table 4.10.9
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 47
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 4
TRADE : SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE ITEM 1
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
STAGE / FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
JKR/SPJ/2008-S4 - Cl 4.11.2
Materials
Visual, testing and measurement
a. Aggregate i. Los Angeles Abrasion
Not more than 25% ASTM C 131
ii. Flakiness Index
Not more than 25% MS 30
iii. Polished Stone Value
Not less than 40 MS 30
iv. Magnesium Sulfate Soundness Test (5 cycles)
Not more than 18% AASHTO T 104
v. Water Absorption
Not more than 2% MS 30
b. Fine Aggregate i. Magnesium Sulfate Soundness Test (5 cycles)
Not more than 20% AASHTO T 104
ii. Water Absorption
Not more than 2% MS 30
iii. Aggregate Fraction Passing 4.75mm sieve iv, Aggregate Angularity
Not less than 45% ASTM D 2419 Not less than 45% ASTM C 1252
Once per project/source
Project Manager
Inspection Form/ Certificate
Visual, testing and measurement
v. Methylene Blue Value
Nota :
TOOLS / EQUIPMENT
Once per project/source
Project Manager
Inspection Form/ Certificate
Not more than 10 mg/g Ohio Department of Transportation Standard Test Method
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 48
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 4
TRADE : SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE ITEM 1 (cont)
DESCRIPTION OF WORKS c. Mineral Filler
d. Gradation
e. Polymer Modified Binder
POINT OF INSPECTION / TEST Hydrated lime i. Passing 75um sieve
Not less than 70% by weight
ii. Amount
Approximately 2% by weight of combined aggregates.
Gradation of Combined
JKR/SPJ/2008 - S4 - Cl 4.11.2
Aggregate
Shall comply with Table 4.11.1
i. Properties
Refer to Table 4.11.2
(PG 76) or higher
2
Mix Design a. Job Mix Formula
STANDARD / REQUIREMENT
TOOLS / EQUIPMENT Visual, testing and measurement
STAGE / FREQUENCY Once per project/source
RESPONSIBILITY Project Manager
EVIDENCE
REMARKS
Inspection Form/ Certificate
Visual, testing and measurement
Once per project/source
Project Manager
Inspection Form/ Certificate
Visual, testing and measurement
Once per project/source
Project Manager
AASHTO - Std M320-02 MS 124 Sampling - MS 539
Inpection Form/ Certificate
JKR/SPJ/2008-S4 - Cl 4.11.3 Visual, testing and measurement
-Stage 1 i. Gradation
Shall comply with Table 4.11.1
ii . Po lym er Mo di fi ed Bin de r
Sh all co mp ly w it hT ab le 4. 11 .3
iii. Compliance
Shall comply with Table 4.11.4
Once per project/source
Project Manager
Inspection Form/ Certificate
-Stage 2 i. Indirect tension test for resilient modulus; Total resilient modulus Test temperature Applied load Loading frequency Loading time Rest period Rise time Poisson’s ratio
No. of preconditioning pulses No. of test pulses Rotation of specimen
Nota :
ASTM D 4123
> 2500 MPa 25 °C 20 N/mm of specimen thickness (max. 1500 N) 1 Hz 0.1 s 0.9 s 70 ms 0.35 50 5 90°
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 49
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 4
TRADE : SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE ITEM
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
2
ii. Dynamic, unconfined,
(cont)
compressive creep test ;
STANDARD / REQUIREMENT EN 12697-25
TOOLS / EQUIPMENT Visual, testing and measurement
STAGE / FREQUENCY Once per project/source
RESPONSIBILITY Project Manager
EVIDENCE
REMARKS
Inspection Form/ Certificate
Dynamic creep modulus
Dynamic creep modulus > 75 MPa
Slope at steady state
Slope at steady state < 0.25
Specimen end treatment Silicone based lubricant + graphite dust
b. Plant trials
Nota :
Pre-conditioning; Test temperature Applied axial stress Loading frequency Loading time Rest period No. of load cycles
40 °C 150 kPa 0.5 Hz 0.2 s 1.8 s 30
Testing; Test temperature Applied axial stress Loading frequency Loading time Rest period No. of load cycles
Testing; 40 °C 300 kPa 0.5 Hz 0.2 s 1.8 s 3600
- Quantity
20 tonnes
- Record -Laying and compaction
JKR/SPJ/2008-S4 - Cl 4.11.3(b) Refer Construction Works
iii. Compliance
Refer to Table 4.11.5
Visual, testing and measurement
Initial stage
Project Manager
Inspection Form and Record
Visual, testing and measurement
Initial stage
P ro je ct M an ag er
R ep or t
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 50
INSPECTION AND TESTING PLAN - VERSION 2
SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 4 DARI 4
TRADE : SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE ITEM 3
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
Construction Works Laying and Compaction
STANDARD / REQUIREMENT
TOOLS / EQUIPMENT
STAGE / FREQUENCY
JKR/SPJ/2008-S4 - Cl 4.11.5 i. Temperature
Not less than 150°C during
RESPONSIBILITY Project Manager
Visual, testing and measurement
Every load
4
5
Surface regularity
Opening to Traffic
Record
ii. Paving Layer
Compacted Thickness not less than twice aggregate size or not more than 100mm
Visual, testing and measurement
Every layer
iii. Compaction
JKR/SPJ/2008-S4 - Cl 4.11.5
Visual, testing and measurement
1 coring/500m or
iv. Density
Refer to Table 4.11.6
min 2 cores per
ASTM Test Method D2726
paving session
98 - 100% of Marshall density 95 - 100% of Marshall density
v. Thickness
Average over any 100m length not less than specified thickness and Min thickness at any point shall be not less than the specified thickness minus 5mm.
International Roughness Index
JKR/SPJ/2008-S4 - Cl 4.11.5 (j)
(IRI)
The lane IRI measured for the whole road length and each 100 meter section shall be less than 2.0m/km
Time
JKR/SPJ/2008-S4 - Cl 4.11.5 (k)
REMARKS
Inspection Form/
laying
- Wearing course - Binder course
EVIDENCE
Project Manager
Inspection Form/ Record
2
Project Manager Inspection Form/Record
Inspection Form/ Record
Visual, testing and measurement
Each 100 meter section
Project Manager
Inspection Form/Record
Visual, testing and measurement
Prior to opening
Projec t Manage r
In spection Form
Not less than 4 hours after commencement of rolling.
Nota :
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 51
INSPECTION AND TESTING PLAN - VERSION 2
SHOULDERS WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
TRADE : SHOULDERS I TE M
1
DE SCR IP TI ON O F WO RK S
P OI NT O F I NS PE CT IO N / T ES T
S TAND AR D / R EQ UIR EM EN T
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
T yp es o f s ho ul de rs i. Paved Shoulders
Refer to Paved Roads JKR/SPJ/2008-S4 - Cl. 4.2
As per drawing
Visual, testing and measurement
All stages
Visual, testing and measurement
i. Initial Stage ii. One test per 750 cu.m supply
Project Manager
Inspection Record
JKR/SPJ/2008-S4 - Cl. 4.4.2.1 and Cl. 4.4.3 ii. Gravel Shoulders a) Detemining the suitability of materials
JKR/SPJ/2008-S4 - Cl. 4.1.3.2
i. Liquid Limit, LL ii.Plasticity Index, PI iii. Aggregate crushing value iv.Gradation shall conform to one of the envelopes
Contractor's QA/QC / Inspection Record Project Manager
Not more than 35% BS 1377 Shall be in the range 4 to 10 BS 1377 Not more than 35% MS 30 Refer to Table 4.1.3 Fraction passing the BS 75 um sieve not greater than 2/3 of the fraction passing the BS 425 um sieve
v. Passing of No. 4 (4.75 mm) sieve Shall be not less than 45% ASTM D 2419
Nota :
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 52
INSPECTION AND TESTING PLAN - VERSION 2
SHOULDERS WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
TRADE : SHOULDERS I TE M
1 (cont)
DE SCR IP TI ON O F WO RK S
P OI NT O F I NS PE CT IO N / T ES T
b) Construction of gravel surfacing
S TAND AR D / R EQ UIR EM EN T
JKR/SPJ/2008 - S4 - Cl. 4.1.3.3 i. Thickness
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
Visual, testing and measurement
SOR
Within tolerance as Table 4.5.1
Average thickness over any 100 m length not less than the required thickness
ii. In-Situ Compaction Test
Not less than 95% max dry density BS1377 : Compaction Test
One test per 500 sq metre of each layer laid
iii. Surface Finishes - shape, super elevation, level, grade
Refer to relevant construction drawings
Dipping Test
RESPONSIBILITY
EVIDENCE
REMARKS
Inspection Record
Within tolerance as Table 4.5.1 iii. Earth Shoulders a) Detemining the suitability of materials
Refer to Sub-section 2.2.1 (e)
Visual, testing and measurement
b) Earth Shoulder Construction
JKR/SPJ/2008-S4 - Cl 4.4.3
Visual, testing and measurement
i. Thickness
Initial Stage
Project Manager Over 100m length
Inspection Record Refer to Trade Earthwork Item 1
Dipping Test
Nota :
Contractor's QA/QC / Inspection Record Project Manager
ii. In Situ Compaction Test
Not less than 95% max dry density BS1377 : Compaction Test
iii. Surface Finishes - shape, super elevation, level, grade
Refer to relevant construction drawings
One test per 150 sq. m of each layer laid
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan. 53
INSPECTION AND TESTING PLAN - VERSION 2
CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAILWORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
TRADE : ROAD FURNITURE (CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAIL) ITEM
1.
DESCRIPTION OF WORKS
Approval of Guardrail Material
POINT OF INSPECTION / TEST
TOOLS / EQUIPMENT
STANDARD/REQUIREMENT
Beam Element
JKR/SPJ/1988-S6-Cl 6.1.2.1, 3810mm (12 feet 6 inches)
effective
Steel Posts
JKR/SPJ/1988-S6-Cl-6.1.2.2(a) and drawing
STAGE/ FREQUENCY
length AASHTO 1 sample every 200 Specification M180 for Class A Type II(galvanised)
B.S. 449, Grade 43
Part
1
RESPONSIBI LITY
Project Manager / Construction Manager / QAQC
EVI DENCE
REM ARKS
Inspection Form/ Certificate /Catalogue /Method of Statement
1 sample every 200
Block Out(Packer) shall be channel section futher test on the material supplied (if needed ) Timber Posts
Medium harwood
JKR/SPJ/1988-S6-Cl-6.1.2.2(b)
Malaysian Timber 1 sample every 200 Industry Board
Block Out(Packer) - treated timber >16kg/cu.m preservative
M.S 733
futher test on the material supplied(if needed ) M.S 733
Heavy Hardwood
2.
Installation of Guardrail
approval of S.O
Setting Post (Timber/steel)
JKR/SPJ/1988-S6-Cl-6.1.3.1
Placing Beams
Post Holes backfilled- concrete grade 20/20 JKR/SPJ/1988-S6-Cl-6.1.3.2
Anchorages
JKR/SPJ/1988-S6-Cl-6.1.3.3
relevant construction drawing
relevant construction drawing relevant construction drawing
Every completion section
Inspection Contractor/ Form/ Record Supervision Engineer
Every completion section Every completion section
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 54
INSPECTION AND TESTING PLAN - VERSION 2
CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAILWORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
TRADE : ROAD FURNITURE (CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAIL) ITEM
3.
DESCRIPTION OF WORKS
Determination of Marking and Storage
POINT OF INSPECTION / TEST
Marking
Storage
STANDARD/REQUIREMENT
JKR/SPJ/1988-S6-Cl-6.1.4.1
TOOLS / EQUIPMENT
AASHTO Specification M180
JKR logo on each beam element JKR/SPJ/1988-S6-Cl-6.1.4.2 1) stored under a cover Observation 2) > 300mm space between lowest element and ground surface
STAGE/ FREQUENCY
Every completion section
RESPONSIBI LITY
EVI DENCE
REM ARKS
Inspection Contractor/ Form/ Record Supervision Engineer
After each delivery
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 55
INSPECTION AND TESTING PLAN - VERSION 2
CONCRETE KERB WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
TRADE : ROAD FURNITURE (CONCRETE KERB) ITEM 1.
2.
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
Approval of Material
Installation of Kerb
TOOLS / EQUIPMENT
STANDARD/REQUIREMENT
STAGE/ FREQUENCY
Refer to JKR/SPJ/1988-S6 - Cl 6.4.2
Concrete Kerb
Grade 25/20 concrete
Bedding
Grade 10/20 concrete
RESPONSIBILITY
Project Manager / Construction Manager / QAQC
EVIDENCE
REMARKS
Inspection Form/ Certificate /Catalogue /Method of Statement
Relevant Construction Initial Stage Drawing
Excavation Refer to 'JKR/SPJ/1988-S6 - Cl 6.4.3.1
Relevant Construction Every completion drawing section or daily operation
Inspection Contractor/ Form/ Record Supervision Engineer
Relevant Construction Every completion Drawing section or daily operation
Inspection Contractor/ Form/ Record Supervision Engineer
- Required depth and bedding thickness as shown on drawing -Suitable material refer JKR/SPJ/1988 : Section 2 Cast In Situ Kerb
Refer to 'JKR/SPJ/1988-S6 -
Cl 6.4.3.2
-ExpensionJoint performed joint filler 10mm thickness refer JKR/SPJ/1988 : Section 26 -Concreting refer JKR/SPJ/1988 : Section 9 -Formed removed after 24 hours -Minor defect repared with mortar 1:2 -Curing for a period of 7 days
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
56
INSPECTION AND TESTING PLAN - VERSION 2
CONCRETE KERB WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
TRADE : ROAD FURNITURE (CONCRETE KERB) ITEM
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST Precast Concrete Kerb
STANDARD/REQUIREMENT JKR/SPJ/1988 : Section 6 - Cl 6.4.3.3
TOOLS / EQUIPMENT
STAGE/ FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
Relevant Construction Initial Stage & Every Inspection Contractor/ Drawing Completion Section or Form/ Record Supervision Engineer Daily Operation
- Steel mould as shown on drawing - Joints kerb filled with mortar 1:2 - Expansion joints shall be 20mm width
Slipfor ming for Co ncr ete Kerb
Refer to JKR/SPJ/1988 : S6 - Cl 6.4.3.4
Relevant Const ruction Initial Stage & Every Contractor/ Inspection Drawing Complition Section or Supervision Engineer Form/ Record '-Approved automatic Daily Operation kerbing machine
Backfilling
Refer to JKR/SPJ/1988 : S6 - Cl 6.4.3.5
Relevant Construction Every completion Drawing section or daily operation
Inspection Contractor/ Form/ Record Supervision Engineer
-Tamped layer not more than 150mm -Finished level within ± 10mm
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
57
INSPECTION AND TESTING PLAN - VERSION 2
WIRE ROPE SAFETY FENCE WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
TRADE : ROAD FURNITURE (WIRE ROPE SAFETY FENCE) ITEM 1
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
A pp ro va l o f W i re R op e S af et y F en ce Galvanised mild steel posts: Component
STANDARD/REQUIREMENT
TOOLS / EQUIPMENT
STAGE/ FREQUENCY
Project Manager / Construction
REAM -GL 9/2006 -S6-Cl 6.3 a )O IV ( Oc cu pa nt I mp ac t V el oc it y) -1 2m /s ( 4 3. 2 k ph ) m ax
RESPONSIBILITY
N CH RP 3 50 Level 3 (TL-3)
T es t
EVIDENCE
Form/ Certificate
Initial Stage
b)ORA (Occupant Ridedown Accelaration) 20g max Height of post : 690mm to 710mm Shape of post refer to REAM -GL 9/2006 -S6-Cl 6.3(iii) Double Curve - form from 6mm thick mild steel Interwoven wire ropes (Gavanised Pre-tensioned steel)
Anchors
2
Installation
Refer to REAM -GL 9/2006 -S6-Cl 6.3(iv) 19mm diagram 3x 7 contruction breaking load: > 17.7 tonnes unfitted > 16.7 tonnes fitted Minimun modulus of elasticity: 8300kg/mm2 on the area of 283mm2 after pre-stressing Detail end anchor refer to Appendix 6A
Refer to REAM - GL9/2006 : Cl 6.3(i)
W ire Rope
Post
Anchors
upper ropes 600mm±10mm from ground lower interwoven ropes 500mm±10mm from ground Refer to REAM - GL9/2006 : Cl 6.3 (ii) Embedded 400mm into concrete foundation of 950mm Post spacing 2.4 m Minimum post spacing 1m Refer to REAM -GL 9/2006 -S6-Cl 6.3 1) length of wire rope between anchor < 627mm 2) Detail end anchor refer to Appendix 6A
Initial Stage
NCHRP 350 Level 3 (TL-3)
Test
Initial stage
NCHRP 350 Test Level 3 (TL-3)
Initial stage Intial Stage
Measurement
Every complition section or daily operation
Measurement
Initia l stage
NCHRP 350 Test Level 3 (TL-3)
Inspection Contractor/ Form/ Record Supervision Engineer
Initial stage Intial Stage
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 58
REMARKS
INSPECTION AND TESTING PLAN - VERSION 2
ROAD MARKING WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 of 3
TRADE : ROAD FURNITURE (ROAD MARKING) ITEM
1.
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
Approval of Road Marking Material
JKR/SPJ/2012-S6-6.3.2, 6.3.3 Standard Material
Thermoplastic Material : Thermoplastic
Thermoplastic Materia l : Gla ss Bead
Road Marking Paint
2.
Site Preparation
TOOLS / EQUIPMENT
STANDARD/REQUIREMENT
STAGE/ FREQUENCY -
Supplied in block form (broken into pieces, each weighing not more than 4kg) or powder. Hydrocarbon resins shall be used within 6 hours Wood and gum resins shall be used within 4 hours To be in corporated in markin g materials to road surface application.
BS EN 1871, BS EN 1436
Additional surface reflectorisation.
CLASS B Glass beads, Table 2 of B.S 6088 (Table 6.2)
RESPONSIBILITY
EVIDENCE
REMARKS
Project Manager / Construction Manager Inspection Form/ Certificate / QAQC /Catalogue /Method of Statement
CLASS A Glass beads, Table 1 of B.S 6088 (Table 6.1)
Standard Material S ti rr ed b ef or e a pp li ca ti on t o k ee p t he p ig me nt s i n u ni fo rm suspension, Tinners or other additives not be permitted
Clean and dry surface
JKR/SPJ/2012-S6-6.3.4 Not be laid over loose detritus, mud, or extraneous matter or over old material or paint marking incompatible with the paint
Tack coat P ri me r o r u nd er co at
Refer manufacturer's instructions t o a vo id bl ee di ng an d d is co lo ra ti on , to e ns ur e p ro pe r a dh es io n.
-
-
Contractor/ Supervision Engineer
Inspection Form/ Record
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 59
INSPECTION AND TESTING PLAN - VERSION 2
ROAD MARKING WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 of 3
TRADE : ROAD FURNITURE (ROAD MARKING) ITEM 3.
DESCRIPTION OF WORKS Laying Roadmarking
POINT OF INSPECTION / TEST Center, lane & edge lines Other marking
STANDARD/REQUIREMENT JKR/SPJ/2012-S6-6.3.5
Thickness Thickness of Thermoplastic Material : Synthetic Hydrocarbon Resin Binder
JKR/SPJ/2012-S6-6.3.7 Screed lines ; 2 mm < x < 5 mm and Extruded line; 2 mm < x < 5 mm
Thickness of Thermoplastic Material : Gum or wood resin binder
Sprayed lines other than yellow lines ; 45SRT 9
10
Opening of traffic
Removal
Completed road marking
Unwanted road marking
JKR/SPJ/2012-S6-6.3.13 Shall not be opened to traffic until material has fully set.
Usually > 1 hour after material has been laid JKR/SPJ/2012-S6-6.3.14 Removal type:
Inspection Form/ Record
Carried out not more than 7day after laying
Contractor/ Supervision Engineer
Inspection Form/ Record
Contractor/ Inspection Form/ Supervision Engineer/ Record SO/ SOR
a) Burning off is not recomm ended b) Painted over with paint is not allowed c) Blasting, grinding, scraping Satisfaction of the S.O.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 61
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNS WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 5
TRADE : ROAD FURNITURE (TRAFFIC SIGNS) ITEM
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
1.
Perma nent Traf fic Signs - General Luminance Requirements
2.
Permanent Traffic Signs - Materia l
(i)Posts
JKR/SPJ/1988-S6 - Cl 6.2.5.1 Category 1 luminance
TOOLS / EQUIPMENT
STAGE/ FREQUENCY
B.S. 873
Initial Stage
RESPO NSIBILI TY
EVIDENCE
Project Manager / Construction Manager / QAQC
Inspection Form/ Certificate /Catalogue /Method of Statement
Contractor/ Inspection Supervision Engineer Form/ Record/ Certificate
Tubular hollow section steel
(ii)Sign Plates Thickness Size
(iii)Sign Faces
STANDARD/REQUIREMENT
JKR/SPJ/1988-S6 - Cl 6.2.5.3 - Not less than 50mm outside diameter
B.S.1387 and B.S. 873
Initial Stage
JKR/SPJ/1988-S6 - Cl 6.2.5.4
Drawings and B.S. 873
Initial Stage
- Made of 10 S.W.G sheets of alluminium alloy HS 30-WP with min. thickness 3mm - N ot e xceeding 1.2m h eight & 2.4m width shall made from single sheet
B.S 1470
(i) Plastic Sheeting
JKR/SPJ/1988-S6 - Cl 6.2.5.5
BS 873 / MS 1216
Faces
Accordance with the manufacturer's instructions
BS 873 / MS 1216
Initial Stage
Up to 1 m in size and no joint. Joint
Lapping less than 6mm
MS 1216
Construction Stage
Colour uniformity
Refer to addendum no.2 S 2.1.7
MS 1216
Initial Stage
Refer to addendum no.2 S 2.1.13
MS 1216
After installation
JKR/SPJ/1988-S6 - Cl 6.2.5.6 made from aluminium alloy HE9-TE > 600mm , 1000 mm height/width use 40mm X 40mmX3mm angles
B.S 1474 B.S 1474
Initial Stage Initial Stage
(iv)Backing Frames Material Size
B ui lt i n s ec ti on 8 m m d ia me te r b ol t a t n ot m or e t ha n 2 00 m m centres
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
62
REMARKS
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNS WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 5
TRADE : ROAD FURNITURE (TRAFFIC SIGNS) ITEM 3.
DESCRIPTION OF WORKS Fluoresent Orange
POINT OF INSPECTION / TEST (i) Photometric-Coefficient or Retroreflection RA
STANDARD/REQUIREMENT
TOOLS / EQUIPMENT
ASTM E 810 table 1.
STAGE/ FREQUENCY
RESPO NSIBILI TY
EVIDENCE
Initial Stage
Inspection Contractor/ QAQC/ Form/ Record Supervision Engineer
Aluminium Test Panels ii)Daytime colour ASTM 1991
ASTM E 991, ASTM E 308 (for 2° observer) & Table 2
Initial Stage
Inspection Contractor/ QAQC/ Form/ Record Supervision Engineer
i ii ) Ni gt ht im e Co lo r
A ST M E 81 1( ca lc ula te d t he u' ) A ST M E 30 8 ( ca lc ula te d t he v' ) & Table 3
Initial Stage
Inspection Contractor/ QAQC/ Form/ Record Supervision Engineer
iv) Resistance to Accelerated Weathering
ASTM G 26 Type B Method A
Initial Stage
Inspection Contractor/ QAQC/ Form/ Record Supervision Engineer
I ni ti al S ta ge
Inspection Contractor/ QAQC/ Form/ Record Supervision Engineer
Initial Stage
Inspection Contractor/ QAQC/ Form/ Record Supervision Engineer
v ) I mp ac t R es is ta nc e
R ef er S he et in g m an uf ac tu re rs r ec om me nd at io ns
Test Panel of alloy 601-T6 , 0.040" (o.10cm) by 3" (7.6cm) by 5"(12.7cm) and conditioned for 24 hour Shall show no cracking outside the impact area when the face of the panel is subject to an impact of 100 inch-pounds (11.3 Nm) using a weigth with a 5/8 in . (15.8 mm) diameter rounded tip dropped from a height necessary to generate an impact of 100 inch-pounds, at test temperatures of both 32° F (O° C and 72° F (22 ° C) vi) Resistance to Heat
ASTM G 26 Type B Method A
Air circulating oven
. exposed to 170 + 5° F (77 + 3°) for 24 hours minimum 70% of the original coefficient. v ii ) F ie ld P er fo rm an ce
R ef er S he et in g m an uf ac tu re rs re co mm en da ti on s Moving vehicle under Coefficient of retroreflection is less than 100 when measured at normal day and night 0.2° observation and -4° entrance at 90° rotation driving conditions
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
After installation
Contractor/ QAQC/ Inspection Supervision Engineer Form/ Record
63
REMARKS
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNS WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 5
TRADE : ROAD FURNITURE (TRAFFIC SIGNS) ITEM 4.
DESCRIPTION OF WORKS P er ma ne nt Tr af fi c S ig ns Construction and Assembly
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
Traffic signs
JKR/SPJ/1988-S6 - Cl 6.2.5.7 or as shown on drawing
Spacing of rivets
JKR/SPJ/1988-S6 - Cl 6.2.5.7
TOOLS / EQUIPMENT
STAGE/ FREQUENCY
Construction Drawings and B.S. 873
Every completion section
Contractor/ QAQC/ Inspection Supervision Engineer Form/ Record
Every completion section
Contractor/ QAQC/ Inspection Supervision Engineer Form/ Record
O bs er va ti on
E ve ry c om ple ti on section
Contractor/ QAQC/ Inspection Supervision Engineer Form/ Record
ARAHAN TEKNIK (JALAN) 2C/85
Every completion section
Contractor/ QAQC/ Inspection Supervision Engineer Form/ Record
RESPO NSIBILI TY
EVIDENCE
-Not exceed 150mm around the outside edge of any sheet -Not exceed 300mm on cross braces
5.
Permanent Traffic Signs - Location and Erection
Posts
JKR/SPJ/1988-S6 - Cl 6.2.5.8
- Di st an ce f ro m t he c en tr e o f t he p os t t o t he e dg e o f t he s ig n plate 300mm diameter -Erected plumb to check verticality - Grade of 20/20 concrete - Within 450mm of the ground surface
6.
7.
Permanent Traffic Signs - Covering Covering Thickness of permanent traffic signs
T em po ra ry T ra ff ic S ig ns
JKR/SPJ/1988-S6 - Cl 6.2.5.9 - 1.5mm (16 S.W.G) thickness
Cover Plates
JKR/SPJ/1988-S6 - Cl 6.2.5.9 - Stainless steel bolts, washers & nuts use 5mm dia bolts not more than 600mm apart. - Non-ferrous rivet use 12mm dia. bolts not more than 600mm apart - 5 mm t hi ck p la st ic d is ta nc e p ie ce s b et we en t he s ig n f ac e & cover plate.
L oc at io n a nd e re ct io n
J KR /S PJ /1 98 8- S6 - C l 6 .2 .6 - Comply with JKR/SPJ/1988-S6 - Cl 6.2.5.8
Covering
JKR/SPJ/1988-S6 - Cl 6.2.6 - Comply with JKR/SPJ/1988-S6 - Cl 6.2.5.9
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
64
REMARKS
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNS WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 4 DARI 5
TRADE : ROAD FURNITURE (TRAFFIC SIGNS) ITEM 8.
DESCRIPTION OF WORKS Traffic Signs On Gantries
POINT OF INSPECTION / TEST Faces of sign plates
STANDARD/REQUIREMENT
TOOLS / EQUIPMENT
JKR/SPJ/1988-S6 - Cl 6.2.7 B.S. 873
9.
Temporary Signs for the work zone
Steel backing frames,fitting and purlins
JKR/SPJ/1988-S6 - Cl 6.2.7
Steel posts and post housing
JKR/SPJ/1988-S6 - Cl 6.2.7
(i) Photometric -Coefficient or Retroreflection RA
STAGE/ FREQUENCY
RESPO NSIBILI TY
EVIDENCE
Initial / Construction Contractor/ QAQC/ Inspection Stage Supervision Engineer Form/ Record
B.S. 873
B.S. 873
ASTM E 810
Initial Stage
Contractor/ QAQC/ Inspection Supervision Engineer Form/ Record
Test panel complied with Addendum No.3 T able 1 i i)Dayti me color
ASTM E 991, ASTM E 308 (for 2° o bserv er) & T est panel complied with Addendum No.3 Table II
Initial Stage
iii) Nigthtime Color
ASTM E 811(calculated the u') ASTM E 308 (calculated the v') Test panel complied with Addendum No.3 T able III
Initial Stage
iv) Resistance to Accelerated Weathering
ASTM G 26 Type B Method A
Initial Stage
v ) I mp ac t R es is ta nc e
R ef er S he et in g m an uf ac tu re rs re co mm en da ti on s A dd en du m No.3-3.1.1 (v) Test Panel of alloy 601-T6 , 0.040" (0.10cm) by 3" (7.6cm) by 5"(12.7cm) and conditioned for 24 hour
Initial Stage
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
65
REMARKS
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNS WORKS
KERJA JALAN
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 5 DARI 5
TRADE : ROAD FURNITURE (TRAFFIC SIGNS) ITEM
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
vi) Resistance to Heat v ii ) Fi el d P er fo rm an ce
10.
Permanent Traffic Signs Foundations
Type and size of foundations
STANDARD/REQUIREMENT Refer Sheeting manufacturers recommendations Addendum No.3-3.1.1 (vi) . R ef er Sh ee ti ng ma nu fa ct ur er s re co mm en da ti on s A d de nd um No.3-3.1.1 (vi)
TOOLS / EQUIPMENT
STAGE/ FREQUENCY
Air circulating oven
Initial Stage
Moving vehicle under normal day and night driving conditions
After installation
JKR/SPJ/1988-S6 - Cl 6.2.5.2
RESPO NSIBILI TY
EVIDENCE
Initial / Construction Contractor/ QAQC/ Inspection Stage Supervision Engineer Form/ Record
SinglePost - Install edcentrally in 300mm diameter or as shown Relevant Construction drawings on drawing - Grade of 20/20 concrete - Depth Within 450mm of the ground surface - Min. three (3) days after placing concrete - Backfilling at least 48 hours after placing the concrete JKR/SPJ/1988Section 9 - Pockets plan dimensions shall be 100mm lar ger Observ ation
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
66
REMARKS
67
INSPECTION AND TESTING PLAN - VERSION 2
DRAINAGE WORKS
KERJA SIVIL
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 3
TRADE : DRAINAGE WORKS I TE TE M 1
D ES ES CR CRI PT PTI ON ON OF OF WO WOR KS KS D ra ra in in ag ag e a nd nd Cu Cu lv lv er er t Exca Excava vatio tion n
POINT OF INSPECTION / TEST - Chec Check k alig alignm nmen entt (pos (positi ition o n of pegs pegs))
Upon completion of excavation: - Check depth of excavation (150mm less than depth in the drawing)
STANDARD/REQUIREMENT
TOOLS / EQUIPMENT
- Cons Constr truc ucti tion on Draw Drawin ing g and and surv survey ey - Survey record equipment/pegs/ markers/TBM/
- Standa Standard rd Specif Specifica icatio tion n For Buildi Building ng - Survey Works Works 2014 2014 (SSB (SSBW W 2014 2014)) Sect Sectio ion n equipment/pegs/ S : Cl. 2.2.3 markers/TBM/ measurement equipment
1 in every 20m run or change in direction or gradient
- Excavatio Excavation n through rock - backfill rock excavation to required level with concrete or suitable materials
- " Ditto" (C (Cl. 2.2.1)
- Excavation to required level
- Chec Check k align alignme ment nt (pos (positi ition o n of peg pegs) s)
- Cons Constr truc ucti tion on Draw Drawin ing g and and surv survey ey - Survey record equipment/pegs/ markers/TBM/ measurement equipment
- Survey equipment/pegs/ markers/TBM/ measurement equipment
Upon completion of excavation: - Check depth of excavation (600 mm - SS BW BW 2 01 01 4 S ec ec titi on on S : Cl 2 .2 .2 .4 .4 - - Survey above the top of culverts design 2.2.6 equipment/pegs/ levels or to the top of subgrade markers/TBM/ levels, whichever is lower) measurement equipment 2
Backfilling
STAGE/ FREQUENCY
- Ba B ackfilling in 150 mm layers of approved materials on both sides of the drain and compacted with mechanical rammers.
SSBW 2014 Section S : Cl. 2.3
- Survey equipment/pegs/ markers/TBM/ measurement equipment
RESPONSIBILITY
EVIDENCE
Kontraktor/ Perunding/PP/WPP/ PTB
Borang Pemeriksaan Kerja-kerja Saliran ; manufacturer's Certificate
Kontraktor/ Perunding/PP/WPP/ PTB
Borang Pemeriksaan Kerja-kerja Saliran ; manufacturer's Certificate
REMARKS
- Excavation to required level
- Immediately after completion of drain laying or installation of culverts
Nota: ITP Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
68
INSPECTION AND TESTING PLAN - VERSION 2
DRAINAGE WORKS
KERJA SIVIL
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 3
TRADE : DRAINAGE WORKS I TE TE M 3
D ES ES CR CRI PT PTI ON ON OF OF WO WOR KS KS
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
TOOLS / EQUIPMENT
STAGE/ FREQUENCY
( i) i) Ca Ca st st i nn- si si tu tu Co Co nc nc re re te te Dr Dr ai ai n
- C he he ck ck co co nc nc re re te te gr gr ad ad e a nd nd le le ng ng th th of of - SSBW 2014 Section Section S : Cl. 4.4.3 cast in-situ concrete drain
- Visual Visual inspection inspection
(ii) Cascade Drain
- "D "Ditto" (Laid stepping on 150mm mass concrete )
- Rele Relevan vantt - during construction Construction Drawing
( iiii i)i) P re re ca ca st st C on on cr cr et et e Dr Dr ai ai n
C he he ck ck c on on cr cr et et e gr gr ad ad e an an d l en en gt gt h of of - SSBW 2014 2014 Section on S : Cl. 4.4.3 4.4.3 precast drain unit or manufacturer's instruction/brochure (for proprietry product) - Inspect dimension dimension and overall - "D " Ditto" inte inte rit of recast recast drain drain unit. t.
- Visu Visual al inspec inspectio tion n
- Ever Every y deli deliver very y
- Delivery Order
- Every delivery
- SSBW SSBW 2014 2014 Section Section S : Cl. 4.4.3 4.4.3
- Every Every delivery delivery
RESPONSIBILITY Kontraktor/ Perunding/PP/WPP/ PTB
EVIDENCE Borang Pemeriksaan Kerja-kerja Saliran ; manufacturer's Certificate
4
Subs Subsoi oill Drai Drain n
- Chec Check k minimu minimum m grad gradie ient nt and and slop slope. e. - SSBW SSBW 2014 2014 Sect Sectio ion n S : Cl. Cl. 5.0 5.0
- Rele Releva vant nt - during constru construction ction Kontraktor/ Kontraktor/ Perundi Perunding/ ng/ Borang Pemeriksaan Construction Drawing PP/WPP/ PTB Kerja-kerja Saliran ; manufacturer's Certificate
5
Sumps
- Check invert level / sumps depth
- Relevant - during constru construction ction Kontraktor/ Kontraktor/ Perundi Perunding/ ng/ Borang Pemeriksaan Construction Drawing PP/WPP/ PTB Kerja-kerja Saliran ; manufacturer's Certificate
- SSBW 2014 Section S : Cl. 6.0
Nota: ITP Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
REMARKS
69
INSPECTION AND TESTING PLAN - VERSION 2
DRAINAGE WORKS
KERJA SIVIL
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 3
TRADE : DRAINAGE WORKS I TE TE M 6
D ES ES CR CRI PT PTI ON ON OF OF WO WOR KS KS Culverts (i ) Pipe Culverts
(i i) Precast Box Culverts
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
TOOLS / EQUIPMENT
STAGE/ FREQUENCY
On delivery to site, check: - Relevant - Each pipe culvert Construction Drawing - N/A
RESPONSIBILITY
EVIDENCE
REMARKS
Kontraktor/ Perunding/ Borang Pemeriksaan PP/WPP/ PTB Kerja-kerja Saliran ; manufacturer's Certificate
- Class, type, dim en ensi on on of pi pipe
- SSBW 2014 Se Section S : Cl. 7.4 ; Manufacturer's Specification
- Date of manufacture
- MS 881
- Approval / compliance compliance of product product and material
- Te T est Certificate
- Site daily
- Every delivery
- Crac Cracks ks,, chip chips s and and defe defect cts s Laying of pipe culverts: - Refer to SSBW SSBW 2014 Section Section S : Cl.7.4
- SSBW SSBW 2014 2014 Sec Secti tion on S : Cl. Cl. 7.4 7.4
- Visu Visual al insp inspec ectio tion n
- Ever Every y deliv deliver ery y
- "Ditto"
- Survey - Each pipe culvert equipment/pegs/mark ers/TBM/ measurement equipment
- Size, thickness
- Manufacturer's Specif icati on on / broucher
- Delivery order, - Every delivery Construction Drawing
- C ra ra ck ck s, s, c hi hi ps ps a nd nd d ef ef ec ec ts ts
- S SB SB W 2 01 01 4 S ec ec titi on on S : C l. 7 .5 .5
- V is is ua ua l I ns ns pe pe ct ct io io n
- Gap between between laid section section ( 2 Mohms. insulation test voltage.
1. Insulation & Continuity Upon completion of continuity Tester. test. Once for each circuit. 2. Insulation Tester.
Contractor
JKR.PK(O).04-SKE.5A (Borang PemeriksaanUjian-ujian Elektrikal) JKR.C&I (Record of Continuit y and Insulation Resistance Test)
Nota: ITP ini
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
161
INSPECTION AND TESTING PLAN - VERSION 2
WIRING SYSTEM & UNDERGROUND CABLE WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 4 DARI 4
LOW VOLTAGE : WIRING SYSTEM & UNDERGROUND CABLE ITEM
DESCRIPTION OF WORKS
(Con't)
POINT OF INSPECTION / TEST
7. Phase sequence test.
STANDARD / REQUIREMENT
1. Phase sequence terminated correctly.
TOOLS / EQUIPMENT
Phase sequence tester.
STAGE/ FREQUENCY
Upon completion of cable insulation test. Once for each circuit.
RESPONSIBILITY
Contractor
EVIDENCE
REMARKS
JKR.PK(O).04-SKE.5A (Borang PemeriksaanUjian-ujian Elektrikal) Borang Phase Sequence Continuity
4
Underground Cable
1. Submission of material for approval
1. Contract. 2. J-MAL. 3. Specifications (L-S1).
Measuring devices.
2 . M at er ia l o n s it e i ns pe ct io n.
1 . T o c on fo rm as pe r a pp ro ve d m at er ia l.
3. Installation of c ables.
1. Specification (L-S3). 2. Approved method statement.
4. Continuity test.
1. C PC i s c ontinuous a nd reasonable ( R ~ I ns ul at io n length x cable internal resistance) Tester.
M ea su ri ng de vi ce s.
Measuring devices.
&
Before material delivery at site. Once for each material.
U po n d el iv er y a t s it e. On ce for each delivery.
In-progress and upon completion of installation. Once for each zone / section.
C on ti nu it y Upon completion of cable installation. Once for each cable.
Co nt ra ct or
J KR .P K(O ). 04 -5 (Borang Pemeriksaan Mock-up)
Contractor / S.O Rep
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
C on tr ac to r
J KR .P K( O) .0 4- SK E. 4A (Borang Pemeriksaan Pemasangan)
C on tr ac to r
J KR .P K( O) .0 4- SK E. 5A (Borang Pemeriksaan Ujian-ujian Elektrikal) JKR.IR&C (Insulation and Continuity test)
5. Insulation resistance test @ d.c volt age 1. R > 2 Mohms notless thantwice (2x)the nominalvoltage of the circuit concerned.
1. Insulation & Continuity Upon completion of cable Tester. continuity test. Once for each 2. Insulation tester. cable
C on tr ac to r
J KR .P K( O) .0 4- SK E. 5A (Borang PemeriksaanUjian-ujian Elektrikal) JKR.IR&C (Insulation and Continuity test)
6 . P ha se se qu en ce te st .
1 . P ha se se qu en ce te rmi na te d c or re ct ly .
P ha se se qu en ce te st er .
U po n c om pl et io n o f c on ti nu it y test. Once for each circuit.
C on tr ac to r
J KR .P K( O) .0 4- SK E. 5A (Borang PemeriksaanUjian-ujian Elektrikal) Borang Phase Sequence Continuity
Nota: ITP ini
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
162
INSPECTION AND TESTING PLAN - VERSION 2
LIGHTNING PROTECTION SYSTEM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
LOW VOLTAGE : LIGHTNING PROTECTION SYSTEM ITEM
DESCRIPTION OF WORKS
1.
Lightning Protection System
POINT OF INSPECTION / TEST 1. Submission of material approval
TOOLS / EQUIPMENT N /A
STANDARD / REQUIREMENT 1. Contract Document 2. Construction Dwg J-MAL 4. Specification L-S9
STAGE/ FREQUENCY
RESPONSIBILITY
EVIDENCE
Be fo re ma te ri al de liv er y a t s it e / Once for each material
Contractor
JKR.PK(O).04-5 (Borang Pemeriksaan Mockup)
N/A
Upon delivery at site / Once for each delivery
C o nt ra c to r / S. O R e p
J KR .P K( O) .0 4 -S KE .2 A (Borang Pengesahan Penerimaan Bahan)
3.
2. Material on site inspection
As per material approval
3. Inspection on air termination system installation
1. Air terminals or vertical finials of annealed copper tape 25mm x 3mm or other approved material. 2. Fixing bracket intervals < 500mm (metallic / non-metallic roof). 3. Air termination rods min. 300mm (L), 16mm dia. with lock nut.
M ea s ur in g E qu ip me n t
I n- p ro gr e ss a n d up o n completion of installation / Once for each block
C o nt ra c to r / S. O R e p
J KR .P K( O) .0 4 -S KE .4 F (Borang Pemeriksaan Pemasangan Sistem Perlindungan Kilat)
4. Inspection on down conductor system installation
A. Conventional (Exposed) 1. Annealed copper tape 25mm x 3mm or other approved material. 2. Conductive fixtures at interval < 500mm. 3. Bending radii > 200mm and > 45°.
M ea s ur in g E qu ip me n t
I n- p ro g re s s an d u po n completion of installation / Once for each down conductor
Contractor / S.O Rep
JKR.PK(O).04-SKE.4F (Borang Pemeriksaan Pemasangan Sistem Perlindungan Kilat)
M ea s ur in g E qu ip me n t
I n- p ro gr e ss a n d u po n completion of installation / Once for each test joint
C o nt ra c to r / S. O R e p
J KR .P K( O) .0 4 -S KE .4 F (Borang Pemeriksaan Pemasangan Sistem Perlindungan Kilat)
REMARKS
B. Structural Bonding (Encased in Concrete) 1. Annealed copper tape 25mm x 3mm or other approved material. 2. Properly clamped down conductor to structural reinforcing bar at 1m intervals.
C. Structural Using Natural Component (e.g. Steel Structure) 1. Vertical and horizontal bars welded over a length > 30mm. 5. Inspecti on on test join t install ation
Nota: ITP
1. Join ts and bonds by copper clamps or exothermic welding or brazing. 2. Height at 2.5m from finished floor level. 3. Copper clamp overlapping >20mm. 4. PVC casing for exposed down conductor between test joint and ground. 5. Flash counter height at 2.0m from floor finished level.
ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
163
INSPECTION AND TESTING PLAN - VERSION 2
LIGHTNING PROTECTION SYSTEM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
LOW VOLTAGE : LIGHTNING PROTECTION SYSTEM ITEM
DESCRIPTION OF WORKS (Con't)
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
6. Inspection on earth termination and bonding installation
1. Annealed copper tape 25mm x 3mm between earth electrode interconnection, burried > 500mm(D) and distance about 1m around external walls. 2. Exothermic weld or brazing between down conductor and earth electrode. 3. Bonding conductor of annealed copper tape 25mm x 3mm for connection between earth termination and MEB. 4. Copper jacketed earth electrode with 16mm dia. 2 nos. 1.5(L). 5. Heavy duty type earth chamber 300mm (L) x 300mm (W) x 180mm (H) with removable cover (strength >6N/mm2). 6. Permanent label "Lightning Protection EarthDo Not Remove" fixed at every connection of down conductor to earth termination and at every earth electrodes.
7. Continuity test : 1. Air termination system 2. Air termination and down conductor system 3. Down conductor system and earth termination 4. Earth termination 5. Earth termination and Main Earthing Bar (MEB)
1. All conductors are continuiously connected (Resistance < 1 Ω). 2. If natural component being used as down conductor system, ov erall electrical resistance between uppermost part and ground level < 0.2 Ω.
8. Resistance test : 1. Earth electrode 2. Earth termination
Entire systemcombine resistance < 10 Ω.
TOOLS / EQUIPMENT M ea s ur in g E qu ip me n t
STAGE/ FREQUENCY
RESPONSIBILITY
EVIDENCE
I n- p ro g re s s an d u po n completion of installation / Once for each termination and bonding
C o nt ra c to r / S. O R e p
J KR .P K( O) .0 4 -S KE .4 F (Borang Pemeriksaan Pemasangan Sistem Perlindungan Kilat)
Continuity Tester
Upon completion of works / Once for each block
C ontrac tor
J KR .PK( O) .04 -SKE.4F (Borang Pemeriksaan Pemasangan Sistem Perlindungan Kilat)
Earth Tester
Upon completion of install ation / Once for each block
C ontrac tor
J KR .PK( O) .04 -SKE.4F (Borang Pemeriksaan Pemasangan Sistem Perlindungan Kilat)
REMARKS
ITP.01.31.(00).2012 (Borang 'Record of Earth Electrode Resistance Test')
Nota: ITP
ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
164
INSPECTION AND TESTING PLAN - VERSION 2
STANDBY GENERATOR SET WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
LOW VOLTAGE : STANDBY GENERATOR SET ITEM
1.
DESCRIPTION OF WORKS
S ta nd by G en er at or Se t.
POINT OF INSPECTION / TEST
TOOLS / EQUIPMENT
RESPONSIBILITY
EVIDENCE
2. Factory Acceptance Test (Routine Test) :
1. Manufacturers Specification. 2. Design requirement. 3. Specification (L-5S) a) Works test. b) Fulfilling to conditioning of Engine Protective Devices. c) Sudden power increase/decrease. 4. Approved shop drawing for generator set. 5. To confirm as per material approved.
1. Inductive Load-bank at pf 0.8 lagging. 2. Measuring Equipment.
b) Cranking Test
1. Manufactures specification. 2. Specification (L-S5).
6 successive abortiv e start. During testing and commissioning.
3 . M at er ia l o n s it e i ns pe ct io n
T o c om fo rm as pe r a pp ro ve d d ur in g m at er ia l approval and FAT.
N/A
Upon delivery at site. Each delivery.
4. Generator set room requirement.
1. Specification (L-S5).
N/A
By the end of construction or after generator set have been energized.
Contractor
JKR.PK(O).04-SKE.4B (Borang Pemeriksaan Bilik Suis / Mesin Elektrik)
5. Inspection on installation works.
1. Manufacturers specification manual. 2. Approved Shop drawing. 3. Specification (L-S5).
N/A
During installation and completion of installation.Throughout the installation.
Contractor / S.O Rep
JKR.PK(O).04-SKE.5C (Borang Pemeriksaan Ujian Fungsi Pemasangan Elektrik)
6. Fuel system test.
1. Jabatan BOMBA & Penyelamat Malaysia. 2. Jabatan Alam Sekitar (JAS). 3. Specification (L-S5)
Upon completion of installation. During testing and commissioning.
Con tra ctor
SPECIFIC ATION (L-S5: Section 11, Engine Protective devices)
7. Noise level measurement
1. Jabatan Alam Sekitar (JAS). 2. Specification (L-S6) 3. 1 Mohms.
TOOLS / EQUIPMENT
1. Insulation & Continuity Tester. 2. Insulation Tester.
STAGE/ FREQUENCY
Upon completion of continuity test. Once for each circuit.
RESPONSIBILITY
Contractor
EVIDENCE
REMARKS
JKR.PK(O).04-SKE.5A (Borang Pemeriksaan Ujianujian Elektrikal) JKR.C&I (Record of Continuity and Insulation Resistance Test)
2 . I ns ul at io n t es t v ol ta ge .
V ol ts ( d. c) .
1 . In su la ti on & C on ti nu it y Tester. 2. Insulation Tester.
Upon completion of cable insulation test. Once for each circuit.
Contractor
JKR.PK(O).04-SKE.5A (Borang Pemeriksaan Ujianujian Elektrikal) JKR.C&I (Record of Continuity and Insulation Resistance Test)
3 . P ola rit y te st.
O hm < 1 O hm s.
In su la tio n & C on ti nu ity Tester.
Upon completion of wiring work. Once for each circuit.
Contractor
JKR.PK(O).04-SKE.5A (Borang Pemeriksaan Ujianujian Elektrikal) JKR.POL (Record of Polarity Test)
Nota: ITP
ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
166
INSPECTION AND TESTING PLAN - VERSION 2
ROAD LIGHTING SYSTEM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 4
LOW VOLTAGE : ROAD LIGHTING SYSTEM ITEM
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
TOOLS / EQUIPMENT N/A
STANDARD/REQUIREMENT
1.
F ee de r P il la r* * Refer CKE.ITP.01.23. (00).2011
1. A nt i- Va nd alis me Fe at ur es
1 . Co nt rac t Do cume nt 2. J-MAL. 3. Specifications (L-S20, NTJ, Standard Drawing) 4. Shop Drawing
2
Und ergr ound Ca ble
1. S ubm iss io n of m at er ia l f or a ppr ov al
1 . Co nt rac t. 2. JMAL. 3. Specifications (L-S3).
2. Material On Sit e Inspection
To conform as per approved material
3. Installation of cables
1. Specification (L-S3). 2. Approved method statement.
4. Continuity test
CPC is continuous (R= reasonable value )
STAGE/ FREQUENCY During FAT/ Once for each material.
N/A
Before material delivery at site/ Once for each material or delivery Measuring equipment Once for each delivery N/A
During installation/ Once for each zone / section / floor Insulation & Continuity Upon completion of Tester cable installation/ Once for each cable
RESPONSIBILITY
EVIDENCE
Contractor
(Borang Pemeriksaan Ciri-Ciri AntiVandalisma)
Contractor
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up)
Contractor / SO rep
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan) JKR.PK(O).04-SKE.3A (Borang Pemeriksaan Kabel Bawah Tanah) JKR.PK(O).04-SKE.5A (Borang Pemeriksaan Ujian-ujian Elektrikal)
Contractor
Contractor
REMARKS
CKE.ITP.01.32.(00).2012(Record of Insulation Resistance and Continuity Test) 5. Insulation resistance test @ d.c voltage R > 2 MOhms not less than twice (2x) the nominal voltage of the circuit concerned
1. Insulation & Continuity Tester. 2. Insulation tester.
Upon completion of continuity test/ Once for each cable
Contractor
JKR.PK(O).04-SKE.5A (Borang Pemeriksaan Ujian-ujian Elektrikal) CKE.ITP.01.32.(00).2012(Record of Insulation Resistance and Continuity Test)
6. P ha se s eque nc e t es t
Pha se s equenc e t er mina ted c or re ct ly
Pha se s equenc e tester
Upon completion of insulation test/ Once for each circuit
Contractor
JKR.PK(O).04-SKE.5A (Borang Pemeriksaan Ujian-ujian Elektrikal) CKE.ITP.01.32.(00).2012(Record of Insulation Resistance and Continuity Test)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
167
INSPECTION AND TESTING PLAN - VERSION 2
ROAD LIGHTING SYSTEM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 4
LOW VOLTAGE : ROAD LIGHTING SYSTEM ITEM 3
DESCRIPTION OF WORKS Column (c/w concrete footing)
POINT OF INSPECTION / TEST 1. Submission of material for approval
2. Factory Acceptance Test (For NonStandard Column).
4
Ro ad Light ing Lumina ir e
STANDARD/REQUIREMENT
TOOLS / EQUIPMENT N/A
1. Contract Document. 2. JMAL 3. Specifications (L-S20, NTJ, Standard Drawing) 1. Contract Document. Measuring Devices 2. JMAL. (Caliper, Measuring 3. Specifications (L-S20, NTJ, Standard Tape, etc.) Drawing)
3. Material on site inspection
To conform as per approved sample.
N/A
4. Mock-up Inspection.
Specifications (L-S20, NTJ, Standard Drawing)
N/A
5 . I ns pe ct io n o f I ns ta l at io n.
S pe ci fi ca ti on s ( L- S2 0, NT J, St an da rd Drawing)
N/A
1. Subm iss io n of mat er ia l f or appr ov al
1 . Co nt rac t Do cume nt . 2. JMAL. 3. Specifications (L-S20, NTJ,Standard Drawing) To conform as per approved sample.
N/A
3. Mock-up Inspection.
Specifications (L-S20, NTJ, Standard Drawing)
N/A
4 . I ns pe ct io n o f I ns ta l at io n.
S pe ci fi ca ti on s ( L- S2 0, NT J, St an da rd Drawing)
N/A
5. Performance Test (Luminance & Illuminance).
1. Specifications (L-S20, NTJ, Standard 1. Luminance meter Drawing) 2. Illuminance meter. 2. MS 825. 3. CIE 140 4. BS EN 13201-3
2. Material on site inspection
N/A
STAGE/ RESPONSIBILITY FREQUENCY Before material Contractor delivery at site/ Once for each material Approved of Contractor Fabrication / Shop Drawing./ Once for each Sample. Upon delivery at site/ Contractor / SO rep Once for each delivery Prior to Installation./ Once for each type of installation. In progress and upon completion of installation./ Periodically, Once upon completion. Before material delivery at site/ Once for each material Upon delivery at site/ Once for each delivery
EVIDENCE
JKR.PK(O).04-SKE.2B (Borang Pemeriksaan Pemeriksaan / Ujian Alatan Di Kilang)
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
Contractor / SO rep
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up)
Contractor / SO rep
(Borang Pemeriksaan Tia ng Lampu Jalan)
Contractor
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up)
Contractor / SO rep
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
Prior to Installation / Contractor / SO rep Once for each type of installation. In progress and upon Contractor / SO rep completion of installation / Periodically, Once upon completion. Upon completion of Contractor installation (T&C)./ Every 6 mths (During DLP).
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up)
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up) (Borang Pemeriksaan Lampu Jalan)
L-S20
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
168
INSPECTION AND TESTING PLAN - VERSION 2
ROAD LIGHTING SYSTEM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 4
LOW VOLTAGE : ROAD LIGHTING SYSTEM ITEM 5
DESCRIPTION OF WORKS Modular Terminatio n Box. (L-S208.14- Loop-In Loop-Out Terminal Block)
POINT OF INSPECTION / TEST
TOOLS / EQUIPMENT N/A
STANDARD/REQUIREMENT
STAGE/ FREQUENCY Before material delivery at site/ Once for each material
RESPONSIBILITY Contractor
EVIDENCE
1. Submissio n of materia l for approval
1. Contract Document. 2. Drawing 3. Specification (L-S20) 4. NTJ 5. JMAL.
2. Material on site inspection
To conform as per approved sample.
N/A
Upon delivery at site/ Contractor / SO rep Once for each delivery
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
3. Mock-up Inspection.
Specification (L-S20).
N/A
Contractor / SO rep
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up)
4. Inspection of Installation.
Specification (L-S20).
N/A
Prior to Installation./ Once for each type of installation. In progress and upon completion of installation./ Periodically, Once upon completion. Pre-concreting/ Once for each Pre-cabling/Once for each Pre-concreting/ Once for each
Contractor / SO rep
(Borang Pemeriksaan Modular Termination Box)
Contractor / SO rep
(Borang Pemeriksaan Pit /Lurang)
Contractor / SO rep
JKR.PK(O).04-SKE.3A (Borang Pemeriksaan Kabel Bawah Tanah) JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up)
6
Pit / Manhole
1. Inspection of Installation
To conform as per approved drawing & specification.
Measuring Tape
7
Ductin g - Pipe Jackin g/HDD/ Open Cut (road crossing / elevated structure) New Jersey Barrier (NJB) Cover
1 . I ns pe ct io n o f I ns ta l at io n
T o c on fo rm as pe r a pp ro ve d d ra wi ng & specification.
Measuring / Roller Tape.
1. Submission of material for approval
ATJ/NTJ, Drawing
N/A
2. Material on site inspection
To conform as per approved sample.
N/A
3. Mock-up Inspection.
To conform as per approved sample.
N/A
Prior to Installation./ Contractor / SO rep Once for each type of installation.
(Borang Pemeriksaan Pemasangan Lampu Jalan)
4. Inspection of Installation.
To conform as per approved sample.
N/A
In progress and upon Contractor / SO rep completion of installation./ Periodically, Once upon completion.
(Borang Pemeriksaan Pemasangan Lampu Jalan)
8
Before material Contractor delivery at site/ Once for each material Upon delivery at site/ Contractor / SO rep Once for each delivery
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up)
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
169
INSPECTION AND TESTING PLAN - VERSION 2
ROAD LIGHTING SYSTEM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 4 DARI 4
LOW VOLTAGE : ROAD LIGHTING SYSTEM ITEM 9
DESCRIPTION OF WORKS Labelling
POINT OF INSPECTION / TEST
STANDARD/REQUIREMENT
TOOLS / EQUIPMENT N/A
1. Submission of material for approval
1. Contract Document. 2. Specifications (L-S20, NTJ, Standard Drawing)
2. Material on site inspection
To conform as per approved sample.
N/A
3. Inspection of Installation.
To conform as per approved drawing.
N/A
STAGE/ RESPONSIBILITY FREQUENCY Before material Contractor delivery at site/ Once for each material Upon delivery at site/ Contractor / SO rep Once for each delivery In progress and upon Contractor / SO rep completion of installation./ For zone / section.
EVIDENCE
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-Up)
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan) (Borang Pemeriksaan Pemasangan Lampu Jalan)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
170
INSPECTION AND TESTING PLAN - VERSION 2
PA SYSTEM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
EXTRA LOW VOLTAGE : PA SYSTEM ITEM
1.
DESCRIPTION OF WORKS
Public Address System
Nota: ITP ini adalah
POINT OF INSPECTION / TEST
1. Material submission approval
STANDARD / REQUIREMENT
1. Contract Document 2. PA Syste, General Specification 3. Schedule of Technical Data
TOOLS / EQUIPMENT
N/A
STAGE/ FREQUENCY
Before material deliver at project site. Once for each type of material.
RESPONSIBILITY
Contractor
EVIDENCE
2. Inc oming material inspec tion
1. To conform with material s ubmiss ion N/A approval
Upon material delivered at project site. Once for each material delivery
Contractor / SO Rep
3. Conduit ing/Trunking & Cabling work
1. Specificatio n(L-S1) 2. PA System General Specification
In-progress and upon completion of installation. Once for each zone / floor.
C on tr ac to r
J KR .P K( O) .0 4- SKE .4 A (Borang Pengesahan PemeriksaanPemasangan)
4. Continuity test
1. Resistance < 5 Ohms [Given the cable use Insulation & Continuity i s m in . 1 8A WG t wi st ed p ai r s pe ak er c ab le Tester with max. length of 100M]
Upon completion of cabling work. Once for each zone/floor
C on tr ac to r
C KE .I TP .0 6. 01 (0 1) .2 01 1 (Senarai Semak Borang Pemeriksaan Ujian Keterusan Dan Rintangan Penebatan Bagi Sistem Siaraya)
5. Insulation test
1. Resistance > 1M Ohms
Upon completion of cabling work. Once for each zone/floor
C on tr ac to r
C KE .I TP .0 6. 01 (0 1) .2 01 1 (Senarai Semak Borang Pemerik saan Ujia n Kete rusan Dan RintanganPenebatan Bagi Sistem Siaraya)
6. Tapping wattage inspection
1. To confirm that the speaker tapping N/A w at ta ge c on fo rms t o s ho p d ra wi ng a nd schematic
Contractor / SO Rep
CKE.I TP.06.01(02).2011 (Senarai Semak Borang Pemeriksaan Ujian P ema sa ng an S pe ak er d an Tapping Wattage Bagi Sis tem Siaraya)
Measurin g equip ement
Insulation & Continuity Tester.
Upon completion of speaker installation. Randomly chosen speakers installed.[Based in project size and/or as per WPP(E) consent]
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-up)
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
171
INSPECTION AND TESTING PLAN - VERSION 2
PA SYSTEM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
EXTRA LOW VOLTAGE : PA SYSTEM ITEM
DESCRIPTION OF WORKS
(Cont')
Nota: ITP ini adalah
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
7. Speaker installation inspection
1. PA General Specification 2. e-PSMG
8 . Fu nc ti on al te st o f a l eq ui pme nt s
TOOLS / EQUIPMENT
N/A
STAGE/ FREQUENCY
RESPONSIBILITY
EVIDENCE
Upon completion of speaker installation. Randomly chosen speakers installed.[Based on project size and/or as per WPP(E) consent].
Contractor / SO Rep
CKE.I TP.06.01.(02).2011 (Senarai Semak Borang Pemeriksaan Ujian P ema sa ng an S pe ak er d an Tapping Wattage Bagi Sis tem Siaraya)
1 . A ll e qu ip me nt s s h al l o p er at e a s s pe ci fy i n N/A the contract and manufacturer specifications.
Upon completion of PA System Installation. Once for each equipment installed
C on tr ac to r
C KE .I TP .0 6. 01 (0 3) .2 01 1 (Senarai Semak Borang P eme ri ks aa n U ji an F un gs i U nt uk S em ua P er al at an B ag i Sistem Siaraya)
9. Zoning test
1. To confirm that the zoning for each N/A speaker install ed conforms to shop drawin g and schematic
Upon completion of PA System installation. Once for each speakers installed
C on tr ac to r
C KE .I TP .0 6. 01 (0 4) .2 01 1 (Senarai Semak Borang Pe me rik saa n U ji an So und Pressure Level Dan Zone Test Bagi Sistem Siaraya)
10. Sound pressure level test
1. To conform with PA System General Sound Pressure Level Specification Meter
Upon completion of PA System installation. Once for each speaker installed
C on tr ac to r
C KE .I TP .0 6. 01 (0 4) .2 01 1 (Senarai Semak Borang Pemeriksaan Ujian Sound Pressure Level Dan Zone Test Bagi Sistem Siaraya)
REMARKS
untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
172
INSPECTION AND TESTING PLAN - VERSION 2
EXTERNAL INSTALLATION FOR ICT & TELEPHONE WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
EXTERNAL INSTALLATION FOR ICT & TELEPHONE ITEM
1.
DESCRIPTION OF WORKS
External Installation Telephone
for
ICT
POINT OF INSPECTION / TEST
& 1. Submission of Materia l for approval.
STANDARD / REQUIREMENT
1. Contract. 2. Specifications. Catalogue must be submit
TOOLS / EQUIPMENT
N/A
STAGE/ FREQUENCY
Before material delivery at site. Once for each material.
RESPONSIBILITY
Contractor
EVIDENCE
2. Material on site inspection.
1. As per approved material. Free from N/A defect. Evidence/ photos. Catalouge
Upon delivery at site. Once for each delivery.
Contractor / SO Rep
JKR.PK(O).04-SKE.2A (BorangPengesahan Penerimaan Bahan)
3. Inspection of Manhole/ Telephone Pit Installation
1. Contract. 2. LS-3 Specifications.
I n-p rog res s a nd upon completion of installation. Once for each zone / section / floor.
Contractor / SO Rep
JKR.PK(O).04-SKE.3A (BorangPengesahan Pemeriksaan Kabel Bawah Tanah)
Me as ur ing tape .
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-up)
CKE.ITP.03.05.(00).2012 (Senarai Semak Pemeriksaan Pemasangan Manhole & Pit)
4. Inspection of uPVC pipe & G.I pipe Installation
1. Contract. 2. LS-3 Specifications.
N/A
In-progress and upon completion of installation. Once for each zone /routing
Contractor / SO Rep
JKR.PK(O).04-SKE.3A (BorangPengesahan Pemeriksaan Kabel Bawah Tanah) CKE.ITP.03.06.(00).2012 (Senarai Semak Pemeriksaan Pemasangan uPVC Pipe & G.I Pipe)
5. Testing & Commissioning; Clearence of ducting
1. Specification - General Practices for ICT Installation 2. TIA/ EIA standard
N/A
Upon completion of installation.. All pipe
Con trac to r
J KR. PK (O). 04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.07.(00).2012 (Senarai Semak Pengujian & Pentauliahan Kelegaan G.I Pipe & uPVC Pipe)
Nota: ITP ini
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
173
INSPECTION AND TESTING PLAN - VERSION 2
EXTERNAL INSTALLATION FOR ICT & TELEPHONE WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
EXTERNAL INSTALLATION FOR ICT & TELEPHONE ITEM
DESCRIPTION OF WORKS
(Con't)
POINT OF INSPECTION / TEST
6. Inspection of Fiber Optic & Jelly Filled Cable Installation
STANDARD / REQUIREMENT
1. Specification - General Practices for ICT Installation & LS - 16 2. Approved Shop Drawing
TOOLS / EQUIPMENT
N/A
STAGE/ FREQUENCY
In-progress and upon completion of installation. Once for each zone /routing
RESPONSIBILITY
C on tr ac to r
EVIDENCE
REMARKS
J KR .P K( O) .0 4- SK E. 3A (BorangPengesahan Pemeriksaan Kabel Bawah Tanah) CKE.ITP.03.08.(00).2012 (Senarai Semak Pemeriksaan Pemasangan Interbuilding Cabling – Fiber & Jelly Filled)
7. Testing & Commissioning; Fiber Optic cable
1. Specification - General Practices for ICT Installation 2. TIA/ EIA standard
Ca bl e A na lyze r
Upo n c omp let ion of cab lin g work. All cable
Con trac to r
J KR. PK (O). 04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.09.(00).2012 (Senarai Semak Pengujian & Pentauliahan Fibre Optic cable)
8. Testing & Commissioning; Jelly Filled cable
1. LS - 16 Specification
C on ti nu it y T es te r
U po n c omp le ti on of c ab li ng work. All cable
C on tr ac to r
J KR .P K( O) .0 4- SK E. 5A (Borang Pemeriksaan Ujian Elektrikal)
Ujian-
CKE.ITP.03.10.(00).2012 (Senarai Semak Pengujian & Pentauliahan Interbuilding Jelly Filled cable)
Nota: ITP ini
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
174
INSPECTION AND TESTING PLAN - VERSION 2
INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT ITEM
1.
DESCRIPTION OF WORKS
Internal Installation for IC T -Activ e Equipment
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
TOOLS / EQUIPMENT
STAGE/ FREQUENCY
RESPONSIBILITY
EVIDENCE
1 . S ub mi ss io n of ma te ri al fo r ap pr o va l
1 . C o nt ra ct . 2. Specifications. Catalogue must be submit
N/A
Before material delivery at site.Once for each material.
C ontrac to r
2. Material on site inspection.
1. As per approved material.
N/A
Upon material are delivered at project site.Once for each material / delivery.
Contr actor / SO Rep
JKR.P K(O).04-SKE.2 A (Borang Pengesahan Penerimaan Bahan)
3. In spectio n & Testin g of Access Switc h
1. Contract. 2. Specifications.
N/A
Upon completion of installation.Once for each zone / section / floor.
Contr actor / SO Rep
JKR.P K(O).04-9 (Senarai Semak Pengujian & Pentauliahan)
REMARKS
J KR .PK( O) .04 -5 (Borang Pemeriksaan Mock-up)
CKE.ITP.03.11.(00).2012 (Senarai Semak Pemeriksaan, Pengujian & Pentauliahan Access Switch)
4. Inspecti on & Testin g of Distribution Switch
1. Contract. 2. Specifications.
N/A
Upon completion of installation.. All equipment
Contr actor / SO Rep
JKR.P K(O).04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.12.(00).2012 (Senarai Semak Pemeriksaan, Pengujian & Pentauliahan Distribution Switch)
5 . I ns p ec ti on & Te s ti ng o f C o re Sw it ch
1 . C o nt ra ct . 2. Specifications.
N/A
Upon completion of installation.. All equipment
Contr actor / SO Rep
JKR.P K(O).04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.13.(00).2012 (Senarai Semak Pemeriksaan, Pengujian & Pentauliahan Core Switch)
6 . In s pe c ti on & Te s ti ng o f W i re le s s A P
1 . Co n tr a ct . 2. Specifications.
N/A
Upon completion of installation.. All equipment
Contr actor / SO Rep
JKR.P K(O).04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.14.(00).2012 (Senarai Semak Pemeriksaan, Pengujian & Pentauliahan Wireless Access Point)
7. Inspection & Testing of Wireless Controller 1. Contract. 2. Specifications.
N/A
Upon completion of installation.. All equipment
Contr actor / SO Rep
JKR.P K(O).04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.15.(00).2012 (Senarai Semak Pemeriksaan, Pengujian & Pentauliahan Wireless Controller)
Nota:
ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
175
INSPECTION AND TESTING PLAN - VERSION 2
INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT ITEM
DESCRIPTION OF WORKS
(Con't)
POINT OF INSPECTION / TEST
8. Inspection & Testing of UPS
STANDARD / REQUIREMENT
1. Contract. 2. Specifications.
TOOLS / EQUIPMENT
N/A
STAGE/ FREQUENCY
Upon completion of installation.. All equipment
RESPONSIBILITY
Contr actor / SO Rep
EVIDENCE
REMARKS
JKR.P K(O).04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.16.(00).2012 (Senarai Semak Pemeriksaan, Pengujian Dan Pentauliahan Un-Interruptible Power Supply (UPS)
9. Inspection & Testing of Server
1. Contract. 2. Specifications.
N/A
Upon completion of installation.. All equipment
Contr actor / SO Rep
JKR.P K(O).04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.17.(00).2012 (Senarai Semak Pemeriksaan, Pengujian & Pentauliahan Server)
1 0. In sp ec ti on & T es ti ng of Fi re wa l
1 . C on tr ac t. 2. Specifications.
N/A
Upon completion of installation.. All equipment
Contr actor / SO Rep
JKR.P K(O).04-9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.18.(00).2012 (Senarai Semak Pemeriksaan, Pengujian & Pentauliahan Firewall)
Nota:
ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
176
INSPECTION AND TESTING PLAN - VERSION 2
INTERNA L INSTALLATION FOR PASSIVE EQUIPMENT & ICT ROOM WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
INTERNAL INSTALLATION FOR PASSIVE EQUIPMENT & ICT ROOM ITEM
1.
DESCRIPTION OF WORKS
Internal Installation for ICT ; Passiv e Equipment & ICT Room
POINT OF INSPECTION / TEST
1 . S u bm i ss i on o f M at e ri al f or ap p ro v al .
TOOLS /
STANDARD / REQUIREMENT
EQUIPMENT
1 . S p ec i fi c at io n s. Ca ta l og u e m us t b e su b mi t N/A
2. Material on site inspection.
As per approved material. Free from defect. Evidence/ photos. Catalouge
3. Inspection of Trunking, Cable Tray & Conduit ICT
1. LS-1 Specifications.
4. Inspection of Indoor Fib re Optic Cable Installation
1. Specification - General Practices for ICT Installation 2. TIA/ EIA standard
N/A
6. Inspection of Unshielded Twisted Pair (UTP) cable 1 . S p ec if i ca ti o n - G en e ra l P r ac ti c es f o r I CT Installation Installation 2. TIA/ EIA standard
8 . In sp e ct io n o f Eq u ip m en t Ra ck & A c ce s so r ie s
1 . S p ec if i ca ti o n - G en e ra l P r ac ti c es f o r I CT Installation 2. TIA/ EIA standard
1. Specification - General Practices for ICT Installation 2. TIA/ EIA standard
10. Inspection of Server Room
1. Specification - General Practices for ICT Installation 2. TIA/ EIA standard
1 1. I ns pe cti on of D ata Ce nt er
Nota: ITP
1. Specification - General Practices for ICT Installation 2. TIA/ EIA standard 3. Without Marginal Pass
9. Inspection of Telecommunication Closet Room (TCR)
Upon delivery at site. Once for each delivery.
As work progress and upon completion of Measuring Equipment. installation. For each zone/section/floor.
5. Testing & Commissioning; Internal fibre optic cable 1. Specification - General Practices for ICT Installation 2. TIA/ EIA standard
7. Testing & Commissioning; UTP cable
STAGE / FREQUENCY
Before material delivery at site. Once for each material.
1 . S pe ci fi ca ti on - Ge ne ra l P ra ct ic es fo r I CT Installation 2. TIA/ EIA standard - TIA 942
N/A
Cable Analyzer
N/A
Cable Analyzer
In-progress and upon completion of installation. Once for each zone /routing Upon completion of installation. All cable
RESPONSIBILITY
Contractor
EVIDENCE
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-up)
REMARKS
N/A
C o nt ra ct or / S O r e p
J KR .P K (O ). 04 -S K E. 2A N/A (Borang Pengesahan Penerimaan Bahan)
Contractor/ SO rep
CKE.ITP.03.19.(00).2012 (Senarai Semak Pemeriksaan Pemasangan Trunking, Cable Tray & Conduit ICT)
N/A
CKE.ITP.03.20.(00).2012 (Senarai Semak Pemeriksaan Pemasangan Indoor Fibre Optic Cable)
N/A
J KR .P K (O ). 04 -9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.09.(00).2012 (Senarai Semak Pengujian & Pentauliahan Fibre Optic cable)
N/A
Certified Installer Cable/ Contractor/SO rep
C e rt if i ed T es te r/ C on tr a ct or
In-progress and upon completion of installation. Once for each zone /routing
Certified Installer Cable/ Contractor/SO rep
CKE.ITP.03.21.(00).2012 (Senarai Semak Pemeriksaan Pemasangan Unshielded Twisted Pair (UTP) cable)
N/A
Upon completion of cabling work. All cable
Certified Installer Cable/ Contractor/SO rep
JKR.PK(O).04-9 (Senarai Semak Pengujian & Pentauliahan)
N/A
CKE.ITP.03.22.(00).2012 (Senarai Semak Pengujian & Pentauliahan UTP cable) Upon completion of cabling work. All rack
Contractor/ SO rep
Upon completion of work. All TCR.
Contractor/ SO rep
CKE.ITP.03.24.(00).2012 (Senarai Semak Pemeriksaan Telecommunication Closet Room (TCR)
N/A
Upon completion of work.
Contractor/ SO rep
CKE.ITP.03.25.(00).2012 (Senarai Semak Pemeriksaan Server Room)
N/A
Upon completion of work.
Contractor/ SO rep
CKE.ITP.03.26.(00).2012 (Senarai Semak Pemeriksaan Data Center)
N/A
N/A
N/A
N/A
N/A
CKE.ITP.03.23.(00).2012 (Senarai Semak Pemeriksaan Pemasangan Equipment Rack & Accessories)
N/A
ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
177
INSPECTION AND TESTING PLAN - VERSION 2
INTERNAL INSTALLATION FOR TELEPHONE WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
INTERNAL INSTALLATION FOR TELEPHONE ITEM
1.
DESCRIPTION OF WORKS
I nt er na l I ns ta ll at io n f or T el ep ho ne
POINT OF INSPECTION / TEST
1 . S ub mi ss io n o f M at er ia l f or a pp ro va l.
STANDARD / REQUIREMENT
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
1 . S pe ci fi ca ti on s. C at al og ue m us t b e s ub mi t N/A
2. Material on site inspection.
3. Inspection of Trunking, Cable Tray & Conduit Telephone
As per approved material. Free from defect. Evidence/ photos. Catalouge
1. LS-1 Specifications.
Before material delivery at site. Once for each material.
Con tr actor
Contractor/ SO rep
CKE.ITP.03.27.(00).2012 (Senarai Semak Pemeriksaan Pemasangan Trunking, Cable Tray & Conduit Telephone)
In-progress and upon completion of installation. Once for each zone /routing
Contractor/ SO rep
Upon completion of installation.. All cable
Certifie d Tester/ Contractor
5. Testing & Commissioning; Indoor backbone Telephone 1. LS16 Specification For Telephone Installation) Cable and 2 pair/ 0.63mm cable
1 . L S 16 Sp e ci f ic a ti on Fo r T e le p ho n e I ns ta l la t io n ) N/A
8 . Te st in g & Co mm is si on in g; P AB X
1 . LS 16 S pe ci fi ca ti on F or Te le ph on e In st al la ti on )
N/A
9 . T es ti ng & C om mi ss io ni ng ; D ir ec t l in e, F ax L in e & 1. LS16 Specification For Telephone Installation) Extension Line Functionality
In-progress and upon completion of work.
Certified Pabx Installer/ Contractor/SO rep
CKE.ITP.03.31.(00).2012 (Senarai Semak Pemeriksaan Pemasangan (PABX) equipment)
Upon completion of work.
Certified Pabx Installer/ Contractor/SO rep
JKR.PK(O).04-9 (Senarai Semak Pengujian & Pentauliahan)
Nota: ITP
CKE.ITP.03.30.(00).2012 ( Se na ra i S em ak P em er ik sa an PABX & MDF Room)
CKE.ITP.03.32.(00).2012 (Senarai Semak Pengujian & Pentauliahan PABX) Con tractor
N/A
JKR.PK(O).04-9 (Senarai Semak Pengujian & Pentauliahan)
Contractor/ SO rep
Upon completion of work.
N/A
CKE.ITP.03.28.(00).2012 (Senarai Semak Pemeriksaan Pemasangan Indoor backbone Telephone Cable/ 2pair 0.63mm cable/ DP/ MDF)
In-progress and upon completion of work.
N/A
N/A
N/A
CKE.ITP.03.29.(00).2012 (Senarai Semak Pengujian & Pentauliahan Indoor backbone Telephone Cable and 2 pair/ 0.63mm cable)
Cable Analyzer
1. LS16 Specification For Telephone Installation)
N/A
As work progress and upon completion of Measuring Equipment. installation. For each zone/section/floor.
N/A
7. Inspection of Private Automatic Branch Exchange (PABX) equipment
REMARKS
J K R. PK ( O) .0 4 -S K E. 2A (Borang Pengesahan Penerimaan Bahan)
4. Inspection of Indoor backbone Telephone Cable, 2 pair/ 1. LS16 Specification For Telephone Installation) 0.63mm cable, Distribution Point (DP) Box, Sub/ Main Distribution Frame (SDF/ MDF)
6 . I ns p ec ti o n o f S D F, PA B X & MD F R oo m
EVIDENCE
J KR.PK (O).04 -5 (Borang Pemeriksaan Mock-up)
C on tr ac to r / S O re p
N/A
Upon delivery at site. Once for each delivery.
RESPONSIBILITY
S DF ,
N/A
N/A
N/A
N/A
J KR.PK (O).04 -9 (Senarai Semak Pengujian & Pentauliahan) CKE.ITP.03.33.(00).2012 (Senarai Semak Pengujian & Pentauliahan Direct line, Fax Line & Extension Line Functionality)
N/A
ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
178
INSPECTION AND TESTING PLAN - VERSION 2
MEDICAL EQUIPMENT : GENERAL RADIOGRAPHY WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
MEDICAL EQUIPMENT : GENERAL RADIOGRAPHY ITEM
1.
DESCRIPTION OF WORKS
G en er al R ad io gr ap hy S ys te m
POINT OF INSPECTION / TEST
1 . M at er ia l a pp ro va l s ub mi ss io n
STANDARD / REQUIREMENT
1. Contract Document 2. General Radiography Specification 3. Schedule of Technical Data Compliance
TOOLS /
STAGE /
RESPONSIBILITY
EVIDENCE
EQUIPMENT
FREQUENCY
N/A
Before materials deliver at project site Once for each system
Contractor
Contractor/ SO Rep
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-up)
4. Approval Letter by MOH
Nota: ITP ini adalah
2. Material Inspection
1 . To co nf or m w ith ma te ria l s ub mi ss io n ap pr ov al
N/A
U pon eq uip me nt de li ver y at project site Once for each system
JKR.PK(O).04-SKE.2A (Borang PengesahanPenerimaan Bahan)
3. Pre-installation work
1. Specification (LS-1) 2. General Radiography Specification
N/A
Before equipment installation at project site
Contractor
JKR.PK(O).04-SKER.4A (Borang Pengesahan PemeriksaanPemasangan)
4. Functionality Test of the system
1. General Radiography specification 2. Ministry Of Health requirement
N/A
After the complete installation of the equipment
Contractor
JKR.PK(O).04-SKER.4A (Borang Pengesahan PemeriksaanPemasangan)
untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
179
INSPECTION AND TESTING PLAN - VERSION 2
MEDICAL EQUIPMENT : EXAMINATION LIGHT WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
MEDICAL EQUIPMENT : EXAMINATION LIGHT ITEM
1.
Nota:
DESCRIPTION OF WORKS
Examination Light
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
TOOLS /
STAGE /
EQUIPMENT
FREQUENCY
RESPONSIBILITY
EVIDENCE
1. Material approval submission
1. Contract Document 2. Examination Light Specification 3. Schedule of Technical Data Compliance
N/A
Before materials deliver at project site Once for each system
Contractor
2. Material Inspection
1. To conform with material submission approval
N/A
Upon equipment delivery at project site Once for each system
Contractor/ SO Rep
JKR.PK(O).04-SKE.2A (Borang PengesahanPenerimaan Bahan)
3. Pre-installation work
1. Specification (LS-1) 2. Examination Light Specification
N/A
Before equipment installation at project site
Contractor
JKR.PK(O).04-SKER.4A (Borang Pengesahan PemeriksaanPemasangan)
4. Functionality Test of the system
1. Examination Light Specification 2. Ministry Of Health requirement
Lux meter
After the complete installation of the equipment
Contractor
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-up)
JKR.PK(O).04-SKER.4A (Borang Pengesahan PemeriksaanPemasangan)
ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
180
INSPECTION AND TESTING PLAN - VERSION 2
MEDICAL EQUIPMENT : SURGICAL LIGHT WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
MEDICAL EQUIPMENT : SURGICAL LIGHT ITEM
1.
DESCRIPTION OF WORKS
Surgical Light
Nota: ITP ini adalah
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
TOOLS / EQUIPMENT
STAGE / FREQUENCY
RESPONSIBILITY
EVIDENCE
1. Material approval submission
1. Contract Document 2. Surgical Light Specification 3. Schedule of Technical Data Compliance
N/A
Before materials deliver at project site Once for each system
Contractor
2. Material Inspection
1. To conform with material submission approval
N/A
Upon equipment delivery at project site Once for each system
Contractor/ SO Rep
3. Pre-installation work
1. Specification (LS-1) 2. Surgical Light Specification
N/A
Before equipment installation at project site
Contractor
JKR.PK(O).04-SKER.4A (Borang Pengesahan PemeriksaanPemasangan)
4. Functionality Test of the system
1. Surgical Light Specification 2. Ministry Of Health requirement
Lux meter
After the complete installation of the equipment
Contractor
JKR.PK(O).04-SKER.4A (Borang Pengesahan PemeriksaanPemasangan)
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mock-up)
JKR.PK(O).04-SKE.2A (Borang Pengesahan PenerimaanBahan)
untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
181
INSPECTION AND TESTING PLAN - VERSION 2
MEDICAL EQUIPMENT : SURGICAL TABLE WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 1
MEDICAL EQUIPMENT : SURGICAL TABLE I TE M 1.
DE SC RIP TI ON OF W OR KS Surgical Table
POIN T OF INS PE CT ION / TES T 1. Material approval submission
ST AN DARD / REQU IRE ME NT 1. Contract Document
TOOLS / EQUIPMENT
STAGE / FREQUENCY
N/A
Before materials deliver at project site
2. Surgical Table Specificat ion 3. Schedule of Technical Data Compliance
2. Material Inspection
1. To conform with material submission approval
RESPONSIBILITY
EVIDENCE
Contractor
JKR.PK(O).04-5 (Borang Pemeriksaan Mockup)
REMARKS
Once for each system
N/A
Upon equipment delivery at project site
Contractor/ SO Rep
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
JKR.PK(O).04-SKER.4A (Borang Pengesahan Pemeriksaan Pemasangan)
Once for each system 3 . Pr e- inst alla tio n wo rk
1 . Spec if ica tio n (LS -1)
N/A
Before equipment installation at project site
Contractor
Lux meter
After the complete installation of the equipment
Contractor
2. Surgical Table Specification
4. Functionality Test of the system
1. Surgical Table Specification 2. Ministry Of Health requirement
JKR.PK(O).04-SKER.4A (Borang Pengesahan Pemeriksaan Pemasangan)
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
182
INSPECTION AND TESTING PLAN - VERSION 2
HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 4
HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER ITEM
1.
DESCRIPTION OF WORKS
1 1kV Dr y Ty pe Tr ans fo rme r
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
1 . Su bmis si on of ma ter ia l f or ap pr ov al
2. Factory Acceptance Test (FAT) Routine Test
a) Visual Inspection
b) Dimension Check
c)Separate Source AC W ithstand Voltage Test
1 . C ont ra ct Doc ume nt 2. Technical Submittal (i.e. Catalogue, Brand & Model) 3. Specification(L-S17). 4. J-MAL
TOOLS / EQUIPMENT
N/A
-
1. Approved Shop Drawing 2. Technical Submittal (i.e. Catalogue, Brand & Model No.) 3. Specification (L-S17). 4.J-MAL 1. Approved Shop Drawing 2.Technical Submittal (i.e. Catalogue, Brand & Model No.) 3. Specification(L-S17). 4. JMAL 1. Specification (L-S17)-Clause 5.2.5 2. J-MAL.
STAGE / FREQUENCY
RESPONSIBILITY
REMARKS
Con tr ac to r
J KR .PK( O) .04 -5 (Borang Kelulusan Bahan)
Before material delivery at site. Each item.
C on tr ac to r
C KE .P M( P) .0 04 -1 ( Bo ra ng N/A Tindakan Sebelum Ujian PenerimaanBahan/Barangan Di Kilang) N/A JKR.PK(O).04.SKE.2B (Borang Pemeriksaan Alatan di kilang)
During FAT. Each item.
Contractor / SO rep
Measuring Devices During FAT. (Caliper, Measuring Tape, Each item. etc)
Contractor / SO rep
N/A
EVIDENCE
Before Factory Acceptance Test (FAT). Each item.
N/A
N/A JKR.PK(O).04.SKE.2B (Borang Pemeriksaan Alatan di kilang)
AC Withstand Voltage Tester
During FAT. Each item.
MANUFACTURERCompetent Person (Chargeman BO)
CKE.PM(P).004-1 (Factory Acceptance Test Report 11kV Dry- Type Distribution Transformer)
The full test voltage shall be applied for 60s between each winding, and all the remaining windings, core,frame connected to earth,No collapse test voltage shall occur.
d) Induced AC Withsta nd Voltage Test
1. Specific ation (L-S17)-Clause 5.2.6 & Clause 12 of MS IEC60076-3 2. J-MAL.
P ow er An al ys er
D ur in g F AT . Each item.
MANUFACTURERCompetent Person (Chargeman BO)
CKE.PM(P).004-1 (Factory Acceptance Test Report 11kV Dry- Type Distribution Transformer)
The test voltage will increased to twice rated voltage .The test duration not less than 15s. No collapse of the test voltage shall occur
e) Measurement of No Load Loss and Current
1. Specification (L-S17)-Clause 5.2.4 2. J-MAL. 3.No load loss tolerance +15%
P ow er An al ys er
D ur in g F AT . Each item.
MANUFACTURERCompetent Person (Chargeman BO)
CKE.PM(P).004-1 (Factory Acceptance Test Report 11kV Dry- Type Distribution Transformer)
Frequency of the test source should be within 0.5% of the rated frequency. The transformer will be supplied from LV side with rated voltage
f) Measurement of Win ding Resista nce
1. Specific ation (L-S17)-Clause 5.2.1 2. J-MAL.
Transformer Resistance Test Instrument
During FAT. Each item.
MANUFACTURERCompetent Person (Chargeman BO)
CKE.PM(P).004-1 (Factory Acceptance Test Report 11kV Dry- Type Distribution Transformer)
1. The transformer shall be at rest in a constant ambient temperature for at least 3 hours before doing measurement. 2. Readings shall not be taken until current reaches a steady state condition & recommended maximun current value is 15% of In.
3. Winding Resistance and Winding temperature shall be measured at the same time.
Nota: ITP ini adalah
untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
183
INSPECTION AND TESTING PLAN - VERSION 2
HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 4
HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER ITEM
DESCRIPTION OF WORKS
(Con't)
POINT OF INSPECTION / TEST
TOOLS / EQUIPMENT
STAGE / FREQUENCY
RESPONSIBILITY
EVIDENCE
REMARKS
g) Measurement of Load Loss
1. Specification (L-S17). Clause 5.2.3 2. J-MAL. 3. Load loss tolerance +15%
P ow er An al ys er
D ur in g F AT . Each item.
h) Measurement of short circuit impedance
1. Specification (L-S17). Clause 5.2.3 2. J-MAL.
P ow er An al ys er
D ur in g F AT . Each item.
MANUFACTURERCompetent Person (Chargeman BO)
CKE.PM(P).004-1 (Factory Acceptance Test Report 11kV Dry- Type Distribution Transformer)
HV windings are supplied with 3 phase power, LV terminals are short circuits. Duration of the test should be as short as possible to avoid any siginificant heatings of the windings.The measured value of short circuit impedance in ohm per phase shall be corrected to reference temperature of 120 °C
i) Measurement of Voltage Ratio and Phase displacement
1. Specifications (L-S17).-Clause 5.2.2 & Sub Clause 10.3 MS IEC 60076-1 2. J-MAL
Transformer Turns Ratio Testing Instrument Meter
During FAT. Each item.
MANUFACTURERCompetent Person (Chargeman BO)
CKE.PM(P).004-1 (Factory Acceptance Test Report 11kV Dry- Type Distribution Transformer)
1. The deviation of the voltage ratio tolerance shall be ±0.5 % of declared ratio or ± 1/10 of actual % Impedance on the principal tapping, whichever is smaller. 2. The Voltage ratio are equals to 11/
[email protected] 3. Vector Group Check(Dyn11) is correct.
1. Specification (L-S17)-Clause 5.2.7 2. J-MAL. 3.The maximun level of partial discharge shall be 10pC.
Partia l Discharge Tester
During FAT. Each item.
MANUFACTURERCompetent Person (Chargeman BO)
CKE.PM(P).004-1 (Factory Acceptance Test Report 11kV Dry- Type Distribution Transformer)
1. Phase to phase pre stress voltage of 1.8Ur shall be induced for 30 s followed without interruption by phase to phase voltage of 1.3Ur for 3 minute during which the partial discharge shall be measured. 2. Partial discharge measurement shall be carried out after all dielectric tests are completed.For imported transformer supplier has to show the copy of the test report from External Test Lab.
Contractor / SO rep
JKR.PK(O).04-SKE.2A (Borang Pemeriksaan PengesahanPenerimaan Bahan)
(i).The drawing of distance layout between enclosure and transformer for 1000kVA should be endorsed by manufacturer. (ii) De-rating factor if IP 23 or Higher Enclosure is installed.
Contractor
Borang Pemeriksaan Bilik Suis/Transformer. JKR.PK(0).04…
N/A
j) Partial Discharge Measurement
Nota: ITP ini adalah
STANDARD / REQUIREMENT
3. Deli very Materia l On Site In spection.
To conform as per approved material and FAT. (complete with enclosure). Transformer Enclosure-Standard MS IEC60529):-
N/A
Upon delivery at site. For each delivery.
4. Transformer Room Requirement
1.Specification L-S17-Clause 11.0 2. Approved Shop Drawing
N/A
BeforeInstallation.
MANUFACTURERCompetent Person (Chargeman BO)
CKE.PM(P).004-1 (Factory The load loss shall be derived and Acceptance Test Report 11kV corrected to reference temperature of Dry- Type Distribution 120° C Transformer) Note: Total losses(No load & Load loss) tolerance +10%
untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
184
INSPECTION AND TESTING PLAN - VERSION 2
HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 3 DARI 4
HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER ITEM
DESCRIPTION OF WORKS
( Con't)
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
5. Installation of 11kV Dry Type Transfor mer 1. Installation Manual giv en by Manufacturer. 2. Specification (L-S17). 3.Approved method of statement (Site Testing) a) 2000 V d.c Insulatio n Resis tance Test 1. Manufactu rer's Specifi catio ns 2.Specification(L-S17)- Clause 8.2 3. R ≥ 1000 M Ohm(Ω)
b) Measurement Of Windin g Resistance
1. Manufacturer's Specifications 2. Specification (L-S17)-Clause 5.2.1
TOOLS / EQUIPMENT
Visual Inspectio n
STAGE / FREQUENCY
In-progress and upon completion of installation. Each item.
RESPONSIBILITY
EVIDENCE
REMARKS
Contractor
Borang Pemeriksaan Bilik Suis/Transformer. JKR.PK(0).04…
N/A
Insulation Tester(Megger Tester)
During Site Testing & Commissioning. Each item.
Contractor/ Competent Person (Chargeman BO)
JKR.C&I (Record of Continuity and Insulation Resistance Test)
N/A
Transformer Resistance Test Instrument
During Site Testing & Commissioning. Each item.
Contractor/ Competent Person (Chargeman BO)
Manufacturer/Supplier Test Sheet
1. The transformer shall be at rest in a constant ambient temperature for at least 3 hours before doing measurement. 2. Readings shall not be taken until current reaches a steady state condition & recommended maximun current value is 15% of In. 3. Winding Resistance and Winding Temperature shall be measured at the same time.
c) 24 kV a.c pressure test for 1.0 min ute
Nota: ITP ini adalah
1. Manufacturer's Specifications 2 . S pe ci fi ca ti on (L -S 17 )- Cl au se 8. 2
During Site Testing & H i - Po t P re ss ur e T es te r Commissioning. Each item.
Contractor/ Competent Person (Chargeman BO)
Manufacturer/Supplier Test Sheet
N/A
Manufacturer/Supplier Test Sheet
N/A
d) Testing and setting of safety devices and 1. Manufacturer's Specifications measuring gauges. 2. Specification (L-S17)- Clause 8.2
Measuring devices
Upon completio n of Testin g and setting of safety devices and measuring gauges. Each item.
Contractor/ Competent Person (Chargeman BO)
e) Any other tests as recommended by the manufacturer and the supplier
1. Manufacturer's Specifications 2. Specification (L-S17)- Clause 8.2
Measurin g devices
During Site Testing & Commissioning. Each item.
Contractor/ Competent Person (Chargeman BO)
Manufacturer/Supplier Test Sheet
N/A
f) Measurement of voltage ratio
1.Specifications (L-S17).-Clause 5.2.2 & Sub Clause 10.3 MS IEC 60076-1
Transformer Turns Ratio Testing Intrument Meter
During Site Testing & Commissioning. Each item.
Contractor/ Competent Person (Chargeman BO)
Manufacturer/Supplier Test Sheet
1. The deviation of the voltage ratio tolerance shall be ±0.5 % of declared ratio or ± 1/10 of actual % Impedance on the principal tapping, whichever is smaller. 2. The Voltage ratio are equals to 11/
[email protected]
untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
185
INSPECTION AND TESTING PLAN - VERSION 2
HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 4 DARI 4
HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER ITEM
DESCRIPTION OF WORKS
(Con't)
Nota: ITP ini adalah
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
g) Earthing Installation
1. Spesification L-S17- Clause 7.0 2. Earth Resistance ≤ 1 Ohm(Ω)
h) Func tional Test.
Functional and working proper ly c omplied to specification L-S17
TOOLS / EQUIPMENT
STAGE / FREQUENCY
RESPONSIBILITY
Earth Tester
In progress and upon completion of installation. Each Item
C on tr ac to r
Phase sequence tester ( At MSB)
Upon completion of other tests above. Each item.
TNB Representative/ Contractor/ Competent Person
EVIDENCE
REMARKS
S en ar ai S ema k B IL IK SUIS/TRANSFORMER/RMU dan Pengujian
1. The neutral point of the LV system of the transformer shall be solidly earthed. The frameworks and all non carrying metal parts of the transformer shall be earth similarly. 2. The copper tape/bar with dimension not less than 25mm x 6 mm shall be installed around 4 walls of the transformer room at a height of 300mm from finished floor level and shall be bolted to the frame earthing terminal of the transformer. 3. The neutral earthing and frame earthing of the transformer shall be separately connected to its own group of earth electrodes. 4. The neutral earthing & frame earthing shall be connected to its electrodes by means of green pvc insulated copper cable.
(i) USPM/P/CPS (ii) Borang JKR.PK(0).04SKE.6A(Pengesahan PentaulihanPemasangan Elektrik)
Warranty Letter
untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
186
INSPECTION AND TESTING PLAN - VERSION 2
HIGH TENSION SYSTEM : HT SWITCHGEAR WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
HIGH TENSION SYSTEM : HT SWITCHGEAR ITEM
1.
Nota: ITP ini
DESCRIPTION OF WORKS
11 kV Switchgear
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
TOOLS /
STAGE /
RESPONSIBILITY
EVIDENCE
EQUIPMENT
FREQUENCY
1. Material submission approval
1. Contract Document. 2. Shop Drawing. 3. Technical Submittal (i.e : catalogue, brand & model).
N/A
Prior to manufacture of switchgear / Once for each type of material
Contractor
JKR.PK(O).04-5 (Borang Pemeriksaan Mockup/bahan)
2. Factory Acceptance test for 11kV Switchgear.
1. Manufacturer's Specification. 2. Design Requirement. 3. Specification (L-S15). 4. TNB requirement Calibration cert
N/ A
P rior to de li very to si te. / Upon completion of manufacturing.
Con trac to r
J KR .P K( O). 04-S KE .2B (Borang Pemeriksaan/Ujian Alatan Di Kilang) Test Report
3. Material o n site inspection
To confirm with material s ubmisson as per approved
N/A
Upon material delivered at project site/Once for each material / delivery
Contractor / SO rep
4. Switch Room Requirement.
1. Specification (L-S15).
N/A
Upon completion of the room. / Once for each room
Con trac to r
5. Switchgear Installation.
1. Approved Shop Drawing 2. Approved Method Statement 3. Specification (L-S15).
N/A
In-progress and upon completion of installation. / Once for each installation
Contractor/Competant person
Senarai Semak PANEL SUIS
6. Earthing Installation.
1. Approved Shopdrawing 2. Specification (L-S15). 3. Resistance ˂ 1 ohm
E art h T es ter
I n-pr ogr es s an d up on completion of installation. / Once for each installation
Contractor/Competant person
Senarai Semak BILIK SUIS/TRANSFORMER/RMU dan Pengujian
7. P rotective Relay Test.
1. Manufac turer's Specification. 2. Specification (L-S15) 3. Functioning
Measuring Devices
Prior to energizing. / During Testing & Commisioning.
Contractor/Competant person
Senarai Semak PENGUJIAN
8. Insulation Resistance Test : a) Circuit Breaker b) Current Transformer c) Voltage/ Potential Transformer
1. Manufacturer's Specification. 2. Specification (L-S15) 3. Functioning
Insula tion Tester
Prior to energizin g. / During Testing & Commisioning.
Contractor/Competant person
Senarai Semak PENGUJIAN
9. Pressure Test. a) Circuit Breaker b) Voltage Transformer
1. Manufacturer's Specification. 2. Specification (L-S15) 3. Functioning
Power Frequency Test Set
Prior to energizing. / During Testing & Commisioning.
Contractor/Competant person
Senarai Semak PENGUJIAN
REMARKS
JKR.PK(O).04-SKE.2A (BorangPengesahan Penerimaan Bahan)
S enar ai S emak B ILI K SUIS/TRANSFORMER/RMU
adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
187
INSPECTION AND TESTING PLAN - VERSION 2
HIGH TENSION SYSTEM : HT SWITCHGEAR WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
HIGH TENSION SYSTEM : HT SWITCHGEAR ITEM
DESCRIPTION OF WORKS
(Con't)
2 11 kV Cable
Nota: ITP ini
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
TOOLS /
STAGE /
RESPONSIBILITY
EVIDENCE
EQUIPMENT
FREQUENCY
10. Ratio Test : a) Current Transformer b)Voltage/ Potential Transformer
1. Manufacturer's Specification. 2. Specification (L-S15) 3. Functioning
1.CurrentInjection Set 2. Voltage Injection Set
Prior to energizing. / During Testing & Commisioning.
Contractor/Competant person
Senarai Semak PENGUJIAN
Dielectric and Power Frequency Voltage Test :
1. Manufacturer's Specification. 2. Specification (L-S15) 3. Functioning
1. Insulation Tester 2. Power Frequency test set
11. Funtional Test : a) VCB Auxiliary Relay,Mechanical ,Elektrical function b) Heater Circuit, indicators lightVoltage/ Potential Transformer
Functional
N/A
Upon completion of other test above. / During Testing & Commisioning.
Contractor/Competant person
Senarai Semak PENGUJIAN
1. Material submission approval
1. Contract Document. 2. JMAL 3. Technical Submittal (i.e : catalogue, brand & model).
N/ A
P rio r t o d el iv er y t o s it e. / Onc e for each type of material
Contractor
2. Mat er ial on sit e i ns pec tio n
1 . Man uf ac ture r' s S pe cif ic at io n. 2. Design Requirement. 3. Specification (L-S13).
N/A
Upon delivery at site. / Onc e for each material / delivery
Contractor / SO rep
3. Cable installation
1. Approved Method Statement 2. Specification (L-S13)
N/A
In-progress and upon completion of installation. / Once for each installation
Contractor/Competant person
Senarai Semak KABEL BAWAH TANAH VOLTAN TINGGI
4. Continuity Test
1. Approved Method Statement 2. Specification (L-S13)
Upon Completion of cable installation / Once for each cable
Contractor/Competant person
Senarai Semak PENGUJIAN
5. Insulation Resistance Test
Resistance
Insulation Tester
Upon Completion of continuity test / Once for each cable
Contractor/Competant person
Senarai Semak PENGUJIAN
6. Phase Sequence test
Phase sequence terminated correctly
Phase sequence tester
Upon Completion of insulation test / Once for each cable
Contractor/Competant person
Senarai Semak PENGUJIAN
7. D.C test
Phase sequence terminated correctly
Phase sequence tester
Upon Completion of above test / Once for each cable
Contractor/Competant person
Senarai Semak PENGUJIAN
REMARKS
JKR.PK(O).04-5 (Borang Pemeriksaan Mockup)
JKR.PK(O).04-SKE.2A (BorangPengesahan Penerimaan Bahan)
adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
188
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNAL LIGHT WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
TRAFFIC SIGNAL LIGHT : TRAFFIC SIGNAL LIGHT ITEM
1
DESCRIPTION OF WORKS
T ra ff ic S ig na l C on tr ol le r
2
Underground Cable Refer ITP 11.1.2
3
Colu mn (c/w concrete footin g) Refer ITP 11.1.5
4
Signal Head
Nota: ITP ini
POINT OF INSPECTION / TEST
S ub mi ss io n o f m at er ia l l is t / b ra nd s f or a pp ro va l
STANDARD / REQUIREMENT
Factory Acceptance Test 1. Visual Inspection. 2. Functional test. 3. Routine test.
1. App roved shop drawing. 2. Technical Submittal (Catalogue,Brand & Model) 3. Contract Document. 4. Specifications (JKR/SPJ/2008-S8).
Material on site inspection.
To conform as per approved material / FAT.
Inspection of Installation 1. Installation / Safety Aspect 2. Electrical Testing 3. Functional Safety Testing 4. Labelling / Circuit Tagging
1. Approved shop drawing. 2. Specifications (JKR/SPJ/2008-S8). 3. NTJ dan ATJ 13/87
Submission of material list / brands for approval
TOOLS / EQUIPMENT
1 . C on tr ac t D oc um en t. 2. Specifications (JKR/SPJ/2008-S8). 3. Approved shop drawing
1. Contract Document. 2. Specifications (JKR/SPJ/2008-S8). 3. Approved shop drawing
Factory Acceptance Test 1. Visual Inspection. 2. Functional test.
1. App roved shop drawing. 2. Technical Submittal (Catalogue,Brand & Model) 3. Contract Document. 4. Specifications (JKR/SPJ/2008-S8).
Material on site inspection.
To conform as per approved material.
Inspection of Installation 1. Visual Inspection.
1. App roved shop drawing. 2. Technical Submittal (Catalogue,Brand & Model) 3. Contract Document. 4. Specifications (JKR/SPJ/2008-S8). 5. NTJ & ATJ 13-87
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
S TA GE / F RE QU EN CY
B ef ore f ab ric at ion at f ac to ry
Measuring devices. Approved of Fabrication/Shop Drawing
Upon delivery at site. Once for each delivery.
Measuring devices. In-progress and upon completion of installation. Once upon completion.
N /A
B ef or e m at er ia l d el iv er y a t site.
Measuring devices. Approved of Fabrication/Shop Drawing
N/A
Upon delivery at site. Once for each delivery.
Measuring devices. In-progress and upon completion of installation. Once upon completion.
R ES PO NS IB IL IT Y
EVIDENCE
Co nt ra ct or
J KR .P K(O ). 04-5 (BorangKelulusan Bahan/Pemeriksaan Mock-up)
C on tr ac to r
1 .J KR .P K( O) .0 4- SK E. 2B (Borang Pemeriksaan/Ujian Alatan Di Kilang). 2.Senarai Semak Pemeriksaan Lampu Isyarat 3. Test report
Contractor/ SO Rep
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
Contractor/ SO Rep
1. JKR.PK(O).04-SKE.4A (Borang Pemeriksaan Pemasangan) 2.Senarai Semak Pemeriksaan Lampu Isyarat
Co nt ra ct or
J KR .P K(O ). 04-5 (BorangKelulusan Bahan/Pemeriksaan Mock-up)
Contractor/ SO Rep
1.JKR.PK(O).04-SKE.2B (Borang Pemeriksaan/Ujian Alatan Di Kilang). 2.Senarai Semak Traffic Signal Light 3. Test report
Contractor/ SO Rep
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
Contractor/ SO Rep
1. JKR.PK(O).04-SKE.4A (Borang Pemeriksaan Pemasangan) 2.Senarai Semak Pengujian Lampu Isyarat.
REMARKS
189
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNAL LIGHT WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
TRAFFIC SIGNAL LIGHT : TRAFFIC SIGNAL LIGHT ITEM
DESCRIPTION OF WORKS
POINT OF INSPECTION / TEST
STANDARD / REQUIREMENT
5
Cable Termination
Inspection of Installation.
1. Approved Shop Drawing. 2. Specification (LS-3 & JKR/SPJ/2008-S8 ).
6
Vehicle Detector
S ubmission of material list / brands / sample for approval
1. Contract. 2. Drawings. 3..Specifications (JKR/SPJ/2008-S8).
M at er ia l on sit e i ns pec tio n.
To c onf or m a s per app rov ed mat eria l.
Inspection of Installation.
1. Approved Shop Drawing. 2. Specification (JKR/SPJ/2008-S8).
(Type 1 : Induction Loop Cable Type 2 : IRF (Infrared) Type 3 : Camera Type 4 : Wireless etc)
TOOLS / EQUIPMENT
N/A
S TA GE / F RE QU EN CY
In-progress of installation.
Measuring devices. Before material delivery at site. Once for each material.
M eas uri ng d ev ic es . U po n de liv ery at si te. On ce for each delivery.
N/A
In-progress and upon completion of installation. Once for each zone / section.
7
Cable & Detector Pit Refer ITP 11.1.5
Inspection of Installation.
To c onform a s per a pproved d rawing a nd specification.
Measuring devices. Pre-cast concreting
8
Earthing system
Submission of material list / brands for approval
1. Contract. 2. J-MAL. 3. Specifications (L-S1 etc.).
Measuring devices. Before material delivery at site. Once for each material.
M at er ia l on sit e i ns pec tio n.
To c onf or m a s per app rov ed mat eria l.
Installation of earthing system.
1. Approved Shop Drawing. 2. Specification (L-S1 etc). 3. R < 1 Ohm
M eas uri ng d ev ic es . U po n de liv ery at si te. On ce for each delivery.
Earth Tester.
In-progress and upon completion of installation. Once for each zone / section.
R ES PO NS IB IL IT Y
Contractor/ SO Rep
Co nt ra ct or
EVIDENCE
J KR .P K(O ). 04-5 (Borang Pemeriksaan Mockup)
Contractor/ SO Rep
JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan)
Contractor/ SO Rep
Senarai Semak Pemeriksaan Lampu Isyarat.
Contractor/ SO Rep
Senarai Semak Pengujian Lampu Isyarat.
Co nt ra ct or
Contractor/ SO Rep
C on tr ac to r
REMARKS
N/A
J KR .P K(O ). 04-5 (Borang Pemeriksaan Mockup) JKR.PK(O).04-SKE.2A (Borang Pengesahan Penerimaan Bahan) J KR .P K( 0) .O 4- SK E. 3B (Pemasangan Elektrod Bumi) JKR.EER (Record of Earth Electrode Resistance Test) JKR.PK(O).04-4 (Borang Kalibrasi Peralatan) c/w Calibration Cert.)
Nota: ITP ini
adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
190
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNAL LIGHT WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 1 DARI 2
LAMPIRAN 1 : SENARAI SEMAK PEMERIKSAAN LAMPU ISYARAT
BIL
PERKARA
1
VISUAL INSPECTION : -
1.1
Traffic Light Controller
Lampu Isyarat YA TIDAK
Tindakan / Catatan
1.1.1 Microprocessor-based 1.1.2 Class IP 55 (MS IEC 60529) Coated with epoxy dry-powder and oven baked semi-gloss enamel grey
1.1.3 (except for stainless steel) 1.1.4 Log Book
1.1.5 Lock & 2 Sets of Key (each controller) 1.1.6 Anti Vandalism Features (2 set of steel bar, handle with lock etc) 1.1.7 Vantilation louvre c/w wire mesh and protection 1.1.8 Anti Sticker Paint 1.1.9 Color Code : a. Golden Yellow Stripe (No. 356 BS 381C) b. Black (BS 873)
1.1.10 Labelling sticker as per approved shop drawing 1.2 Signal Head 1.2.1 Nominal diameter 300mm 1.2.2 Three optical arranged vertically 1.2.3 Arrangment (upper = red, middle = amber, lower = green) 1.2.4 Type A visor 1.2.5 Height : a. Post-Mounted = Centre of green optical shall be 2.5m above the carriageway b.
1.3 1.3.1 1.3.2 1.3.3 1.3.4 1.3.5 1.3.6 1.4
Overhead = lowest point of signal shall be not less than 5.5m or more than 6.5m above the carriageway
Column Nominal diameter 100mm Twin service door Information Board "Aduan Kerosakan" as per approved shop drawing Alternate orange and black band Anti-vandalism locking device Double slot hinged service door Vehicle Detector
1.4.1 Type of vehicle detector as approved shop drawing
1.5
Cable and Detector Pit
1.5.1 Heavy duty pre-cast concrete pit 1.5.2 Cable pit size = 450mm (L) X 450mm (W) X 450mm (H) 1.5.3 Detector pit size = 300mm (L) X 300mm (W)
1.6
Others
1.6.1 Plinth dimension 1.6.2 Facility Switch 1.6.3 Fittngs (Lamp, Switch Socket Outlet, Heater efc ) 1.6.4 Meter TNB 1.6.5 Maintenance Tool (If Any)
Nota:
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
191
INSPECTION AND TESTING PLAN - VERSION 2
TRAFFIC SIGNAL LIGHT WORKS
KERJA ELEKTRIK
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK
HELAIAN 2 DARI 2
LAMPIRAN 1 : SENARAI SEMAK PEMERIKSAAN LAMPU ISYARAT
BIL
Lampu Isyarat YA TIDAK
PERKARA
Tindakan / Catatan
FUNCTIONAL INSPECTION :-
2 2.1
Green Conflict
2.2
Double lamp conflict
2.3
Sequence of phasing
2.4
Time settings
2.5
Pedestrian Facilities Test
2.6
Buzzer
2.7
Push Button
2.8
Flashing Rate
2.9
Vehicle Detector Test
2.10
Green Wave (Integration of traffic light controller between two or more junction)
2.11
Auto Reclosure RCCB
2.12
Earthing Test
ULASAN :
TERIMA / TIDAK TERIMA DISEMAK OLEH : ( K o n t r a k t o r )
DISAHKAN OLEH : ( P en g u r u s P r o j e k )
Tandatangan :
Tandatangan :
Nama Pegawai :
Nama Pegawai :
Tarikh:
Tarikh:
Nota:
ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan